the development will consist of permission for 3 no. 4 bedroom storey and a half type dwellings, 3 no. domestic garages, 3 no. waste water treatment systems, 3. No site entrance’s together with access road and all associated site works

Observations close 13 Nov 2026 13 days left
5 weeks from receipt (received 9 Oct 2026) · s.34 Planning and Development Act 2000 · art. 29 Regulations 2001 · fee €20 · council decision due 3 Dec 2026

The application

Reference
2661250 · full record
Authority
Meath County Council
Type
PERMISSION
Status
NEW APPLICATION
Applicant
not published by the national dataset — see the council register
Units
1
Floor area
751 m²
Site area
1.08 ha
Received
9 Oct 2026
We first saw it
28 Oct 2026, 01:34
Decision due
3 Dec 2026
Decision
N/a

The national dataset truncates descriptions (80 characters for DLR, 70 for Fingal) and omits the applicant. The full description and the drawings are on the council register linked in step 1.

How to submit an observation

  1. Read the file on the council register.Drawings, planning statement and site notices are at http://www.eplanning.ie/MeathCC/AppFileRefDetails/2661250/0.
  2. Write your observation.Quote 2661250 at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on.
  3. Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. Meath County Council takes it online with the submission or at the counter.
  4. Submit before 13 Nov 2026.Online through the register above, or in writing to the Planning Department, Meath County Council. The test is the date the authority receives it, not the date you post it.
  5. Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.

Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.

After you submit: keep the acknowledgement. Under the 2024 Act it secures your right to appeal — only the applicant and a person who made a valid observation may bring the council's decision to An Coimisiún Pleanála, within four weeks of the decision. Making a valid observation is also what buys a right of appeal: under s.37(1) of the 2000 Act, only the applicant and a person who made a valid submission or observation to the planning authority may appeal the decision to An Coimisiún Pleanála (within four weeks of the decision). Missing the five-week window closes both doors.

What the site is zoned

CodeObjectivePlanIn force
M1
Metro / rail economic corridor
C1 - Mixed Use: Mixed Usemeath county development plan 2021 20273 Nov 2021 → 2 Nov 2027
O1
Green belt and strategic open land
WL - White Lands: White Landsmeath county development plan 2021 20273 Nov 2021 → 2 Nov 2027
R2
Existing residential
A1 - Existing Residential: Existing Residentialmeath county development plan 2021 20273 Nov 2021 → 2 Nov 2027
M2
Major town centre
C1 - Mixed Use: Mixed Usemeath county development plan 2021 2027 as varied3 Nov 2021 → 2 Nov 2027
O1
Green belt and strategic open land
WL - White Lands: White Landsmeath county development plan 2021 2027 as varied3 Nov 2021 → 2 Nov 2027
R2
Existing residential
A1 - Existing Residential: Existing Residentialmeath county development plan 2021 2027 as varied3 Nov 2021 → 2 Nov 2027

An application that accords with the zoning objective is hard to resist on principle; one that does not may be a material contravention, which the council can only grant by the s.34(6) procedure with its own notice and window.

Source: Meath County Council development plan zoning · fetched 4 Oct 2026, 23:04
SourceLicenceFetchedLink
Meath County Council development plan zoning—4 Oct 2026, 23:04open

Designations on or near the site

  • Radon risk area × 1
    About 1 in 20 homes in this area is likely to have high radon levels
  • OPW flood extent nearby floodinfo.ie
    Shown as a flag only — the OPW licence does not allow us to redistribute the extent.

Nearby precedents within 500 m, last 5 years

Decisions

ReferenceDecisionDecidedUnitsDistanceDescription
2560676Conditional12 Nov 202574439 mThe proposed development consists of 74no residential units comprising 66no houses (14no 2bed, 46no 3bed and 6no 4bed) in a mix of semi-detached and terraced units and 8no simplex/duplex apartments (4no 1bed and 4no 2bed) in a standalone three-storey building. A new vehicular access and egress is proposed off Fairyhouse Road, together with all associated site development works including undergrounding of overhead ESB lines, ESB substation, public lighting, landscaping, and boundary treatments. Signifcant further information/revised plans submitted on this application
2583Conditional21 Aug 20251185 mextension to front porch and RETENTION PERMISSION extensions to side and rear of existing house, conversion of original garage to bedroom, construction of new detached garage, games room, two garden sheds and greenhouse and all associated siteworks.
2560637Conditional14 Aug 2025364275 mWe, Beo Properties Limited, intend to apply to Meath County Council for a 7-year planning permission for a Large-scale Residential Development (LRD) at this site (12.58 ha) located on the southern edge of the settlement of Ratoath in County Meath, within the townlands of Commons and Jamestown. The subject site is generally bound to the north by Glascarn Lane, the rear of houses at Glascarn Lane, further existing residential dwellings and a permitted strategic housing development (SHD) scheme (Reg Ref: TA17/305196); to the east by the permitted SHD scheme (Reg Ref: TA17/305196); to the south by existing agricultural fields and by Glascarn Lane; and to the west by Fairyhouse Road (R155), the rear of houses on Fairyhouse Road, Cairn Court and Carraig na Gabhna, and existing agricultural fields. …....
24231Conditional31 Oct 2024034 mthe retention of biocycle wastewater treatment unit and raised sand polishing filter system and all associated siteworks
2460574Conditional18 Sept 2024122 mthe proposed erection of alterations and extensions to an existing dwelling house (demolition of the existing garage), erection of a new domestic garage together with associated and auxiliary accommodation, upgrade of the existing effluent treatment system together with associated and auxiliary site works
2460314Conditional24 Jun 20240239 mretention of the construction of a flat roof structure in the rear garden currently used as two separate habitable units, and conversion of this structure to use as storage, hobby room and home office space ancillary to the existing dwelling
2460210Conditional20 May 20240331 mplanning permission to replace an existing 30m lattice type telecommunications support structure and associated equipment and cabinets located adjacent to Fairyhouse Racecourse Stadium with a new 30m multi-user lattice type telecommunications support structure carrying antenna and dishes enclosed within a 2.4 metre high palisade fenced compound together with associated ground equipment cabinets and associated site works in the storage area at the north eastern boundary of Fairyhouse Racecourse
2360296Conditional17 Nov 20230307 mEirGrid PLC, with the consent and approval of the Electricity Supply Board (ESB), intends to apply to Meath County Council for permission for works associated with the proposed uprate of the existing Louth – Woodland 220 kV overhead powerline (OHL) between the existing Louth 220 kV substation in the townland of Monavallet, County Louth and the existing Woodland 220 kV substation in the townland of Woodland, County Meath. The Louth – Woodland 220 kV OHL is approximately 61.5 km long and comprises 207 no. steel lattice tower structures. The existing circuit is located within the functional area of Louth County Council and Meath County Council. Approximately 38.5 km of the existing OHL circuit is located within the functional area of Meath County Council and approximately 23 km is within the functional area of Louth County Council. A separate planning application is being lodged with Louth County Council. The Proposed Development within the functional area of Meath County Council is located in the townlands of Cardrath, Broomfield, Balrenny, Higginstown (Slane Electoral Division), Coalpits, Mooretown (Slane Electoral Division), Cashel, Crewbane, Rossnaree, Fennor (Painestown Electoral Division), Newtown (Painestown Electoral Division), Rathdrinagh, Thurstianstown, Painestown (Painestown Electoral Division), Knockharley, Veldonstown, Kentstown, Danestown, Proudstown (Skreen Electoral Division), Macetown (Skreen Electoral Division), Painestown (Macetown Electoral Division), Frankstown, Riggins (Kilbrew Electoral Division), Reask (Kilbrew Electoral Division), Hallstown, Cabinhill, Flemingtown (Ratoath Electoral Division), Twentypark, Lagore Little, Brownstown (Ratoath Electoral Division), Bradystown, Curkeen, Commons (Ratoath Electoral Division), Gormanstown, Wilkinstown (Dunshaughlin Electoral Division), Powderlough, Raynestown, Derrockstown, Mill Land (Dunshaughlin Electoral Division), Parsonstown, Rathregan, Portan (Dunshaughlin Electoral Division), and Woodland. Five (5) temporary construction compounds and associated access routes are located in the townlands of Knockmooney, Slane, Rath, Flemingstown and Tuiterath. The Proposed Development works within the functional area of County Meath will comprise: ? the replacement (“restringing”) of the existing overhead line circuit conductor with a new higher capacity conductor; ? the strengthening of up to 25 no. tower foundations; ? the replacement of hardware and fittings, such as insulators, insulator ha

Appeals

ACP caseTypeOutcomeDecidedDistance
323566—open4 Sept 2025275 m
313658—Refused14 Sept 2023261 m

If neighbours here have appealed before and lost, the inspector's report on that case is the single most useful thing to read.

What has happened on this file

  • 9 Oct 2026 New application · observations close 13 Nov 2026
  • 9 Oct 2026 Decision