Kilfera Court , Kilfera , Co. Kilkenny

For development. The development will consist of works to the existing two-storey residential dwelling as follows: 1). The demolition of an existing chimney to the southeast elevation, 2) The construction of single storey extension to the southeast elevation and a dormer window to the front elevation with associated internal modifications, 3) Alterations to all elevations to include externally wrapped insulation and 4) all associated site works to facilitate the development

Observations close 14 Dec 2026 17 days left
5 weeks from receipt (received 9 Nov 2026) · s.34 Planning and Development Act 2000 · art. 29 Regulations 2001 · fee €20 · council decision due 12 Jan 2027

The application

Reference
2660714 · full record
Authority
Kilkenny County Council
Type
PERMISSION
Status
NEW APPLICATION
Site area
3,959 m²
Received
9 Nov 2026
Decision due
12 Jan 2027

How to submit an observation

  1. Read the file on the council register.Drawings, planning statement and site notices are at http://www.eplanning.ie/KilkennyCC/AppFileRefDetails/2660714/0.
  2. Write your observation.Quote 2660714 at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on.
  3. Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. Kilkenny County Council takes it online with the submission or at the counter.
  4. Submit before 14 Dec 2026.Online through the register above, or in writing to the Planning Department, Kilkenny County Council. The test is the date the authority receives it, not the date you post it.
  5. Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.

Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.

After you submit: keep the acknowledgement. Under the 2024 Act it secures your right to appeal — only the applicant and a person who made a valid observation may bring the council's decision to An Coimisiún Pleanála, within four weeks of the decision. Making a valid observation is also what buys a right of appeal: under s.37(1) of the 2000 Act, only the applicant and a person who made a valid submission or observation to the planning authority may appeal the decision to An Coimisiún Pleanála (within four weeks of the decision). Missing the five-week window closes both doors.

Designations on or near the site within 100 m

  • Recorded monument × 1
    R139186

Nearby precedents within 500 m, last 5 years

Decisions

ReferenceDecisionDecidedUnitsDistanceDescription
25124Conditional23 Jun 20261335 mto construct a single storey dwelling, treatment system/percolation area, including all associated site works
2560444Conditional13 Feb 2026123 mfor the importation of approximately 2,350sq.m. of top and subsoil to the existing agricultural field of 1.27 hectares and all associated site and development works
2460334Conditional2 Sept 2024335 m1) Retention permission for the demolition of a single-storey bathroom extension to the rear and construction of a ground floor slab for future extension to the rear, and all associated site & development works at Kilfera, Co. Kilkenny R95 V58H. 2) Planning permission for the renovation of existing single-storey dwelling including new external wall insulation with render finish throughout, additional pitched-roof single-storey extension to the rear, new on-site wastewater treatment system, reconfiguration of front driveway area to facilitate greater vehicular manoeuvrability and all associated site & development works
21851Conditional27 May 2022464 mfor existing holiday cottage to continue as a holiday cottage. This is a Protected Structure Ref. No. 831
21415Conditional6 Dec 2021365 mto demolish an existing extension and porch, to construct a single storey extension to the rear and side of my dwelling, and a waste water treatment system with all associated site works at

What has happened on this file

  • 9 Nov 2026 New application · observations close 14 Dec 2026
  • 9 Nov 2026 Decision