PlanningRegister.ie
Observation pack · South Dublin County Council

6 Tullyhall Drive, Lucan, Co.Dublin, K78RY86

Attic conversion with modifications to the existing gable and roof, 1no. skylight to rear and side roof, internal alterations along with all associated site works

Observations close 27 Nov 2026 1 day left
5 weeks from receipt (received 23 Oct 2026) · s.34 Planning and Development Act 2000 · art. 29 Regulations 2001 · fee €20 · council decision due 17 Dec 2026

The application

Reference
SD26B/0475W · full record
Authority
South Dublin County Council
Type
Permission
Status
REFERRAL
Floor area
22 m²
Site area
211 m²
Received
23 Oct 2026
Decision due
17 Dec 2026

How to submit an observation

  1. Read the file on the council register.Drawings, planning statement and site notices are at https://planning.agileapplications.ie/southdublin/application-details/71288.
  2. Write your observation.Quote SD26B/0475W at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on.
  3. Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. South Dublin County Council takes it online with the submission or at the counter.
  4. Submit before 27 Nov 2026.Online through the register above, or in writing to the Planning Department, South Dublin County Council. The test is the date the authority receives it, not the date you post it.
  5. Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.

Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.

After you submit: keep the acknowledgement. Under the 2024 Act it secures your right to appeal — only the applicant and a person who made a valid observation may bring the council's decision to An Coimisiún Pleanála, within four weeks of the decision. Making a valid observation is also what buys a right of appeal: under s.37(1) of the 2000 Act, only the applicant and a person who made a valid submission or observation to the planning authority may appeal the decision to An Coimisiún Pleanála (within four weeks of the decision). Missing the five-week window closes both doors.

What the site is zoned

CodeObjectivePlanIn force
R2
Existing residential
RES: To protect and/or improve residential amenitysouth dublin county development plan 2022 20288 Mar 2022 → 8 Mar 2028

An application that accords with the zoning objective is hard to resist on principle; one that does not may be a material contravention, which the council can only grant by the s.34(6) procedure with its own notice and window.

Source: South Dublin County Council development plan zoning · fetched 11 Sept 2026, 23:18
SourceLicenceFetchedLink
South Dublin County Council development plan zoning—11 Sept 2026, 23:18open

Designations on or near the site within 100 m

  • Radon risk area × 1
    About 1 in 20 homes in this area is likely to have high radon levels

Nearby precedents within 500 m, last 5 years

Decisions

ReferenceDecisionDecidedUnitsDistanceDescription
SD26B/0461WGrant permission25 Nov 2026200 mHip build up into dutch hip at attic level with window in gable wall at attic level. Dormer roof window on rear slope of roof. Dormer roof window & 2No. roof lights on front slope of roof all at attic level. Attic conversion with w.c.. First floor internal alterations.
SD26B/0457WGrant permission19 Nov 2026253 mSingle-storey pitched-roof front extension incorporating a gable feature over the front entrance door, installation of three rooflights to the front roof slope, and widening of the existing vehicular entrance.
SDZ25A/0044WGrant permission17 Sept 202684433 mDevelopment at this site (c. 3.74Ha) at the Kishoge Southwest Development Area, including lands located within development sub-sector KSW-S2 and development sub-sector KSW-S4, in the Clonburris Strategic Development Zone (SDZ) within the townland of Grange, Dublin 22. The proposed development will consist of the removal of existing hard standing and associated sub-structures and the construction of 84no. dwelling units consisting of 42no. 2-bed 3p apartments and 42no. 3-bed 5p duplexes arranged across 6no. 3-storey Blocks A-F (9,255sqm GFA) with associated communal amenity space (3,444sqm total) and all ancillary accommodation including bicycle and refuse stores. Vehicular access to development sub-sector KSW-S2 is proposed from the Clonburris Southern Link Street (as permitted under Reg. Ref. SDZ20A/0021) via local roads (as proposed under Pl. Ref. SDZ25X/0001; ACP Ref. 322638) within adjoining development sectors KSW-S1 and KSW-S3 to the north of the subject site. Vehicular access to development sub-sector KSW-S4 is proposed from the Clonburris Southern Link Street (as permitted under Reg. Ref. SDZ20A/0021) via Lynch's Lane. Within development sub-sector KSW-S4, provision is also made for a future vehicular access to directly adjoining lands in development sub-sector KSW-S4 to the east of the subject site. The development will also consist of the provision of public open space including the southern part of Kishoge Linear Park, hard and soft landscaping including internal roads, shared paths and pedestrian pathways and associated connections to adjoining lands, boundary treatments and street furniture; surface car parking (95no. spaces in total, including 5no. accessible spaces and 19no. electric vehicle charging spaces); bicycle parking (252no. spaces in total, including 210no. long-stay resident spaces and 42no. short-stay visitor spaces); 2no. ESB substations; piped infrastructural services and connections; ducting; plant; SuDS measures; attenuation basins; water crossings; water, surface water, and foul drainage infrastructure; public lighting; and all site development and excavation works above and below ground. This application is being made in accordance with the Clonburris Strategic Development Zone Planning Scheme 2019 and relates to a proposed development within the Clonburris Strategic Development Planning Scheme Area, as defined by Statutory Instrument No. 604 of 2015.
SD26B/0308WGrant permission17 Aug 2026438 mConstruction of a two storey side extension to the existing house with flat roof dormer formed at the rear of the house over the new and existing roof area; Demolition of existing single storey pitched roof rear extension and replacement with single storey pitched roof rear extension full width of property including site works and landscaping.
ED26/0068Declared not exempt17 Aug 2026146 mShed / Outhouse in rear garden - 25 sq.m in area.
SD26B/0297WGrant permission & grant retention7 Aug 2026166 mAttic conversion with hip to gable roof to rear and dormer to side to accommodate stairs to allow access to attic conversion as non-habitable storage space with roof windows to both sides. Retention for extended vehicle access all with associated ancillary works.
SD26B/0263WGrant permission10 Jul 2026389 mConversion of existing attic space comprising of modification of existing roof structure; raising of existing gable c/w window, new access stairs; 2no. roof windows to the front and flat roof dormer to the rear.
ED26/0055Declared not exempt3 Jul 2026144 mShed / Outhouse in rear garden - 25 Sq.m. in area.

Appeals

ACP caseTypeOutcomeDecidedDistance
323650Amend Planning Schema/Add Planning Schemapending15 Sept 2025122 m
322164Planning AppealGranted with conditions25 Jul 2025294 m
316119Railway Order ApplicationOther13 Nov 2024138 m
320895Planning AppealInvalid25 Sept 2024293 m
316581Planning AppealInvalid27 Apr 2023427 m

If neighbours here have appealed before and lost, the inspector's report on that case is the single most useful thing to read.

What has happened on this file

  • 23 Oct 2026 New application · observations close 27 Nov 2026

Generated from the Planning Register store; nothing was fetched live for this page. Source: national planning dataset, fetched 25 Nov 2026, 23:00. Not legal advice — confirm the deadline with South Dublin County Council before relying on it.