Ballyfoyle , Maganey , Co. Laois.
To construct of a part single-storey, part two-storey dwelling house, a domestic garage, the installation of a new wastewater treatment system and associated percolation area, a new splayed entrance and a new bored well, together with all associated site development works
The application
- Reference
- 2660827 · full record
- Authority
- Laois County Council
- Type
- PERMISSION
- Status
- NEW APPLICATION
- Units
- 1
- Floor area
- 244 m²
- Site area
- 2,601 m²
- Received
- 17 Nov 2026
- Decision due
- 20 Jan 2027
How to submit an observation
- Read the file on the council register.Drawings, planning statement and site notices are at http://www.eplanning.ie/LaoisCC/AppFileRefDetails/2660827/0.
- Write your observation.Quote
2660827at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on. - Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. Laois County Council takes it online with the submission or at the counter.
- Submit before 22 Dec 2026.Online through the register above, or in writing to the Planning Department, Laois County Council. The test is the date the authority receives it, not the date you post it.
- Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.
Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.
Designations on or near the site within 100 m
- Radon risk area × 1About 1 in 10 homes in this area is likely to have high radon levels
Nearby precedents within 500 m, last 5 years
Decisions
| Reference | Decision | Decided | Distance | Description |
|---|---|---|---|---|
| 2660323 | Conditional | 23 Jul 2026 | 140 m | - Replace (“restringing”) and uprating of c.10.2km section of the conductor along the existing Athy - Carlow 110 kV OHL circuit; - Provision of fibre communication connection on the uprated circuit; - Replacement of 14No. existing Intermediate Wooden Polesets, with similar structures. The replacement of these structures will result in standardised heights from 16m to 23m, with height increases between 1m and 2m; - Replacement of 15No. existing Intermediate Wooden Poleset crossarms; - Bar member replacements to 2No. existing steel angle masts; - Recapping works on shear blocks at 2No. existing steel angle masts; and, - All associated works/development to existing structures, including insulator/hardware replacement (strain clamps, suspension clamps and vibration dampers), replacement of step bolts, replacement of line identification and danger notices, painting of angle masts, replacement/installation of anti-climbing guards, access tracks, vegetation clearance, temporary construction compounds and all other works necessary to facilitate the development |
| 2660550 | Conditional | 17 Jul 2026 | 140 m | Replacement (“restringing”) and uprating of c.8.89km section of the conductor along the existing Athy - Carlow 110 kV OHL circuit; - Provision of fibre communication connection on the uprated circuit; - Replacement of 11No. existing Intermediate Wooden Polesets, with similar structures. The replacement of these structures will result in standardised heights from 16m to 24m, with height increases between 1m and 3m; - Replacement of 12No. existing intermediate Wooden Polesets crossarms; - Recapping works on shear blocks at 1No. existing steel angle mast; - Foundation strengthening of 1No. existing steel angle mast; - Bar member replacements to 8No. existing steel angle masts; - Separation of the existing double OHL circuit to provide for a new bypass OHL section measuring approximately 422m, connecting from the existing Athy 110 kV substation to the following proposed new structures on the existing Athy - Portlaoise 110 kV OHL: 2no. new single circuit angle masts (approximately 22.5m maximum height) and 1no. new wooden poleset (approximately 23.6m maximum height); and, - All associated works/development to existing structures, including hardware replacement (strain clamps, suspension clamps and vibration dampers), replacement of step bolts, replacement of line identification and danger notices, painting of angle masts, replacement/installation of anti-climbing guards, access tracks, vegetation clearance, temporary construction compounds and all other works necessary to facilitate the development |
What has happened on this file
- 17 Nov 2026 New application · observations close 22 Dec 2026
- 17 Nov 2026 Decision
Generated from the Planning Register store; nothing was fetched live for this page. Source: national planning dataset, fetched 24 Nov 2026, 23:00. Not legal advice — confirm the deadline with Laois County Council before relying on it.