retention and completion of dwelling house, previous planning reference P07/1560

Observations close 2 Nov 2026 14 days left
5 weeks from receipt (received 28 Sept 2026) · s.34 Planning and Development Act 2000 · art. 29 Regulations 2001 · fee €20 · council decision due 22 Nov 2026

The application

Reference
26232 · full record
Authority
Mayo County Council
Type
RETENTION
Status
NEW APPLICATION
Applicant
not published by the national dataset — see the council register
Units
0
Floor area
—
Site area
3,389 m²
Received
28 Sept 2026
We first saw it
7 Oct 2026, 01:19
Decision due
22 Nov 2026
Decision
N/a

The national dataset truncates descriptions (80 characters for DLR, 70 for Fingal) and omits the applicant. The full description and the drawings are on the council register linked in step 1.

How to submit an observation

  1. Read the file on the council register.Drawings, planning statement and site notices are at http://www.eplanning.ie/MayoCC/AppFileRefDetails/26232/0.
  2. Write your observation.Quote 26232 at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on.
  3. Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. Mayo County Council takes it online with the submission or at the counter.
  4. Submit before 2 Nov 2026.Online through the register above, or in writing to the Planning Department, Mayo County Council. The test is the date the authority receives it, not the date you post it.
  5. Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.

Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.

After you submit: keep the acknowledgement. Under the 2024 Act it secures your right to appeal — only the applicant and a person who made a valid observation may bring the council's decision to An Coimisiún Pleanála, within four weeks of the decision. Making a valid observation is also what buys a right of appeal: under s.37(1) of the 2000 Act, only the applicant and a person who made a valid submission or observation to the planning authority may appeal the decision to An Coimisiún Pleanála (within four weeks of the decision). Missing the five-week window closes both doors.

What the site is zoned

No current zoning polygon covers this site in the store.

Designations on or near the site

Nothing designated within 100 m of the site.

Nearby precedents within 500 m, last 5 years

Decisions

ReferenceDecisionDecidedUnitsDistanceDescription
2360274Conditional24 Aug 20231436 mThe proposed development will consist of the construction of a dwelling and ancillary shed, with proprietary waste water treatment system, percolation area and all associated site works
2360016Conditional15 Mar 202310 mThe installation of approximately 15Km of 250mm OD water Trunk Main, which will extend from a position approximately 1Km from Westport at the junction of Pound Road and the R355 in the townland of Carrownalurgan to Kilsallagh Lower at the road junction between the R355 and the L1826 road to Drummin and the installation of approximately 29.3Km of a mains distribution network to supply water to 473 No Consumers along the route of the Trunk Main and in the area to the Townlands to the West of Croagh Patrick. All associated temporary site development works to gain access including clearance of vegetation, disassembly and reassembly of gate posts/ piers and removal and reinstatement of existing fencing, walls, and hedging; and any other temporary associated and ancillary development works required for the purposes of the proposed watermain, including the installation of stone tracks and temporary watercourse crossings. The watermain pipeline is located within the townlands of Cloghan, Clooneen, Knockfin, Ardoley, Churchfield, Knockaraha East, Knockaraha West, Streamstown, Belclare, Killadangan, Deerpark West, Murrisknaboll, Carrowkeeran, Bellataleen, Carrowkeel, Murrisk Demesne, Meermihil, Glaspatrick, Thornhill, Carrowmacloughlin, Leckanvy, Killsallagh Lower, Killsallagh Upper, Kinknock, Kilgeever, Cuilleen, Mullagh, Cartoor, Glenbaun, Glencally, Furgill, Cregganroe and Boheh in County Mayo.
21498Conditional1 Nov 20211256 mPERMISSION TO CONSTRUCT A DOMESTIC GARAGE AS WELL AS PERMISSION TO RETAIN AND COMPLETE THE EXISTING HOUSE ALREADY GRANTED PERMISSION UNDER P04/1622 WITH A PROPRIETARY EFFLUENT TREATMENT SYSTEM TOGETHER WITH ALL ANCILLARY SITE WORKS

Appeals

No appeals within 500 m in the last 5 years.

What has happened on this file

  • 28 Sept 2026 New application · observations close 2 Nov 2026
  • 28 Sept 2026 Decision