PlanningRegister.ie
Observation pack · Limerick City and County Council

Edward Lifesciences Industrial Campus , National Technology Park , Plassey Park Road

new external glazing and 2no. external doors to the south-east elevation

Observations close 22 Oct 2026 16 days left
5 weeks from receipt (received 17 Sept 2026) · s.34 Planning and Development Act 2000 · art. 29 Regulations 2001 · fee €20 · council decision due 11 Nov 2026

The application

Reference
2661090 · full record
Authority
Limerick City and County Council
Type
PERMISSION
Status
NEW APPLICATION
Applicant
not published by the national dataset — see the council register
Units
0
Floor area
—
Site area
458 m²
Received
17 Sept 2026
We first saw it
29 Sept 2026, 23:03
Decision due
11 Nov 2026
Decision
N/a

The national dataset truncates descriptions (80 characters for DLR, 70 for Fingal) and omits the applicant. The full description and the drawings are on the council register linked in step 1.

How to submit an observation

  1. Read the file on the council register.Drawings, planning statement and site notices are at https://eplanning.ie/LimerickCCC/AppFileRefDetails/2661090/0.
  2. Write your observation.Quote 2661090 at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on.
  3. Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. Limerick City and County Council takes it online with the submission or at the counter.
  4. Submit before 22 Oct 2026.Online through the register above, or in writing to the Planning Department, Limerick City and County Council. The test is the date the authority receives it, not the date you post it.
  5. Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.

Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.

After you submit: keep the acknowledgement. Under the 2024 Act it secures your right to appeal — only the applicant and a person who made a valid observation may bring the council's decision to An Coimisiún Pleanála, within four weeks of the decision. Making a valid observation is also what buys a right of appeal: under s.37(1) of the 2000 Act, only the applicant and a person who made a valid submission or observation to the planning authority may appeal the decision to An Coimisiún Pleanála (within four weeks of the decision). Missing the five-week window closes both doors.

What the site is zoned

CodeObjectivePlanIn force
C6
Waterfront
High Tech/Manufacturing Campus: To provide for office, research and development, high technology, regional distribution/ logistics, manufacturing and processing type employment in a high quality built and landscaped campus style environment.LI-003:DP:limerick-development-plan-2022-202829 Jul 2022 → 1 Jun 2028

An application that accords with the zoning objective is hard to resist on principle; one that does not may be a material contravention, which the council can only grant by the s.34(6) procedure with its own notice and window.

Source: LIMERICK LI-003:DP:limerick-development-plan-2022-2028 · fetched 27 Sept 2026, 19:37
SourceLicenceFetchedLink
LIMERICK LI-003:DP:limerick-development-plan-2022-2028—27 Sept 2026, 19:37open

Designations on or near the site

Nothing designated within 100 m of the site.

Nearby precedents within 500 m, last 5 years

Decisions

ReferenceDecisionDecidedUnitsDistanceDescription
2660164Conditional14 May 20261453 mconstruction of two storey detached dwelling house, detached garage, new entrance from the estate road, connection to public services together with all associated site works previously approved under planning ref.no. 20/728
2560990Conditional23 Feb 20260475 mthe construction of a family flat extension to accommodate a dependent relative to the side of the existing house and all associated site works
2560307Conditional30 May 20250392 mthe construction of a new covered entrance to the front of the building, provision of additional office space to the internal courtyard, HSE signage at the front entrance, landscaping to the front of the building including a paved seating area and all associated works above and below ground
2460298Conditional30 May 20240167 mthe development that comprises: (a) the retention of modifications to previously approved permission Planning Ref. No. 15/180 to omit the 3-storey office building and canteen to the front (south-west) of the main facility; and (b) the retention of 2 no. groups of temporary cabin structures to the front (south-west) of the main facility, and associated site works
2460294Conditional29 May 20240274 mthe construction of a new plant room structure in the adjacent car park, ancillary to Mary Rosse Centre 3 and all associated site works above and below ground
2360291Conditional16 Apr 20240443 mthe improvement of playing facilities at U.L. Bohemians Rugby Football Club, Mulcair Drive, Annacotty, Co. Limerick, V94 X267. The facility comprises of a number of structures, sports and playing facilities, namely (1) a two-storey clubhouse/administration building (1,434m2) to contain a gymnasium, 6 no. dressing rooms, 2 no. officials changing rooms, treatment rooms, meeting rooms, kitchen, public toilets, storage spaces, hospitality facilities and function room. (2) a 500 no. seated spectator viewing area (3) reconfiguration of the existing 4 no. floodlit playing surfaces with an end-goal netting system, fencing and electronic scoreboard (4) bike shed and bin store (39m2), (5) reconfiguration of the existing associated car/coach parking facilities, & (6) all ancillary site works, site development works and landscaping to accommodate access works, connections to public services and groundskeeping and maintenance facilities A Natura Impact Statement has been prepared in respect of the proposed development and accompanies the planning application
23563Conditional24 Jan 20240291 mthe development that will consist of permission for: (1) The construction of building extensions to the rear(north-east) of the existing facility including roof plant & equipment. (2) The construction/installation of tanks, plant & equipment, equipment enclosures and associated bunds to the existing tank farm & nitrogen compound, to the rear of the main facility. (3) The installation of an access panel in the front(south-west) facade. (4) Modifications/Retention permission to previously as granted scheme under planning ref. no. 18/884, including facade changes, modifications to roof plant and roof access stairs. (5) All associated ancillary site works
221143Conditional12 Dec 20220223 mthe construction of two external signs; one sign is proposed to be fixed to the north east elevation of the AMC building, and one sign is to be located at the ground level entrance with associated site and services works

Appeals

ACP caseTypeOutcomeDecidedDistance
323410—Refused25 Jun 2026485 m
312559—Granted with conditions20 Sept 2022452 m

If neighbours here have appealed before and lost, the inspector's report on that case is the single most useful thing to read.

What has happened on this file

  • 17 Sept 2026 New application · observations close 22 Oct 2026
  • 17 Sept 2026 Decision

Generated from the Planning Register store; nothing was fetched live for this page. Source: national planning dataset, fetched 29 Sept 2026, 23:03. Not legal advice — confirm the deadline with Limerick City and County Council before relying on it.