The Cottage , Greenogue , Kilsallaghan

The development consists of the retention of rear extension, internal alterations, and all associated works

Observations close 9 Dec 2026 23 days left
5 weeks from receipt (received 4 Nov 2026) · s.34 Planning and Development Act 2000 · art. 29 Regulations 2001 · fee €20 · council decision due 7 Jan 2027

The application

Reference
26225 · full record
Authority
Meath County Council
Type
PERMISSION
Status
PRE_VALIDATION
Site area
1,497 m²
Received
4 Nov 2026
Decision due
7 Jan 2027

How to submit an observation

  1. Read the file on the council register.Drawings, planning statement and site notices are at http://www.eplanning.ie/MeathCC/AppFileRefDetails/26225/0.
  2. Write your observation.Quote 26225 at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on.
  3. Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. Meath County Council takes it online with the submission or at the counter.
  4. Submit before 9 Dec 2026.Online through the register above, or in writing to the Planning Department, Meath County Council. The test is the date the authority receives it, not the date you post it.
  5. Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.

Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.

After you submit: keep the acknowledgement. Under the 2024 Act it secures your right to appeal — only the applicant and a person who made a valid observation may bring the council's decision to An Coimisiún Pleanála, within four weeks of the decision. Making a valid observation is also what buys a right of appeal: under s.37(1) of the 2000 Act, only the applicant and a person who made a valid submission or observation to the planning authority may appeal the decision to An Coimisiún Pleanála (within four weeks of the decision). Missing the five-week window closes both doors.

What the site is zoned

CodeObjectivePlanIn force
P5
Rural and agricultural
RA - Rural Area: Rural Areameath county development plan 2021 20273 Nov 2021 → 2 Nov 2027
P5
Rural and agricultural
RA - Rural Area: Rural Areameath county development plan 2021 2027 as varied3 Nov 2021 → 2 Nov 2027

An application that accords with the zoning objective is hard to resist on principle; one that does not may be a material contravention, which the council can only grant by the s.34(6) procedure with its own notice and window.

Source: Meath County Council development plan zoning · fetched 4 Oct 2026, 23:04
SourceLicenceFetchedLink
Meath County Council development plan zoning—4 Oct 2026, 23:04open

Designations on or near the site within 100 m

  • Radon risk area × 3
    About 1 in 10 homes in this area is likely to have high radon levels · About 1 in 20 homes in this area is likely to have high radon levels · About 1 in 20 homes in this area is likely to have high radon levels
  • OPW flood extent nearby floodinfo.ie
    Shown as a flag only — the OPW licence does not allow us to redistribute the extent.

Nearby precedents within 500 m, last 5 years

Decisions

ReferenceDecisionDecidedUnitsDistanceDescription
2561018Conditional19 Dec 2025409 mRED III - the Proposed Development will consist of an amendment to a previously consented development (planning reference: 211436) comprising the slight relocation of the substation building 7.2m north and its replacement with a storage building, removal of the 4 no. temporary storage containers in the temporary construction compound and replacement with 3 no. permanent 40 ft storage containers, minor panel reconfiguration, realignment of access track, and adjustment to the duration period from a 5 to 10-year permission. An updated Natura Impact Statement (NIS) has been submitted with this application. This development is covered by the provisions of the Renewable Energy Directive III (Directive (EU) 2023/2413) and it is important to note that the planning application may be subject to section 34D of the Planning and Development Act 2000, as amended. When a notice issues in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply
23698Conditional10 Jan 2024165 mretention of dwelling and permission for new vehicular entrance and the provision of a new wastewater treatment system and percolation area and all associated site works and to omit condition number 2 of planning permission reference number AA200094. Significant furher information/revised plans submitted on this application

What has happened on this file

  • 4 Nov 2026 New application · observations close 9 Dec 2026
  • 4 Nov 2026 Decision

Generated from the Planning Register store; nothing was fetched live for this page. Source: national planning dataset, fetched 11 Nov 2026, 23:00. Not legal advice — confirm the deadline with Meath County Council before relying on it.