PlanningRegister.ie
Observation pack · Offaly County Council

Derryarkin , Rhode , Co. Offaly

the demolition of existing agricultural sheds and structures on-site and the construction and operation of a Materials Recovery Facility (MRF) for the acceptance and processing of up to 90,000 tonnes per annum of household, commercial and industrial (C&I), and construction and demolition (C&D) waste. Elements of the proposed development include the following. (1) The demolition of all existing agricultural sheds and structures on-site (which cover an area of 1,417 m2). (2) The construction and operation of a Materials Recovery Facility, comprising: (a) a site entrance; (b) a weighbridge; (c) truck set down and parking areas; (d) staff parking, comprising 24 parking spaces including disabled parking and electric vehicle (EV) charging; (e) a concrete yard area; (f) a fuel storage area, consisting of a diesel tank and a raised bund wall; (g) external waste storage bays; (h) skip/bin storage areas; (i) a perimeter boundary wall (4 m in height) and perimeter fencing (2.1 m in height), with a hawthorn hedgerow maintained at a height of 4.5 to 5 m and width of 1.5 to 2 m along the southern perimeter of the site; (j) an overground firewater storage tank (5.5 m in diameter and 3.8 m in height, with a maximum capacity of 78 m³); (k) a two-storey Administration Building (7.35 m in height, with an overall floor area of 396 m²); (l) a single storey MRF building (13 m in height, with an overall floor area of ca. 2,850 m² to a maximum height of 13 m), which will include waste storage and processing areas and a separate workshop area; (m) a below grade truck loading bay situated within the MRF building; (n) an on-site ESB sub-station and adjoining electrical room (2.175 m in height, with a combined floor area of 61 m²); (o) solar panels (covering a total area of 737 m²) mounted atop the proposed Administration and MRF building roofs; (p) an on-site wastewater treatment system (for wastewater generated at sanitary facilities in the Administration Building), including an associated percolation area and ancillary services; (q) a dedicated drainage system for managing uncontaminated stormwater generated on roof and non-process yard areas on-site, which will include a Continuous Water Quality Monitoring System, an underground stormwater attenuation tank (436.8 m³ in size), a Class 1 By-Pass Separator, a proposed slam shut valve (which can be triggered automatically), a hydrobrake and a proposed manhole gate valve; and (r) a separate, dedicated collection system for managing

Observations close 3 Nov 2026 26 days left
5 weeks from receipt (received 29 Sept 2026) · s.34 Planning and Development Act 2000 · art. 29 Regulations 2001 · fee €20 · council decision due 23 Nov 2026

The application

Reference
2660511 · full record
Authority
Offaly County Council
Type
PERMISSION
Status
PRE_VALIDATION
Applicant
not published by the national dataset — see the council register
Units
0
Floor area
—
Site area
7,916 m²
Received
29 Sept 2026
We first saw it
7 Oct 2026, 01:19
Decision due
23 Nov 2026
Decision
N/a

The national dataset truncates descriptions (80 characters for DLR, 70 for Fingal) and omits the applicant. The full description and the drawings are on the council register linked in step 1.

How to submit an observation

  1. Read the file on the council register.Drawings, planning statement and site notices are at http://www.eplanning.ie/OffalyCC/AppFileRefDetails/2660511/0.
  2. Write your observation.Quote 2660511 at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on.
  3. Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. Offaly County Council takes it online with the submission or at the counter.
  4. Submit before 3 Nov 2026.Online through the register above, or in writing to the Planning Department, Offaly County Council. The test is the date the authority receives it, not the date you post it.
  5. Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.

Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.

After you submit: keep the acknowledgement. Under the 2024 Act it secures your right to appeal — only the applicant and a person who made a valid observation may bring the council's decision to An Coimisiún Pleanála, within four weeks of the decision. Making a valid observation is also what buys a right of appeal: under s.37(1) of the 2000 Act, only the applicant and a person who made a valid submission or observation to the planning authority may appeal the decision to An Coimisiún Pleanála (within four weeks of the decision). Missing the five-week window closes both doors.

What the site is zoned

No current zoning polygon covers this site in the store.

Designations on or near the site

Nothing designated within 100 m of the site.

Nearby precedents within 500 m, last 5 years

Decisions

ReferenceDecisionDecidedUnitsDistanceDescription
2560511Conditional14 Apr 20260390 m1. An overall application area of c. 19.5 hectares; 2. Phased extraction of sand and gravel (wet working) over an area of c. 11.7 hectares with processing that includes crushing and screening and all ancillary works and structures; 3. Provision of new site facilities to include wheelwash (c. 35m²), weighbridge (c. 69m²); mobile welfare pod facility (c. 16m²) consisting of office, canteen, toilet and drying room; dedicated parking area, perimeter vegetation planting and fencing; 4. Access to the site will be via an existing entrance onto the local access road to the north of the site; 5. Progressive restoration of the site to naturally regenerated wildlife habitat and a permanent water body; 6. The proposed development life is for 15 years to complete extraction and restoration operations. An Environmental Impact Assessment Report (EIAR) and Natura Impact Statement (NIS) have been prepared in respect of this planning application
22490Conditional7 Nov 202300 mTHE DEVELOPMENT WILL CONSIST OF THE DEMOLITION OF EXISTING AGRICULTURAL SHEDS AND STRUCTURES ON-SITE AND THE CONSTRUCTION AND OPERATION OF A MATERIALS RECOVERY FACILITY FOR THE ACCEPTANCE AND PROCESSING OF UP TO 90,000 TONNES PER ANNUM OF HOUSEHOLD, COMMERCIAL AND INDUSTRIAL (C&I), AND CONSTRUCTION AND DEMOLITION (C&D) WASTE. ELEMENTS OF THE PROPOSED DEVELOPMENT INCLUDE THE FOLLOWING. (1) THE DEMOLITION OF ALL EXISTING SITE AGRICULTURAL SHEDS AND STRUCTURES ON-SITE (WHICH COVER AN AREA OF 1,417 M2). (2) THE CONSTRUCTION AND OPERATION OF A MATERIALS RECOVERY FACILITY, COMPRISING: (A) A SITE ENTRANCE, (B) A WEIGHBRIDGE, (C)TRUCKING SET DOWN AND PARKING AREAS, (D) STAFF PARKING, COMPRISING 24 PARKING SPACES INCLUDING DISABLED PARKING AND EV CHARGING, (E) A CONCRETE YARD AREA, (F) A FUEL STORAGE AREA, (G) EXTERNAL WASTE STORAGE BAYS, (H) SKIP / BIN STORAGE AREAS, (I) A PERIMETER BOUNDARY WALL (4 M IN HEIGHT) AND PERIMETER FENCING (2.1 M IN HEIGHT), (J) A STORMWATER DRAINAGE AND ATTENUATION SYSTEM, (K) AN ADMINISTRATION TWO-STOREY BUILDING (WITH AN OVERALL FLOOR AREA OF C. 396M2 AND C.7.35M IN HEIGHT), (L) A SINGLE STOREY MATERIALS RECOVERY FACILITY (WITH AN OVERALL FLOOR AREA OF C. 2,850M2 TO A MAXIMUM HEIGHT OF C.13M), (M) A TRUCK LOADING BAY, (N) AN ON-SITE WASTEWATER TREATMENT SYSTEM, ASSOCIATED PERCOLATION AREA AND ANCILLARY SERVICES, (O) AN ON-SITE ESB SUB-STATION AND ADJOINING ELECTRICAL ROOM (WITH A COMBINED FLOOR AREA OF 61 M2 AND 2.175 M IN HEIGHT), (P) SOLAR PANELS (COVERING A TOTAL AREA OF 737 M2) MOUNTED ATOP THE PROPOSED ADMINISTRATION AND MATERIALS RECOVERY FACILITY BUILDINGS. THE APPLICATION IS ACCOMPANIED BY AN ENVIRONMENTAL IMPACT ASSESSMENT REPORT (EIAR) AND NATURA IMPACT STATEMENT (NIS). THE PROPOSED DEVELOPMENT WILL ACCEPT UP TO 50,000 TONNES OF WASTE PER ANNUM AND OPERATE UNDER A WASTE FACILITY PERMIT FROM OFFALY COUNTY COUNCIL DURING PHASE 1 OF OPERATIONS. THE PROPOSED DEVELOPMENT WILL ACCEPT UP TO 90,000 TONNES OF WASTE PER ANNUM AND OPERATE UNDER AN INDUSTRIAL EMISSIONS LICENCE FROM THE ENVIRONMENTAL PROTECTION AGENCY DURING PHASE 2 OF OPERATIONS
23322Refused29 Aug 2023048 mROCK EXTRACTION FROM AN AREA OF LAND CONSISTING OF 3.6 HECTARES TO A LEVEL OF 54.5 METRES ABOVE ORDNANCE DATUM, RESTORATION OF AREA ON COMPLETION OF EXTRACTION AND ALL ASSOCIATED ANCILLARY FACILITIES/WORKS. ROCK WILL BE EXTRACTED BY MECHANICAL MEANS AND TRANSPORTED TO THE EXISTING MANUFACTURING AREA. THE APPLICANT IS SEEKING A 10-YEAR PLANNING PERMISSION
21247Conditional18 Feb 20220341 mA 23 YEAR PERMISSION FOR A 44.0 HECTARE EXTENSION TO AN EXISTING AUTHORISED SAND AND GRAVEL PIT COMPRISING OF THE FOLLOWING: AN EXTRACTION AREA OF 43.8 HA.; REMOVAL OF 10.2 HA. OF COMMERCIAL FORESTRY AND REMOVAL OF OVERBURDEN MATERIAL FROM THE REMAINING 33.6 HECTARES OF THE PROPOSED EXTRACTION AREA; EXTRACTION OF SAND AND GRAVEL BY MECHANICAL MEANS; UPGRADING OF THE EXISTING INTERNAL HAUL ROAD MEASURING 0.2 HA.; TRANSPORTATION OF EXTRACTED MATERIAL TO THE EXISTING AUTHORISED MANUFACTURING AREA FOR PROCESSING VIA THE INTERNAL HAUL ROAD; LANDSCAPING AND RESTORATION OF THE SITE INCLUDING SCREENING BERMS; ALL ASSOCIATED ANCILLARY FACILITIES/WORKS. THE APPLICATION IS ACCOMPANIED BY AN ENVIRONMENTAL IMPACT ASSESSMENT REPORT (EIAR)

Appeals

ACP caseTypeOutcomeDecidedDistance
501316—pending11 May 2026390 m
319023—Granted with conditions28 Apr 2026187 m
318566—Refused19 Sept 20240 m
315436—Withdrawn15 Jan 2024187 m

If neighbours here have appealed before and lost, the inspector's report on that case is the single most useful thing to read.

What has happened on this file