PlanningRegister.ie
Observation pack · South Dublin County Council

12, Tower Road, Clondalkin, Dublin 22, D22T386

Retention of the partially complete hard & soft landscaping to the front (East) of the existing dwelling. 1) permission to complete the forementioned partially complete works; 2) Proposed single storey Ground Floor Extension to the rear (West) of the existing dwelling; 3) Proposed demolition of existing addition to the side (North) of the existing dwelling at Ground Floor level; 4) Proposed alterations to the existing single storey annex to the side (North) of the existing dwelling complete with proposed First Floor Extension above; 5) Proposed associated alterations to facades; and 6) associated site works & services

Observations close 4 Jan 2027 39 days left
5 weeks from receipt (received 19 Nov 2026) · s.34 Planning and Development Act 2000 · art. 29 Regulations 2001 · fee €20 · council decision due 22 Jan 2027

The application

Reference
SD26B/0512W · full record
Authority
South Dublin County Council
Type
Retention
Status
VALID
Floor area
75 m²
Site area
656 m²
Received
19 Nov 2026
Decision due
22 Jan 2027

How to submit an observation

  1. Read the file on the council register.Drawings, planning statement and site notices are at https://planning.agileapplications.ie/southdublin/application-details/71458.
  2. Write your observation.Quote SD26B/0512W at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on.
  3. Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. South Dublin County Council takes it online with the submission or at the counter.
  4. Submit before 4 Jan 2027.Online through the register above, or in writing to the Planning Department, South Dublin County Council. The test is the date the authority receives it, not the date you post it.
  5. Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.

Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.

After you submit: keep the acknowledgement. Under the 2024 Act it secures your right to appeal — only the applicant and a person who made a valid observation may bring the council's decision to An Coimisiún Pleanála, within four weeks of the decision. Making a valid observation is also what buys a right of appeal: under s.37(1) of the 2000 Act, only the applicant and a person who made a valid submission or observation to the planning authority may appeal the decision to An Coimisiún Pleanála (within four weeks of the decision). Missing the five-week window closes both doors.

What the site is zoned

CodeObjectivePlanIn force
G1
Open space with recreation
OS: To preserve and provide for open space and recreational amenitiessouth dublin county development plan 2022 20288 Mar 2022 → 8 Mar 2028
M2
Major town centre
VC: To protect, improve and provide for the future development of Village Centressouth dublin county development plan 2022 20288 Mar 2022 → 8 Mar 2028

An application that accords with the zoning objective is hard to resist on principle; one that does not may be a material contravention, which the council can only grant by the s.34(6) procedure with its own notice and window.

Source: South Dublin County Council development plan zoning · fetched 11 Sept 2026, 23:18
SourceLicenceFetchedLink
South Dublin County Council development plan zoning—11 Sept 2026, 23:18open

Designations on or near the site within 100 m

  • NIAH-recorded building × 13
    house · house · house
  • Radon risk area × 2
    About 1 in 10 homes in this area is likely to have high radon levels · About 1 in 5 homes in this area is likely to have high radon levels
  • Recorded monument × 10
    Historic town · Ecclesiastical enclosure · Church
  • OPW flood extent nearby floodinfo.ie
    Shown as a flag only — the OPW licence does not allow us to redistribute the extent.

Nearby precedents within 500 m, last 5 years

Decisions

ReferenceDecisionDecidedUnitsDistanceDescription
ED26/0120Declared exempt25 Nov 202657 mAttic conversion with side dormer.
ED26/0115Declared exempt16 Nov 2026182 mSeeking a shopfront enhancement grant to support the replacement and improvement of the existing shopfront, enhancing the overall appearance of the premises and contributing to the visual appeal of the local street scape. Replacing sign , facia , cornice and all moulding and soffits. Lighting and Painting.
SD25A/0288WGrant permission & grant retention4 Nov 20263294 mPermission is sought for development consisting of: (i) Retention permission for a bay window to the front elevation at first-floor level of the existing dwelling, 8 no. rooflights and alterations to window openings on the existing elevations; (ii) Demolition of an existing standalone garage and (iii) Permission for the construction of 3 no. three-storey terraced dwelling houses to the side of the existing dwelling, together with a new vehicular entrance, off-street parking, boundary treatments, connection to existing public services, landscaping, and all associated site development works.
LRD26A/0005WRefuse permission20 Oct 2026408459 mThe proposed development will consist of the demolition of the existing warehouses and structures on the site and the construction of a mixed-use residential led development comprising a total of 408 no. residential units (403 apartments consisting of 24 no. studio units, 230 no. 1 bed units and 149 no. 2 bed units, and 5 no. 3 bed 2 storey houses) and 1 no. childcare facility. The proposed development will comprise the following: (a) Block 1 is a 9-storey mixed-use building comprising 64 apartments (32 no. 1 bedroom units, 32 no. 2 bedroom units), with associated private balconies; bin store; plant and switch room; esb substation; green roofs; pv panels at roof level and a childcare facility at ground level. (b) Block 2 is a 5-storey apartment building comprising 114 apartments (24 no. studio units, 54 no. 1 bedroom units, 36 no. 2 bedroom units) with associated private balconies/terraces; bin stores; bicycle parking; plant rooms; a communal roof terrace at fourth floor level; green roofs and pv panels at roof level. (c) Block 3 is a 5-storey apartment building comprising 112 apartments (68 no. 1 bedroom units, 44 no. 2 bedroom units) with associated private balconies/terraces; bicycle parking; bulky items stores; bin stores; plant and switch rooms; 2 no. esb substations; green roofs and pv panels at roof level. (d) Block 4 is a 5 storey apartment building comprising 113 apartments (76 no. 1 bedroom units, 37 no. 2 bedroom units) with associated private balconies/terraces; bin stores; bicycle stores; bulky item stores; 2 no. esb substations; plant and switch rooms; green roofs and pv panels at roof level; and undercroft car parking (62 no. car parking spaces and 2 no. motorcycle parking spaces). (e) 5 no. own-door house(comprising 2 no. 2 storey, 3-bedroom detached units; and 3 no. 2 storey, 3-bedroom terraced units) with associated private balconies/terraces. (f) The proposed development will also comprise 202 no. car parking spaces (140 spaces at surface level and 62 no. at undercroft level and including EV and Accessible spaces), 752 no. bicycle parking spaces (comprising short-term surface spaces, long-term spaces in bike stores and cargo bike spaces), 2 no. motorcycle parking spaces, refuse and storage areas, plant, landscaping, open space, boundary treatment, public lighting, drainage, and all infrastructural and engineering works necessary to facilitate the proposed development, including connections to existing services at the Ninth Lock Road and New Nangor Road. Vehicular access will be via the existing industrial estate road off Ninth Lock Road. A dedicated website has been set up for the LRD application, which may be viewed at: www.elmfieldlrd.ie.
SD26A/0196WRequest additional information8 Oct 2026107 mConstruction of a new single-storey school building(230sq.m.), soft play area (100sq.m.), and all associated site works located within the vicinity of Protected Structure ( Ref. No. 154).
SD26A/0194Grant permission6 Oct 2026338 mFrom a café to a takeaway including opening and closing times from 7:30am to 11:30pm.
SD26B/0350WGrant permission21 Sept 2026465 mDormer window at attic level to front elevation.
ED26/0072Declared exempt24 Aug 2026117 mThe provision and playing of traditional and social pub games, including darts, pool, shuffleboard, table football and similar activities within the permitted beer garden pavilion.

Appeals

ACP caseTypeOutcomeDecidedDistance
501553Planning Appealpending12 Jun 2026451 m
322854Planning AppealOther6 Oct 2025420 m
321386Planning AppealGranted with conditions19 Mar 2025314 m
320719Planning AppealGranted with conditions14 Jan 202565 m
319931Planning AppealRefused18 Dec 2024146 m
318442Building Control - Fire Safety CertificateGranted with conditions18 Dec 2024172 m
318742Planning AppealGranted12 Aug 2024172 m
318476Planning AppealRefused8 May 2024133 m

If neighbours here have appealed before and lost, the inspector's report on that case is the single most useful thing to read.

What has happened on this file

  • 19 Nov 2026 New application · observations close 4 Jan 2027

Generated from the Planning Register store; nothing was fetched live for this page. Source: national planning dataset, fetched 25 Nov 2026, 23:00. Not legal advice — confirm the deadline with South Dublin County Council before relying on it.