PlanningRegister.ie
Observation pack · Kilkenny County Council

Jerpoint West , Thomastown , County Kilkenny

for development consisting of a roadside boundary wall including field entrance piers and gates, single storey agricultural storage shed and associated site works

Observations close 21 Oct 2026 24 days left
5 weeks from receipt (received 16 Sept 2026) · s.34 Planning and Development Act 2000 · art. 29 Regulations 2001 · fee €20 · council decision due 10 Nov 2026

The application

Reference
2660598 · full record
Authority
Kilkenny County Council
Type
RETENTION
Status
NEW APPLICATION
Applicant
not published by the national dataset — see the council register
Units
0
Floor area
—
Site area
6,330 m²
Received
16 Sept 2026
We first saw it
22 Sept 2026, 16:10
Decision due
10 Nov 2026
Decision
N/a

The national dataset truncates descriptions (80 characters for DLR, 70 for Fingal) and omits the applicant. The full description and the drawings are on the council register linked in step 1.

How to submit an observation

  1. Read the file on the council register.Drawings, planning statement and site notices are at http://www.eplanning.ie/KilkennyCC/AppFileRefDetails/2660598/0.
  2. Write your observation.Quote 2660598 at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on.
  3. Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. Kilkenny County Council takes it online with the submission or at the counter.
  4. Submit before 21 Oct 2026.Online through the register above, or in writing to the Planning Department, Kilkenny County Council. The test is the date the authority receives it, not the date you post it.
  5. Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.

Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.

After you submit: keep the acknowledgement. Under the 2024 Act it secures your right to appeal — only the applicant and a person who made a valid observation may bring the council's decision to An Coimisiún Pleanála, within four weeks of the decision. Making a valid observation is also what buys a right of appeal: under s.37(1) of the 2000 Act, only the applicant and a person who made a valid submission or observation to the planning authority may appeal the decision to An Coimisiún Pleanála (within four weeks of the decision). Missing the five-week window closes both doors.

What the site is zoned

No current zoning polygon covers this site in the store.

Designations on or near the site

  • Radon risk area × 1
    About 1 in 10 homes in this area is likely to have high radon levels

Nearby precedents within 500 m, last 5 years

Decisions

ReferenceDecisionDecidedUnitsDistanceDescription
2660459Refused9 Sept 20261493 mfor 3 serviced sites for dwellings with treatment plants and soil filters, wells, new entrance and all associated site works
2560747Refused26 Jan 20261275 mto construct a new two- bedroom house and all associated site works
2460645Conditional25 Jun 20251238 mfor the following developments at their organic farm, (a) construction of a storey and a half style dwelling house, (b) sewage treatment system, (c) slatted cow shed, (d) tractor/hay shed, (e) garden shed, (f) gravel driveway and all associated site development works
259Refused24 Mar 20251275 mto construct one new two-bedroom house and all associated site works on lands
2460395Conditional3 Oct 20240455 mto construct a single storey extension to the rear (north) of existing dwelling house and all associated site development works
2460173Refused5 Jun 202410 mPERMISSION for a single-storey dwelling house, wastewater treatment system and associated site works
2424Refused18 Apr 20241224 mto construct one new two bedroom house with integrated garage and all associated site works on lands
23203Refused10 Oct 20231224 mto construct 1 new two-bedroom house with integrated garage and all associated site works

Appeals

ACP caseTypeOutcomeDecidedDistance
500806—Refused19 Jun 2026275 m
323102—Granted with conditions27 Mar 2026238 m
322309—Refused21 Jul 2025275 m
319663—Refused8 Nov 2024224 m
320045—Refused5 Nov 20240 m
310149—Granted with conditions24 Jan 202228 m

If neighbours here have appealed before and lost, the inspector's report on that case is the single most useful thing to read.

What has happened on this file

  • 16 Sept 2026 New application · observations close 21 Oct 2026
  • 16 Sept 2026 Decision

Generated from the Planning Register store; nothing was fetched live for this page. Source: national planning dataset, fetched 22 Sept 2026, 16:10. Not legal advice — confirm the deadline with Kilkenny County Council before relying on it.