PlanningRegister.ie
Observation pack · Galway County Council

Cloonluane , Renvyle , Co. Galway

To construct a new dwelling house, domestic garage and a new effluent treatment system including all associated site works

Observations close 17 Dec 2026 29 days left
5 weeks from receipt (received 12 Nov 2026) · s.34 Planning and Development Act 2000 · art. 29 Regulations 2001 · fee €20 · council decision due 15 Jan 2027

The application

Reference
2661868 · full record
Authority
Galway County Council
Type
PERMISSION
Status
PRE_VALIDATION
Units
1
Floor area
135 m²
Site area
4,360 m²
Received
12 Nov 2026
Decision due
15 Jan 2027

How to submit an observation

  1. Read the file on the council register.Drawings, planning statement and site notices are at http://www.eplanning.ie/GalwayCC/AppFileRefDetails/2661868/0.
  2. Write your observation.Quote 2661868 at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on.
  3. Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. Galway County Council takes it online with the submission or at the counter.
  4. Submit before 17 Dec 2026.Online through the register above, or in writing to the Planning Department, Galway County Council. The test is the date the authority receives it, not the date you post it.
  5. Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.

Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.

After you submit: keep the acknowledgement. Under the 2024 Act it secures your right to appeal — only the applicant and a person who made a valid observation may bring the council's decision to An Coimisiún Pleanála, within four weeks of the decision. Making a valid observation is also what buys a right of appeal: under s.37(1) of the 2000 Act, only the applicant and a person who made a valid submission or observation to the planning authority may appeal the decision to An Coimisiún Pleanála (within four weeks of the decision). Missing the five-week window closes both doors.

Nearby precedents within 500 m, last 5 years

Decisions

ReferenceDecisionDecidedUnitsDistanceDescription
2661575Conditional6 Nov 20261307 mto construct a new dwelling house and new effluent treatment system including all associated site works
26100Unconditional24 Jun 2026332 mof planning reference 2260925, for change of house plan/design to previously granted planning permission 20/730. Gross floor space of proposed works 180.00sqm
2561574Refused16 Dec 20251165 mfor construction of a new house, effluent treatment system and associated works. A Natura Impact Statement will be submitted to the Planning Authority with this application
2460068Conditional1 Oct 20241491 mto construct a new dwelling house, new domestic garage & new effluent treatment system including associated site works. Gross floor space of proposed works: 240.3 sqm (house) & 34 sqm (garage)
2361078Refused28 Jun 20241165 mfor construction of a new house, effluent treatment unit & associated works. Roof ridge 6.0m above FFL. A Natura Impact Statement will be submitted with this application
2360510Conditional5 Jun 20241389 mFor development consisting of refurbishment and upgrading works [including (where necessary) replacement of existing poles along the existing overhead electricity line, minor ground works e.g. replacement or installation of stays, and maintenance or improvement works]; and all associated ancillary works including the provision of temporary accessways. Replacement poles will be constructed at, or immediately adjacent to, the existing structures that they will replace. Replacement poles will have a maximum height of 12m above ground; and be similar in appearance to existing poles. Planning permission is sought for a 10 year period. A Natura Impact Statement (NIS) will be submitted to the Planning Authority with the application
2360760Conditional18 Apr 202410 mfor the construction of new dwellinghouse (215.9 sqm), domestic garage (34 sqm), effluent treatment system & associated site works
22920Conditional17 Feb 20231495 mto construct a dwelling house with a wastewater treatment system. Gross floor space of proposed works: 289sqm

What has happened on this file

  • 12 Nov 2026 New application · observations close 17 Dec 2026
  • 12 Nov 2026 Decision

Generated from the Planning Register store; nothing was fetched live for this page. Source: national planning dataset, fetched 17 Nov 2026, 23:00. Not legal advice — confirm the deadline with Galway County Council before relying on it.