PlanningRegister.ie
Observation pack · South Dublin County Council

75, Idrone Park, Knocklyon, Dublin 16, D16 E7T1

Rear extension c22m, front door to be brought forward to existing porch door. Building up right-hand side (if facing) of garage in similar brick finish to existing house to narrow the garage door opening.

Observations close 14 Oct 2026 19 days left
5 weeks from receipt (received 9 Sept 2026) · s.34 Planning and Development Act 2000 · art. 29 Regulations 2001 · fee €20 · council decision due 6 Oct 2026

The application

Reference
ED26/0098 · full record
Authority
South Dublin County Council
Type
Declaration of Exemption Sect. 5
Status
Officer Allocation
Applicant
not published by the national dataset — see the council register
Units
—
Floor area
—
Site area
11 m²
Received
9 Sept 2026
We first saw it
15 Sept 2026, 20:40
Decision due
6 Oct 2026
Decision
not yet decided

The national dataset truncates descriptions (80 characters for DLR, 70 for Fingal) and omits the applicant. The full description and the drawings are on the council register linked in step 1.

How to submit an observation

  1. Read the file on the council register.Drawings, planning statement and site notices are at https://planning.agileapplications.ie/southdublin/application-details/70993.
  2. Write your observation.Quote ED26/0098 at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on.
  3. Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. South Dublin County Council takes it online with the submission or at the counter.
  4. Submit before 14 Oct 2026.Online through the register above, or in writing to the Planning Department, South Dublin County Council. The test is the date the authority receives it, not the date you post it.
  5. Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.

Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.

After you submit: keep the acknowledgement. Under the 2024 Act it secures your right to appeal — only the applicant and a person who made a valid observation may bring the council's decision to An Coimisiún Pleanála, within four weeks of the decision. Making a valid observation is also what buys a right of appeal: under s.37(1) of the 2000 Act, only the applicant and a person who made a valid submission or observation to the planning authority may appeal the decision to An Coimisiún Pleanála (within four weeks of the decision). Missing the five-week window closes both doors.

What the site is zoned

CodeObjectivePlanIn force
R2
Existing residential
RES: To protect and/or improve residential amenitySD-001:DP:south-dublin-county-development-plan-2022-20288 Mar 2022 → 8 Mar 2028

An application that accords with the zoning objective is hard to resist on principle; one that does not may be a material contravention, which the council can only grant by the s.34(6) procedure with its own notice and window.

Source: SDCC SD-001:DP:south-dublin-county-development-plan-2022-2028 · fetched 11 Sept 2026, 23:18
SourceLicenceFetchedLink
SDCC SD-001:DP:south-dublin-county-development-plan-2022-2028—11 Sept 2026, 23:18open

Designations on or near the site

  • Radon risk area × 1
    About 1 in 20 homes in this area is likely to have high radon levels

Nearby precedents within 500 m, last 5 years

Decisions

ReferenceDecisionDecidedUnitsDistanceDescription
SD26B/0344Grant permission9 Sept 2026—392 mDemolition of portions of the existing rear and side external walls at ground floor level and the rear wall of the first floor; Demolition of the existing garage roof and the existing rear utility room, and the construction of (a) A single storey extension to the rear and side of the existing dwelling; (b) The partial conversion of the existing garage to habitable accommodation; (c) A first floor extension to the rear of dwelling, including the extension of the existing roof over the proposed first floor extension; (d) The widening of the existing vehicular entrance; and (e) Associated external works, including a new front entrance, entrance steps, planter, landscaping and all ancillary site development works.
ED26/0081Declared exempt7 Sept 2026—296 mReplacing one car park space with one bike rack for bicycles to be parked for visitors to the Iona Centre. Improving accessibility and encouraging cyclists to come to the centre.
SD26A/0156WGrant permission for retention19 Aug 2026—342 mThe retention of 1.96m wide pedestrian entrance, disabled ramp, handrail, balustrading and associated site works.
SD26B/0309WGrant permission17 Aug 2026—167 mConstruction of a 32sq.m ground floor flat roof extension to the rear, providing a new utility room, extended kitchen and dining room with no.1 new rooflight; Attic conversion to the rear extending the property to two storeys to include two additional bedrooms, office space, shower room and en-suite; Two roof lights to the north facing front elevation; External insulation with brick finish to the front, side and rear facades; Ancillary site works as required to facilitate construction works.
SD26B/0225WGrant permission for retention6 Jul 2026—414 mThe development consists of re-location and enlargement of ground floor window to eastern side elevation of dwelling-house.
SD17A/0364/FEP1Grant further ext. of duration of permission2 Jul 202611446 m(a) Demolition of existing house 'Vista Montana'; (b) construction of 11 no. 3-storey houses consisting of 1 detached 5-bed and 10 semi-detached 4-bed units; (c) new access road with raised crossing at entrance off Firhouse Road; (d) provision of on-street parking and off-street parking; (e) connection to Local Authority and Irish Water storm, foul and water main systems, and all associated site works.
SD21B/0201/EPRefuse ext. of duration of permission2 Jun 2026—400 mConstruction of a two storey extension at the side and a single storey extension to the rear of existing semi-detached house; canopy at the front of the house above the main entrance and continuing over a new single storey bay window; 3 no. west facing roof lights to the rear of the house; 3 no. new west-facing roof-lights to the single storey extension to the rear of the house; 3 no. windows to the new end wall and gable; connection into existing public mains; internal reconfiguration; all with a total floor area of approx.. 49sq.m and associated site works.
SD26B/0156WGrant permission28 May 2026—251 mAmendmetns to the first floor extension previously granted planning permission Reg Ref: SD21B/0021

Appeals

ACP caseTypeOutcomeDecidedDistance
501266Planning AppealRefused25 Aug 2026435 m
322307Planning AppealGranted with conditions6 Aug 2025161 m

If neighbours here have appealed before and lost, the inspector's report on that case is the single most useful thing to read.

What has happened on this file

  • 9 Sept 2026 New application · observations close 14 Oct 2026

Generated from the Planning Register store; nothing was fetched live for this page. Source: national planning dataset, fetched 15 Sept 2026, 20:40. Not legal advice — confirm the deadline with South Dublin County Council before relying on it.