PlanningRegister.ie
Observation pack · Mayo County Council

Rockland , Castlebar , Co. Mayo.

New dwelling house with garage and boat shed including tertiary on site waste water treatment system with all associated site works & services

Observations close 21 Dec 2026 26 days left
5 weeks from receipt (received 16 Nov 2026) · s.34 Planning and Development Act 2000 · art. 29 Regulations 2001 · fee €20 · council decision due 19 Jan 2027

The application

Reference
2660909 · full record
Authority
Mayo County Council
Type
PERMISSION
Status
NEW APPLICATION
Site area
3,908 m²
Received
16 Nov 2026
Decision due
19 Jan 2027

How to submit an observation

  1. Read the file on the council register.Drawings, planning statement and site notices are at http://www.eplanning.ie/MayoCC/AppFileRefDetails/2660909/0.
  2. Write your observation.Quote 2660909 at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on.
  3. Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. Mayo County Council takes it online with the submission or at the counter.
  4. Submit before 21 Dec 2026.Online through the register above, or in writing to the Planning Department, Mayo County Council. The test is the date the authority receives it, not the date you post it.
  5. Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.

Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.

After you submit: keep the acknowledgement. Under the 2024 Act it secures your right to appeal — only the applicant and a person who made a valid observation may bring the council's decision to An Coimisiún Pleanála, within four weeks of the decision. Making a valid observation is also what buys a right of appeal: under s.37(1) of the 2000 Act, only the applicant and a person who made a valid submission or observation to the planning authority may appeal the decision to An Coimisiún Pleanála (within four weeks of the decision). Missing the five-week window closes both doors.

Nearby precedents within 500 m, last 5 years

Decisions

ReferenceDecisionDecidedUnitsDistanceDescription
2660508Conditional16 Nov 20260 mMountain Dew Property Company Ltd. intends to apply for a 10-year planning permission for development at Derryool, Rocklands, Castlebar, Co. Mayo, comprising: The development will consist of the re-contouring of agricultural land by the use of imported by-product of soil and stone over an area of 0.79 hectares on an overall site area of 1.05 hectares for the benefit of agricultural land. The deposition area will accommodate 25,200 tonnes of soil and stone. Permission is sought for access, fencing and all associated site development works and services and any mitigation measures such as silt fencing to protect watercourses. Permission is also sought for the retention of an existing access road and pre-existing deposits of topsoil and stone that were claimed from these lands.
2560083Conditional14 May 20251117 mThe construction of a new dwelling house and domestic garage, on-site wastewater treatment system, a new access road, connections to public services and ancillary site development works above and below ground.
2460236Refused29 Oct 2024117 mThe construction of a new dwelling house and domestic garage, on-site wastewater treatment system, a new access road, connections to public services and ancillary site development works above and below ground.

What has happened on this file

  • 16 Nov 2026 New application · observations close 21 Dec 2026
  • 16 Nov 2026 Decision

Generated from the Planning Register store; nothing was fetched live for this page. Source: national planning dataset, fetched 24 Nov 2026, 23:00. Not legal advice — confirm the deadline with Mayo County Council before relying on it.