PlanningRegister.ie
Observation pack · Limerick City and County Council

Woodfield , Dromcollogher , Co.Limerick

construction of a loose straw bedded shed, feed passage and concrete apron

Observations close 16 Oct 2026 9 days left
5 weeks from receipt (received 11 Sept 2026) · s.34 Planning and Development Act 2000 · art. 29 Regulations 2001 · fee €20 · council decision due 5 Nov 2026

The application

Reference
26206 · full record
Authority
Limerick City and County Council
Type
PERMISSION
Status
NEW APPLICATION
Applicant
not published by the national dataset — see the council register
Units
0
Floor area
—
Site area
1.79 ha
Received
11 Sept 2026
We first saw it
29 Sept 2026, 23:03
Decision due
5 Nov 2026
Decision
N/a

The national dataset truncates descriptions (80 characters for DLR, 70 for Fingal) and omits the applicant. The full description and the drawings are on the council register linked in step 1.

How to submit an observation

  1. Read the file on the council register.Drawings, planning statement and site notices are at https://eplanning.ie/LimerickCCC/AppFileRefDetails/26206/0.
  2. Write your observation.Quote 26206 at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on.
  3. Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. Limerick City and County Council takes it online with the submission or at the counter.
  4. Submit before 16 Oct 2026.Online through the register above, or in writing to the Planning Department, Limerick City and County Council. The test is the date the authority receives it, not the date you post it.
  5. Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.

Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.

After you submit: keep the acknowledgement. Under the 2024 Act it secures your right to appeal — only the applicant and a person who made a valid observation may bring the council's decision to An Coimisiún Pleanála, within four weeks of the decision. Making a valid observation is also what buys a right of appeal: under s.37(1) of the 2000 Act, only the applicant and a person who made a valid submission or observation to the planning authority may appeal the decision to An Coimisiún Pleanála (within four weeks of the decision). Missing the five-week window closes both doors.

What the site is zoned

No current zoning polygon covers this site in the store.

Designations on or near the site

  • NIAH-recorded building × 1
    Woodfield House

Nearby precedents within 500 m, last 5 years

Decisions

ReferenceDecisionDecidedUnitsDistanceDescription
2560698Conditional16 Jul 20260344 mUisce Éireann intends to apply for a 10-year planning permission to construct a new wastewater treatment plant (WwTP) at Coolaboy, Dromcollogher, Co. Limerick. The Proposed Development will comprise the construction of a new WwTP to provide treatment capacity for a population equivalent (PE) of 1,350 (10 years) and 1,550 (30 years). The wastewater will be treated and discharged via an outfall pipe into the River Deel at a location approximately 6.5 kilometres to the northwest of the WwTP. The outfall pipe will be located primarily in public roads in the townlands of Coolaboy, Mundellihy, Ballinlongig, Cloonmore and Tulligmacthomas. The existing WwTP will be decommissioned and demolished upon completion of the Proposed Development. The Proposed Development will comprise: i) Development of a new preliminary wastewater treatment plant including infrastructure such as bypass channels and screens; grit and fats, oils, greases (FOG) removal plant; storm water overflow tank; sludge drying reed beds; flash mixer chamber; return liquor pumping station facilities; caustic and ferric dosing storge tanks; flow to full treatment (FFT) pumping station; final settlement tank flow split chamber; 2 no. final clarifiers; sludge draw off chamber (return-activated sludge and waste-activated sludge pumping station); static mixer; wash water pumping station; tertiary disk filter; and final effluent pumping station. ii) Development of an ESB sub-station, control building, and fuel tank. iii) Provision of approx. 54m of new gravity sewer to direct flows to the new WwTP. This will replace an existing combined sewer overflow which will be decommissioned after the process switchover. iv) Provision of adequate site lighting, access gates, access stairs, walkways, car parking and electric charging facilities, and site boundary hedging and fencing. v) Provision of photovoltaic (PV) panels on the site of the existing WwTP following its decommissioning. vi) Provision of site drainage infrastructure including a hydrocarbon interceptor, construction of outfall pipe along public roads, and headwall in Tulligmacthomas. vii) Realignment and widening of existing site entrance, including provision of a new access road into the site and a bridge within the site. viii) All hard and soft landscaping throughout the site, and all associated and ancillary site works. The Proposed Development will be accompanied by a Natura Impact Statement (NIS)
2660548Conditional9 Jul 20260164 ma new footbridge over river with edge protection & connecting paved link between the church grounds & the town park lands & all associated site works (The proposed works are in the Curtilage of a protected structure)
2561011Conditional20 Feb 20260349 mthe construction of an extension to the existing dwelling house, the construction of a domestic garage, the construction of dog kennels and all ancillary site works
2560003Conditional4 Apr 20250389 mconstruction of an extension to the North Eastern (Entrance) Elevation, to include a revision to the entrance and also the elevational treatment
2560089Conditional28 Mar 20250164 ma new public walkway link between the church carpark & town park lands & associated site works
2360457Conditional22 Aug 20230401 mconstruction of a new all-weather playing pitch complete with enclosure fence/ball wall, and 6no. 12m high floodlighting columns, construction of 8no. 20m high floodlighting columns to the perimeter of the existing playing pitch and construction of a new walkway along with pedestrian lighting to the perimeter of the existing playing pitch and carry out all associated ancillary site works
2319Conditional25 Apr 20230268 mthe extension, alterations and renovations of existing domestic derelict structures on site and all associated site works for use as 1 no. dwelling and all associated site works
22885Conditional24 Apr 20231235 ma variation in the use of a existing nursing home which contains two existing dwelling units at the rear and a partially demolished building to the front. Permission is being sought for the demolition of one of the two existing buildings to the rear to allow access and sunlight into the proposed developments. The second building to the rear will be converted into 2nr apartments. Permission is also being sought for the reconstruction of the front building into a proposed Guesthouse. The demolished front building will be constructed to reconstitute the street façade and provision of access way to allow access to rear car park and to allow access to emergency services(Fire Services)

Appeals

No appeals within 500 m in the last 5 years.

What has happened on this file

  • 11 Sept 2026 New application · observations close 16 Oct 2026
  • 11 Sept 2026 Decision

Generated from the Planning Register store; nothing was fetched live for this page. Source: national planning dataset, fetched 29 Sept 2026, 23:03. Not legal advice — confirm the deadline with Limerick City and County Council before relying on it.