Rossadrehid , Co. Tipperary , E34 YP80
the construction of an existing extension and timber store to an existing dwelling and all associated site development works
The application
- Reference
- 2660875 · full record
- Authority
- Tipperary County Council
- Type
- RETENTION
- Status
- NEW APPLICATION
- Applicant
- not published by the national dataset — see the council register
- Units
- 0
- Floor area
- —
- Site area
- 2,178 m²
- Received
- 7 Sept 2026
- We first saw it
- 18 Sept 2026, 15:44
- Decision due
- 1 Nov 2026
- Decision
- N/a
The national dataset truncates descriptions (80 characters for DLR, 70 for Fingal) and omits the applicant. The full description and the drawings are on the council register linked in step 1.
How to submit an observation
- Read the file on the council register.Drawings, planning statement and site notices are at http://www.eplanning.ie/TipperaryCC/AppFileRefDetails/2660875/0.
- Write your observation.Quote
2660875at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on. - Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. Tipperary County Council takes it online with the submission or at the counter.
- Submit before 12 Oct 2026.Online through the register above, or in writing to the Planning Department, Tipperary County Council. The test is the date the authority receives it, not the date you post it.
- Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.
Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.
What the site is zoned
No current zoning polygon covers this site in the store.
Designations on or near the site
Nothing designated within 100 m of the site.
Nearby precedents within 500 m, last 5 years
Decisions
| Reference | Decision | Decided | Units | Distance | Description |
|---|---|---|---|---|---|
| 2660118 | Conditional | 13 Jul 2026 | 1 | 434 m | new single storey dwelling, proposed waste-water treatment system and percolation area, external garage, new site entrance including gate and piers and modifications to adjoining hedgerow and all necessary associated site works and services |
| 2460714 | Conditional | 22 Oct 2024 | 0 | 114 m | 1) attic conversion to existing dwelling, 2) elevational changes to existing dwelling, 3) garden shed including lean-to storage structure to side of shed, 4) revised site boundaries, 5) as constructed entrance and driveway and all associated site works |
| 2460692 | Conditional | 15 Oct 2024 | 2 | 409 m | dwelling, garage, effluent treatment system, entrance and all associated site works |
| 2360189 | Conditional | 3 Aug 2023 | 0 | 124 m | (1) the demolition of existing dwelling (2) the construction of a new replacement dwelling (3) the replacement of existing septic tank system with new waste water treatment system, percolation area and associated site works |
| 22512 | Conditional | 23 Sept 2022 | 0 | 124 m | an extension to dwelling and permission to extend and renovate existing dwelling and permission to replace existing septic tank with waste water treatment system and tertiary treatment system and associated site works |
Appeals
No appeals within 500 m in the last 5 years.
What has happened on this file
- 7 Sept 2026 New application · observations close 12 Oct 2026
- 7 Sept 2026 Decision
Generated from the Planning Register store; nothing was fetched live for this page. Source: national planning dataset, fetched 18 Sept 2026, 15:44. Not legal advice — confirm the deadline with Tipperary County Council before relying on it.