Ballybrittas , Co. Laois , Co. Laois
1. Removal of existing scrub and failed plantation and the sequential raising of ground levels across the proposed development site by an average of 1.25m using imported soil and stone comprising both waste and (non-waste) byproduct; 2. Development and operation of a construction and demolition (C&D) waste recovery facility at a new (unpaved) hardstanding area to the north-west of the site. The recovery facility provides for the processing / recycling of inert C&D waste (principally solid / reinforced concrete, bricks, ceramics and solid bituminous waste mixtures) using mobile crushing and screening equipment to produce recycled (secondary) aggregate and the use of surrounding hardstanding areas for the external handling and storage of both unprocessed C&D wastes and recycled aggregates. 3. The construction of a portal frame building with roof-mounted solar panels (3,058sqm), (which will accommodate a workshop, offices and staff welfare facilities) with external provision of staff and visitor car-parking and bicycle parking on a concrete paved area to the south-west of the site; 4. Upgrading of the existing site entrance from the R445 Regional Road and internal access road into the site to provide a secure access point and provision of a weighbridge / site office, and wheelwash to facilitate the proposed development; 5. The provision of surface water management infrastructure for the office and concrete paved area to the south-west of the site, including silt traps and hydrocarbon interceptor (Full flow treatment system) attenuation pond for storm runoff, flow control device from Attenuation Pond and and all associated drainage works. 6. Provision of a foul wastewater treatment system at the site to treat all wastewater(s); 7. Landscaping including boundary treatment and fencing and internal hard and soft landscaping at the hardstand areas and proposed building. 8. All ancillary site development works to facilitate the proposed development, including water services, utilities, lighting and other associated infrastructure works and services. A Natura Impact Statement (NIS) will also be submitted to the planning authority with the planning application.
The application
- Reference
- 2660583 · full record
- Authority
- Laois County Council
- Type
- PERMISSION
- Status
- INCOMPLETED APPLICATION
- Applicant
- not published by the national dataset — see the council register
- Units
- 0
- Floor area
- —
- Site area
- 11.53 ha
- Received
- 27 Aug 2026
- We first saw it
- 18 Sept 2026, 15:44
- Decision due
- —
- Decision
- N/a
The national dataset truncates descriptions (80 characters for DLR, 70 for Fingal) and omits the applicant. The full description and the drawings are on the council register linked in step 1.
How to submit an observation
- Read the file on the council register.Drawings, planning statement and site notices are at http://www.eplanning.ie/LaoisCC/AppFileRefDetails/2660583/0.
- Write your observation.Quote
2660583at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on. - Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. Laois County Council takes it online with the submission or at the counter.
- Submit before 1 Oct 2026.Online through the register above, or in writing to the Planning Department, Laois County Council. The test is the date the authority receives it, not the date you post it.
- Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.
Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.
What the site is zoned
No current zoning polygon covers this site in the store.
Designations on or near the site
Nothing designated within 100 m of the site.
Nearby precedents within 500 m, last 5 years
Decisions
| Reference | Decision | Decided | Units | Distance | Description |
|---|---|---|---|---|---|
| 2560147 | Conditional | 30 Sept 2025 | 0 | 37 m | for works associated with the proposed uprate of the existing 110 kV Overhead Line (OHL) between the existing Cushaling 110 kV substation in the townland of Ballykilleen, Co. Offaly & the existing Portlaoise 110 kV substation in the townlands of Clonminam & Kylekiproe, Co. Laois. The replacement (“restringing”) of the existing overhead line circuit conductor with a new higher capacity conductor incl. installation of a new fibre communication connection; Replacement of 8 no. steel towers & their foundations; Replacement of steel members at 1 no. tower; Full tower painting required at 3 no. locations; Shear block remedial works (raise & cap) at 6 no. tower locations; Replacement of wooden poles only at 15 no. locations; Replacement of wooden poles & crossarm at 5 no. locations; Replacement of crossarm only at 14 no. locations; Replacement of existing danger notices at various locations, as required; Replacement of hardware and fittings, such as insulators, insulator hardware, earthwire hardware and anti-climbing guards at various locations as required; Replacement of suspension clamps, vibrations dampers and compression assemblies at all locations as required; All associates temporary site development works to gain access to the existing structures including clearance of vegetation, disassembly & reassembly of gate posts/piers & removal & re instatement of existing fencing; other temporary associated & ancillary development works required for the purpose of the existing circuit, including temporary items, such as; guard poles, construction compounds (located in the townlands of Bracklone, Tullaghan, Morett, Clonaddodoran and Kyletalesha), clearance or management of vegetation, installation of silt traps, silt fences, stone tracks, ground protections mats & watercourse crossings. No additional structures are proposed along the existing circuit. Structure 203,which will be relocated approx. 101m back towards structure 202 due to its existing position on top of a gravel mound & there being potential for subsidence of the gravel in the long term. No alteration to the nature, extent, alignment, character, or voltage of the existing electricity infrastructure is proposed. In addition, works to support this uprate also include the Cushlaing-Portlaoise 110KV bay lead-in conductor uprate at the Portlaoise 110KV station. A Natura Impact Statement (NIS) has been submitted with this application. Full description of all works within Site Notice. |
| 2560302 | Conditional | 2 Sept 2025 | 0 | 37 m | for works associated with the proposed uprate of the existing 110 kV Overhead Line (OHL) between the existing Cushaling 110 kV substation in the townland of Ballykilleen, Co. Offaly and the existing Portlaoise 110 kV substation in the townlands of Clonminam and Kylekiproe, Co. Laois. The Cushaling – Portlaoise 110 kV OHL is approximately 41.6 km long and comprises 17 no. steel lattice tower structures and 193 no. wooden pole structures. The existing circuit is located across the functional areas of Offaly County Council (OCC), Kildare County Council (KCC) and Laois County Council (LCC). Approximately 10 km of the existing OHL circuit is located within the functional area of OCC, approximately 9 km is within the functional area of KCC and approximately 22.6 km is located within the functional area of LCC. Separate planning applications are being lodged with each respective County Council. The Proposed Development across the functional area of Co. Kildare is located in the townlands of Coolelan, Kiltaghan North, Kiltaghan South, Clonmoyle West, Ummeras More, Mountrice, Mullaghroe Upper, Mullaghroe Lower, Coolatogher, Coolsickin or Quinsborough and Coolnafearagh. The Proposed Development works across the functional area of Co. Kildare will comprise: 1. The replacement (“restringing”) of the existing overhead line circuit conductor with a new higher capacity conductor including installation of a new fibre communication connection; 2. The replacement of 2 no. steel towers and their foundations; 3. The replacement of steel members at 1 no. tower; 4. Full tower painting required at 1 no. location; 5. Shear block remedial works (raise and cap) at 1 no. tower location; 6. The replacement of wooden poles only at 8 no. locations; 7. The replacement of wooden poles and crossarm at 3 no. locations; 8. The replacement of crossarm only at 4 no. locations; 9. The replacement of existing danger notices at various locations, as required; 10. The replacement of hardware and fittings, such as insulators, insulator hardware, earthwire hardware and anti-climbing guards at various locations, as required; 11. The replacement of suspension clamps, vibration dampers and compression assemblies at all locations, as required; 12. All associated temporary site development works to gain access to the existing structures including clearance of vegetation, disassembly and reassembly of gate posts/piers and removal and reinstatement of existing fencing; and 13. Other temporary associated |
| 2460576 | Conditional | 25 Nov 2024 | 0 | 87 m | construct agricultural building for storage of machinery and crops, and all associated site works |
Appeals
| ACP case | Type | Outcome | Decided | Distance |
|---|---|---|---|---|
| 500151 | — | Granted | 25 Feb 2026 | 37 m |
If neighbours here have appealed before and lost, the inspector's report on that case is the single most useful thing to read.
What has happened on this file
- 27 Aug 2026 New application · observations close 1 Oct 2026
- 27 Aug 2026 Decision
Generated from the Planning Register store; nothing was fetched live for this page. Source: national planning dataset, fetched 18 Sept 2026, 15:44. Not legal advice — confirm the deadline with Laois County Council before relying on it.