5 weeks from receipt (received 30 Sept 2026) · s.34 Planning and Development Act 2000 · art. 29 Regulations 2001 · fee €20 · council decision due 24 Nov 2026

The application

Reference
2661084 · full record
Authority
Kildare County Council
Type
RETENTION
Status
WITHDRAWN
Applicant
not published by the national dataset — see the council register
Units
1
Floor area
118 m²
Site area
1,785 m²
Received
30 Sept 2026
We first saw it
14 Oct 2026, 01:45
Decision due
24 Nov 2026
Decision
N/a

The national dataset truncates descriptions (80 characters for DLR, 70 for Fingal) and omits the applicant. The full description and the drawings are on the council register linked in step 1.

How to submit an observation

  1. Read the file on the council register.Drawings, planning statement and site notices are at http://www.eplanning.ie/KildareCC/AppFileRefDetails/2661084/0.
  2. Write your observation.Quote 2661084 at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on.
  3. Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. Kildare County Council takes it online with the submission or at the counter.
  4. Submit before 4 Nov 2026.Online through the register above, or in writing to the Planning Department, Kildare County Council. The test is the date the authority receives it, not the date you post it.
  5. Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.

Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.

After you submit: keep the acknowledgement. Under the 2024 Act it secures your right to appeal — only the applicant and a person who made a valid observation may bring the council's decision to An Coimisiún Pleanála, within four weeks of the decision. Making a valid observation is also what buys a right of appeal: under s.37(1) of the 2000 Act, only the applicant and a person who made a valid submission or observation to the planning authority may appeal the decision to An Coimisiún Pleanála (within four weeks of the decision). Missing the five-week window closes both doors.

What the site is zoned

No current zoning polygon covers this site in the store.

Designations on or near the site

  • Radon risk area × 1
    About 1 in 10 homes in this area is likely to have high radon levels

Nearby precedents within 500 m, last 5 years

Decisions

ReferenceDecisionDecidedUnitsDistanceDescription
2660109Conditional1 Apr 20260490 mfor minor modifications to previously permitted side extension to existing house as constructed, retention permission for side vehicular entrance access for accessible use as constructed and all associated site works
2360157Conditional17 Oct 2023069 mfor change of house type from previously approved bungalow under planning reference 20/629 to new single storey bungalow and all associated site works
22775Refused19 Jun 202310 mto remove existing prefabricated living unit and septic tank and replace with Bungalow, Oakstown waste water treatment system and percolation area and all associated works and services
221419Conditional25 Jan 20230490 mthe construction of a single storey side extension to existing semi detached dormer bungalow, installation of new side window to existing house at ground floor level, permission for new side vehicular entrance access for accessible use and all associated site works
22509Conditional29 Nov 20220418 msought to erect a gas operated crematorium facility to include: (a) Crematorium with administration office; (b) Gas storage compound; (c) Wastewater treatment system with raised polishing filter; (d) Access road from the existing Wellbrook embalming centre and chapel of rest with extensive landscaping and screening and all associated site works. Revised by Significant Further Information which consists of (1) change site levels to mitigate flood risk and (2) to connect and discharge to the public foul sewer
22375Refused26 May 20220331 m(Extension of Duration for Previous Planning File 17/300) to raise 0.934 Ha of lands by 1.5m approximately using subsoil and topsoil only

Appeals

ACP caseTypeOutcomeDecidedDistance
315458—Granted with conditions17 Apr 2024417 m

If neighbours here have appealed before and lost, the inspector's report on that case is the single most useful thing to read.

What has happened on this file

  • 30 Sept 2026 New application · observations close 4 Nov 2026
  • 30 Sept 2026 Decision

Generated from the Planning Register store; nothing was fetched live for this page. Source: national planning dataset, fetched 14 Oct 2026, 01:45. Not legal advice — confirm the deadline with Kildare County Council before relying on it.