PlanningRegister.ie
Observation pack · Mayo County Council

Knockranny , Westport

construct an all weather sand arena, construct an all weather turnout paddock and construct a covered dung stead and water harvesting tanks together with associated site services

Observations close 28 Sept 2026 3 days left
5 weeks from receipt (received 24 Aug 2026) · s.34 Planning and Development Act 2000 · art. 29 Regulations 2001 · fee €20 · council decision due 18 Oct 2026

The application

Reference
26202 · full record
Authority
Mayo County Council
Type
PERMISSION
Status
NEW APPLICATION
Applicant
not published by the national dataset — see the council register
Units
0
Floor area
—
Site area
2.22 ha
Received
24 Aug 2026
We first saw it
18 Sept 2026, 15:44
Decision due
18 Oct 2026
Decision
N/a

The national dataset truncates descriptions (80 characters for DLR, 70 for Fingal) and omits the applicant. The full description and the drawings are on the council register linked in step 1.

How to submit an observation

  1. Read the file on the council register.Drawings, planning statement and site notices are at http://www.eplanning.ie/MayoCC/AppFileRefDetails/26202/0.
  2. Write your observation.Quote 26202 at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on.
  3. Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. Mayo County Council takes it online with the submission or at the counter.
  4. Submit before 28 Sept 2026.Online through the register above, or in writing to the Planning Department, Mayo County Council. The test is the date the authority receives it, not the date you post it.
  5. Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.

Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.

After you submit: keep the acknowledgement. Under the 2024 Act it secures your right to appeal — only the applicant and a person who made a valid observation may bring the council's decision to An Coimisiún Pleanála, within four weeks of the decision. Making a valid observation is also what buys a right of appeal: under s.37(1) of the 2000 Act, only the applicant and a person who made a valid submission or observation to the planning authority may appeal the decision to An Coimisiún Pleanála (within four weeks of the decision). Missing the five-week window closes both doors.

What the site is zoned

No current zoning polygon covers this site in the store.

Designations on or near the site

Nothing designated within 100 m of the site.

Nearby precedents within 500 m, last 5 years

Decisions

ReferenceDecisionDecidedUnitsDistanceDescription
26137Conditional6 Aug 20260447 mThe development will consist of amendments to Planning Reference P24/546 1) seeking a 10 year permission instead of the 5 year permission already permitted 2) the construction of 38 KVA substation and 3) the relocation of battery storage containers 1 - 4 on site all within the original site boundaries together with associated site services
2660325Conditional10 Jun 20260260 mConstruction of an extension to an existing dwelling together with ancillary site works.
2660225Conditional15 May 20261321 mDemolish existing sunroom, construct new 2-storey rear extension, remove existing dormer windows at first floor level and replace with new velux rooflights and carry out minor elevational alterations to existing dormer dwelling. Works to include the creation of a new entrance driveway from the Knockranny village road.
25468Conditional15 Jan 20260342 mdemolish an existing entrance porch and to construct a new entrance porch
2560779Conditional17 Dec 20250474 mApplication is being made to Mayo County Council on behalf of Charles Hughes Ltd for planning permission to construct a loading bay and Dock Leveller, revisions to western elevation and site layout permitted under P25/60234 with revised office layout and elevations at Castlebar Road, Carrowbeg, Westport, Co Mayo.
24546Conditional25 Sept 20250447 mconstruct an electrical transmission support long duration battery array. The array will consist of 52 number battery storage containers each holding battery storage units of up to 4.5MW for a maximum total of 234MQ together with associated site services
2560234Conditional18 Aug 20250474 mApplication is being made to Mayo County Council on behalf of Charles Hughes Ltd for planning permission to demolish existing outbuildings / sheds and to construct 2 extensions to existing office, manufacturing and distribution centre located at the above address. The extensions will comprise warehousing of 1557m², 2 storeys of offices comprising 1038m², revised front elevation, revised western elevation with goods inwards and outwards, dock leveller, service yard and turning area, revised carparking and all ancillary site services at Castlebar Road, Carrowbeg, Westport, Co Mayo
2460759Conditional23 Jun 20251346 mDevelopment will consist of the construction of a dwelling and ancillary storage shed, with connection to nearby public sewerage and water supply and all associated site works.

Appeals

No appeals within 500 m in the last 5 years.

What has happened on this file

  • 24 Aug 2026 New application · observations close 28 Sept 2026
  • 24 Aug 2026 Decision