34 Abbey Court , Killala Road Ballina , Co. Mayo

Full planning permission for the following: (1) Demolish existing semi-detached two-story dwelling house, (2) Construct replacement semi-detached two-story dwelling house, together with all associated site works at 34 Abbey Court, Killala Road, Ballina, Co. Mayo, F26F9R9.

Observations close 11 Nov 2026 6 days left
5 weeks from receipt (received 7 Oct 2026) · s.34 Planning and Development Act 2000 · art. 29 Regulations 2001 · fee €20 · council decision due 1 Dec 2026

The application

Reference
2660786 · full record
Authority
Mayo County Council
Type
PERMISSION
Status
NEW APPLICATION
Applicant
not published by the national dataset — see the council register
Units
0
Floor area
—
Site area
244 m²
Received
7 Oct 2026
We first saw it
14 Oct 2026, 01:45
Decision due
1 Dec 2026
Decision
N/a

The national dataset truncates descriptions (80 characters for DLR, 70 for Fingal) and omits the applicant. The full description and the drawings are on the council register linked in step 1.

How to submit an observation

  1. Read the file on the council register.Drawings, planning statement and site notices are at http://www.eplanning.ie/MayoCC/AppFileRefDetails/2660786/0.
  2. Write your observation.Quote 2660786 at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on.
  3. Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. Mayo County Council takes it online with the submission or at the counter.
  4. Submit before 11 Nov 2026.Online through the register above, or in writing to the Planning Department, Mayo County Council. The test is the date the authority receives it, not the date you post it.
  5. Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.

Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.

After you submit: keep the acknowledgement. Under the 2024 Act it secures your right to appeal — only the applicant and a person who made a valid observation may bring the council's decision to An Coimisiún Pleanála, within four weeks of the decision. Making a valid observation is also what buys a right of appeal: under s.37(1) of the 2000 Act, only the applicant and a person who made a valid submission or observation to the planning authority may appeal the decision to An Coimisiún Pleanála (within four weeks of the decision). Missing the five-week window closes both doors.

What the site is zoned

No current zoning polygon covers this site in the store.

Designations on or near the site

Nothing designated within 100 m of the site.

Nearby precedents within 500 m, last 5 years

Decisions

ReferenceDecisionDecidedUnitsDistanceDescription
2660336Conditional18 Jun 2026172 mfull planning permission for the following: (1) Demolish existing two-story detached dwelling house, (2) Construct replacement two-story detached dwelling house, together with all associated site works
2560102Conditional13 Feb 20260427 m1. A new football pitch with associated highlevel flood lighting, ball stopping and multi-purpose track surround. 2. A new astro turf pitch and playground area, 3. new changing facilites building and spectator stand, 4 the construction of new access road, car park, pedestrian access, all of this together the excavation and recountouring of the site, connection to services all associated site works at, Culleens Td., Ballina, Co.Mayo.
2560027Conditional18 Jul 20250499 mFull planning permission for a proposed steel framed commercial unit, together with on-site parking, wastewater treatment system and connection to existing public services to include all associated site works. A Natura Impact Statement will be submitted to the planning authority with the application.
24130Conditional17 Jun 20240273 mretention of minor alterations to dwelling house (front porch and 3 windows in front elevation instead of 4 windows) and retention of domestic shed
2360566Conditional18 Apr 2024151 m(1) Construct new dwelling house, (2)Construct new domestic garage, (3) retention permission of a temporary mobile home (for the duration of the works only) (4) to complete all service connections as required, (5) upgrade existing entrance to domestic use, and (6) Carry out all required ancillary works on site.
2360422Conditional21 Nov 20231148 mfull planning permission for the following: (1) Demolish existing detached dwelling house, (2) Construct replacement detached dwelling house, together with all associated site works at Culleens, Killala Rd, Ballina, Co. Mayo.
2360361Conditional16 Oct 2023080 mChange of Plans for planning previously granted (Planning Reference PL23/60068) at 73 Abbey Court, Killala Road, Ballina, Co. Mayo
2360264Conditional22 Aug 2023198 m(1) Demolish existing two storey dwelling, and (2) Construct a replacement two storey dwelling, with all associated ancillary site works

Appeals

ACP caseTypeOutcomeDecidedDistance
313975—Granted with conditions19 Feb 2024147 m

If neighbours here have appealed before and lost, the inspector's report on that case is the single most useful thing to read.

What has happened on this file

  • 7 Oct 2026 New application · observations close 11 Nov 2026
  • 7 Oct 2026 Decision