PlanningRegister.ie
Observation pack · Kildare County Council

7 Sli na Roigh , Kilcullen Road , Naas

for :(a) RETENTION FOR EXISTING ATTIC FLOOR (SECOND FLOOR OFEXISTING DUPLEX APARTMENT) AS CONSTRUCTED AND ALL ASSOCIATED SITE WORKS

Observations close 8 Oct 2026 window closed
5 weeks from receipt (received 3 Sept 2026) · s.34 Planning and Development Act 2000 · art. 29 Regulations 2001 · fee €20 · council decision due 28 Oct 2026

The five-week window has passed. Late observations are returned unread. If the council has decided, the next door is the appeal window — but under s.37 only the applicant and those who made a valid observation may appeal.

The application

Reference
2660990 · full record
Authority
Kildare County Council
Type
RETENTION
Status
NEW APPLICATION
Applicant
not published by the national dataset — see the council register
Units
1
Floor area
46 m²
Site area
58 m²
Received
3 Sept 2026
We first saw it
18 Sept 2026, 16:04
Decision due
28 Oct 2026
Decision
N/a

The national dataset truncates descriptions (80 characters for DLR, 70 for Fingal) and omits the applicant. The full description and the drawings are on the council register linked in step 1.

How to submit an observation

  1. Read the file on the council register.Drawings, planning statement and site notices are at http://www.eplanning.ie/KildareCC/AppFileRefDetails/2660990/0.
  2. Write your observation.Quote 2660990 at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on.
  3. Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. Kildare County Council takes it online with the submission or at the counter.
  4. Submit before 8 Oct 2026.Online through the register above, or in writing to the Planning Department, Kildare County Council. The test is the date the authority receives it, not the date you post it.
  5. Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.

Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.

After you submit: keep the acknowledgement. Under the 2024 Act it secures your right to appeal — only the applicant and a person who made a valid observation may bring the council's decision to An Coimisiún Pleanála, within four weeks of the decision. Making a valid observation is also what buys a right of appeal: under s.37(1) of the 2000 Act, only the applicant and a person who made a valid submission or observation to the planning authority may appeal the decision to An Coimisiún Pleanála (within four weeks of the decision). Missing the five-week window closes both doors.

What the site is zoned

CodeObjectivePlanIn force
R2
Existing residential
Existing Residential / Infill: To protect and enhance the amenity of established residential communities and promote sustainable intensification.KI-001:LAP:naas-local-area-plan-2021-20271 Dec 2021 → 24 Jan 2028

An application that accords with the zoning objective is hard to resist on principle; one that does not may be a material contravention, which the council can only grant by the s.34(6) procedure with its own notice and window.

Source: KILDARE KI-001:LAP:naas-local-area-plan-2021-2027 · fetched 27 Sept 2026, 19:37
SourceLicenceFetchedLink
KILDARE KI-001:LAP:naas-local-area-plan-2021-2027—27 Sept 2026, 19:37open

Designations on or near the site

  • Radon risk area × 1
    About 1 in 10 homes in this area is likely to have high radon levels

Nearby precedents within 500 m, last 5 years

Decisions

ReferenceDecisionDecidedUnitsDistanceDescription
2660226Conditional10 Jun 20260324 m(i) to demolish the existing single storey Cold Room Lean-to building on the Southern side of the existing Supermarket building, (ii) to construct a single storey Extension on the Southern side of the existing Supermarket building and amalgamate the proposed Extension with the existing SuperValu Supermarket Unit (iii) to revise the Car Park layout and reduce the ground level of the Southern section of the existing Car Park and associated external signage and site works
2561193Conditional2 Jun 20260496 ma change of use and internal alterations to a vacant building. The proposed development includes change of use from a permitted financial institution use at ground floor level to a proposed mixed-use building, accommodating of 1 no. office unit (measuring c. 235 sq.m) at ground floor level and 4 no. apartments consisting of 3 no. 2 bed apartments and 1 no. 1 bed apartment located at first and second floors. The proposed development also includes for all associated site development works, communal open space, bin & bike storage etc. on an overall site area of c. 0.04 hectares. Revised by Significant Further Information which consists of: a change of use and internal alterations to a vacant building located at No.s 24-25 South Main Street, Naas, County Kildare. The proposed development includes a change of use from a permitted financial institution use at ground floor level to a proposed mixed-use building, accommodating of 1 no. office unit (measuring c. 235 sq.m) at ground floor level and 4 no. apartments consisting of 3 no. 2 bed apartments and 1 no. 1 bed apartment located at first and second floors. The proposed development also consists of the removal of the existing black stone shopfront and replacement of same with a traditional timber shop front at ground floor level facing onto South Main Street, as well as all associated site development works, communal open space, bin & bike storage etc., on an overall site area of c. 0.04 hectares
2660016Conditional6 Mar 20260442 mThe proposed development consists of the following: • Construction of a new 120m x 74m all-weather pitch including storage areas to replace an existing grass pitch and ball courts including new 2.4m high perimeter fencing, 6m high ball stop netting and up to 12m high ball stop netting, • Removal of basketball courts in order to facilitate proposed pitch, • 6 no. new 18.3m high lighting columns around the new pitch and 1 no. new 6m high lighting column to the new car parking area, • Installation of a new 45kVA diesel generator in a new compound with 2.4m high perimeter fencing, • New hard standing car parking spaces, • Erection of advertising signs around the perimeter of the new pitch, • Realignment of a portion of the existing emergency access road, • Retention and relocation of existing storage containers on the site, • All associated site development
2561497Refused22 Feb 20260459 m(i) demolition of existing vacant part single, part two storey structure on-site (972sq.m), previously in use as a public house; (ii) careful removal of the existing stone wall along the side (western) boundary of the site to be reused within the ground floor of the proposed development; (iii) construction of a mixed-use development comprising 4 no. commercial units, resident amenity room and a creche at ground floor level. Provision of 76 no. residential units (33 no. one- bedroom units, 39 no. two-bedroom units and 4 no. three-bedroom units) at upper floor levels in a part four, part five-storey building. Each apartment will be provided with private amenity space in the form of a balcony/terrace space and communal open space will be provided at first floor level to the east of the site. A total of 182 no. bicycle parking spaces are proposed to serve the development comprising 123 no. resident, 38 no. visitor, 12 no. commercial and 6 no. creche spaces. A total of 54 no. car parking spaces are proposed to serve the development comprising 41 no. resident, 2 no. visitor, 3 no. accessible, 3 no. commercial, 4 no. club car and 1 no. creche spaces. A total of 4 no. motorbike parking spaces. Provision of 2 no. set-down areas for servicing and deliveries at surface level. The proposed development also includes; (iv) all associated site and infrastructural works, including foul and surface water drainage, landscaping, plant areas, site lighting, bin storage and signage necessary to facilitate the development
2560624Conditional28 Nov 20250323 mfor an extension comprising a mixed use development of office & apartments. The development will consist of: A) Demolition of Single Storey House (73m2) at The Cottage, Fairgreen, Naas Co. Kildare (W91 NXR7); B) Partial demolition of existing single storey extension to rear and Internal modifications and alterations to existing offices at No. 3 Highland View Terrace C) Construction of a two storey Dormer extension on north side of the existing offices facing the main street with dormer style windows to pitched roofs and comprises of proposed office accommodation at ground, first & second floor level (Total floor area= 250m2), two storey covered stairway and walkway in centre of proposed building and a two storey Dormer /three-storey building to rear comprising office accommodation at ground floor level (floor area = 100m2) and 1 no. 2-bedroom apartment on first & second floor levels (floor area = 92m2 each apartment). Each apartment will have private amenity space provided by an inset balcony. D) Secure cycle parking and bin storage will be located to the rear of the mixed-use development; new railings and pedestrian gate to match existing at front boundary, with hard landscaping area to front set-back; hard & soft landscaping to rear courtyards & open spaces. E) Ancillary site development works that include the installation of pipes & connections to the existing public sewage system & water supply, new soakaway and all associated works. Revised by Significant Further Information which consists of: revised site layout, revisions to building line to front and rear, revised courtyard and communal space arrangements, details of proposed finishes, landscape designs, submission of additional reports including bat survey, tree survey and sunlight analysis and construction management plan
2560192Refused13 Nov 20251424 mfor demolition of existing single storey commercial unit with permission to construct a new two storey with part three storey (to rear) building to be used as a 7 bedroom guesthouse and all associated site works
2560691Conditional11 Aug 2025132 mfor existing attic floor (second floor of existing duplex apartment) as constructed and all associated site works
2560514Conditional8 Jul 20250280 mfor a) new canopy over front door and b) pedestrian gateway to side boundary wall along with all associated site development and facilitating works

Appeals

ACP caseTypeOutcomeDecidedDistance
500437—Refused24 Aug 2026424 m
501038—Refused21 Jul 2026458 m
316372—Granted with conditions13 Mar 2025387 m
320309—open19 Jul 20240 m
320344—open19 Jul 20240 m
318599—Refused1 Jul 2024323 m
316728—Other1 Nov 20230 m
316726—Other1 Nov 20230 m

If neighbours here have appealed before and lost, the inspector's report on that case is the single most useful thing to read.

What has happened on this file

  • 3 Sept 2026 New application · observations close 8 Oct 2026
  • 3 Sept 2026 Decision

Generated from the Planning Register store; nothing was fetched live for this page. Source: national planning dataset, fetched 18 Sept 2026, 16:04. Not legal advice — confirm the deadline with Kildare County Council before relying on it.