A bungalow type dwelling, detached domestic garage, proprietary effluent treatment system, recessed vehicular entrance, American barn with dungstead & effluent holding tank, to be accessed off an existing recessed vehicular entrance/egress point & access avenue, and all associated ancillary site works

Observations close 14 Dec 2026 23 days left
5 weeks from receipt (received 9 Nov 2026) · s.34 Planning and Development Act 2000 · art. 29 Regulations 2001 · fee €20 · council decision due 12 Jan 2027

The application

Reference
2661234 · full record
Authority
Kildare County Council
Type
PERMISSION
Status
NEW APPLICATION
Units
1
Floor area
154 m²
Site area
3,727 m²
Received
9 Nov 2026
Decision due
12 Jan 2027

How to submit an observation

  1. Read the file on the council register.Drawings, planning statement and site notices are at http://www.eplanning.ie/KildareCC/AppFileRefDetails/2661234/0.
  2. Write your observation.Quote 2661234 at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on.
  3. Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. Kildare County Council takes it online with the submission or at the counter.
  4. Submit before 14 Dec 2026.Online through the register above, or in writing to the Planning Department, Kildare County Council. The test is the date the authority receives it, not the date you post it.
  5. Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.

Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.

After you submit: keep the acknowledgement. Under the 2024 Act it secures your right to appeal — only the applicant and a person who made a valid observation may bring the council's decision to An Coimisiún Pleanála, within four weeks of the decision. Making a valid observation is also what buys a right of appeal: under s.37(1) of the 2000 Act, only the applicant and a person who made a valid submission or observation to the planning authority may appeal the decision to An Coimisiún Pleanála (within four weeks of the decision). Missing the five-week window closes both doors.

Nearby precedents within 500 m, last 5 years

Decisions

ReferenceDecisionDecidedDistanceDescription
2560397Conditional18 Aug 2025426 mfor (A) Temporary retention for a period of 2 years sought for the existing mobile home on site. (B) refurbishment of existing derelict cottage complete with new slate roof and the restoration of existing stone walls and the insertion of new window fenestration to front (south east) elevation, (C) single storey extension to side (north east) elevation and link roof to rear (north west) elevation, (D) the installation of an Oakstown BAF wastewater treatment plant with polishing filter percolation area and (E) upgrading of existing agricultural entrance to a new vehicular recessed entrance gate and piers and all associated site works. Revised by Significant Further Information which consists of: The garage is now part of the application
22131Conditional28 Mar 2022215 mretaining alterations to garage/store block granted permission under PI. Ref. 03/1537, including installation of 5 No. rooflights to side and rear, raising of ridge level for storage accommodation along with all associated ancillary site-works
211694Conditional27 Jan 2022119 mThe development will consist of the construction of a three car detached garage with a plant room to the side and attic storage over, all to the side of the existing detached dwelling.

Appeals

ACP caseTypeOutcomeDecidedDistance
311551Refused9 Jun 202366 m

If neighbours here have appealed before and lost, the inspector's report on that case is the single most useful thing to read.

What has happened on this file

  • 9 Nov 2026 New application · observations close 14 Dec 2026
  • 9 Nov 2026 Decision