PlanningRegister.ie
Observation pack · Kilkenny County Council

Derrylacky , Mullinavat , Co. Kilkenny

For the erection of a dwelling house, installation of a treatment system and percolation area and all associated site works

Observations close 22 Dec 2026 27 days left
5 weeks from receipt (received 17 Nov 2026) · s.34 Planning and Development Act 2000 · art. 29 Regulations 2001 · fee €20 · council decision due 20 Jan 2027

The application

Reference
2660732 · full record
Authority
Kilkenny County Council
Type
PERMISSION
Status
NEW APPLICATION
Units
1
Floor area
267 m²
Site area
1.17 ha
Received
17 Nov 2026
Decision due
20 Jan 2027

How to submit an observation

  1. Read the file on the council register.Drawings, planning statement and site notices are at http://www.eplanning.ie/KilkennyCC/AppFileRefDetails/2660732/0.
  2. Write your observation.Quote 2660732 at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on.
  3. Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. Kilkenny County Council takes it online with the submission or at the counter.
  4. Submit before 22 Dec 2026.Online through the register above, or in writing to the Planning Department, Kilkenny County Council. The test is the date the authority receives it, not the date you post it.
  5. Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.

Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.

After you submit: keep the acknowledgement. Under the 2024 Act it secures your right to appeal — only the applicant and a person who made a valid observation may bring the council's decision to An Coimisiún Pleanála, within four weeks of the decision. Making a valid observation is also what buys a right of appeal: under s.37(1) of the 2000 Act, only the applicant and a person who made a valid submission or observation to the planning authority may appeal the decision to An Coimisiún Pleanála (within four weeks of the decision). Missing the five-week window closes both doors.

Designations on or near the site within 100 m

  • Radon risk area × 1
    About 1 in 10 homes in this area is likely to have high radon levels

Nearby precedents within 500 m, last 5 years

Decisions

ReferenceDecisionDecidedUnitsDistanceDescription
2560724Conditional13 Feb 20261146 merection of a new 4-bedroom, single storey dwelling house, new bore hole well, new wastewater treatment unit and percolation area and all associated site works
2560802Conditional11 Feb 20261423 mfor the construction of fully serviced dwelling and associated works situated
2560551Refused20 Oct 202579 mfor 1) Agricultural shed for potato storaqe & distribution 316m2 2) Cabin office 48m2 3) Six number containers for storaqe of potatoes 4) Concrete hard standinq area 552m2 5) New aqricultural access to premises and all associated site works.
2360066Conditional19 Apr 20231497 mto build a single storey dwelling, garage, septic tank with effluent treatment system, site entrance and associated site works
22743Refused19 Jan 20231497 mTo build a single storey dwelling, garage, septic tank with effluent treatment system, site entrance and associated site works .
10309306Conditional29 Sept 2022199 mSTRATEGIC INFRASTRUCTURE DEVELOPMENT Aplication made to An Bord Pleanala for: The construction of 21 wind turbines and ancillary works
22234Conditional18 Jul 2022412 mto retain indefinitely the dormer extension and external design changes to my existing dwelling and all associated works

Appeals

ACP caseTypeOutcomeDecidedDistance
313950Other9 Sept 2024297 m
309306Granted with conditions26 Sept 2022189 m

If neighbours here have appealed before and lost, the inspector's report on that case is the single most useful thing to read.

What has happened on this file

  • 17 Nov 2026 New application · observations close 22 Dec 2026
  • 17 Nov 2026 Decision

Generated from the Planning Register store; nothing was fetched live for this page. Source: national planning dataset, fetched 24 Nov 2026, 23:00. Not legal advice — confirm the deadline with Kilkenny County Council before relying on it.