The application

Reference
2661059 · full record
Authority
Tipperary County Council
Type
RETENTION
Status
INCOMPLETED APPLICATION
Applicant
not published by the national dataset — see the council register
Units
0
Floor area
—
Site area
100 m²
Received
28 Oct 2026
We first saw it
3 Nov 2026, 23:01
Decision due
—
Decision
N/a

The national dataset truncates descriptions (80 characters for DLR, 70 for Fingal) and omits the applicant. The full description and the drawings are on the council register linked in step 1.

How to submit an observation

  1. Read the file on the council register.Drawings, planning statement and site notices are at http://www.eplanning.ie/TipperaryCC/AppFileRefDetails/2661059/0.
  2. Write your observation.Quote 2661059 at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on.
  3. Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. Tipperary County Council takes it online with the submission or at the counter.
  4. Submit before 2 Dec 2026.Online through the register above, or in writing to the Planning Department, Tipperary County Council. The test is the date the authority receives it, not the date you post it.
  5. Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.

Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.

After you submit: keep the acknowledgement. Under the 2024 Act it secures your right to appeal — only the applicant and a person who made a valid observation may bring the council's decision to An Coimisiún Pleanála, within four weeks of the decision. Making a valid observation is also what buys a right of appeal: under s.37(1) of the 2000 Act, only the applicant and a person who made a valid submission or observation to the planning authority may appeal the decision to An Coimisiún Pleanála (within four weeks of the decision). Missing the five-week window closes both doors.

What the site is zoned

No current zoning polygon covers this site in the store.

Designations on or near the site

Nothing designated within 100 m of the site.

Nearby precedents within 500 m, last 5 years

Decisions

ReferenceDecisionDecidedUnitsDistanceDescription
2460758Conditional1 Nov 2024094 m(i) for the demolition of an existing extension to the rear of dwelling, (ii) to construct a new extension to existing dwelling, (iii) to carry out elevational amendments to the existing dwelling (iv) to relocate the existing vehicular entrance (v) to construct a new waste water treatment system (vi) for a residential unit (mobile home) and continuance of use until construction on the proposed extended dwelling is complete and all associated site works
2360159Conditional2 May 20230313 man extension and renovations to dwelling including; (1) permission to construct rear extension (2) permission to develop first floor accommodation by raising the existing blockwork and roof and (3) permission to replace existing septic tank system with new waste water treatment system and percolation area and (4) associated site works
2260372Conditional26 Aug 20220313 madjusted location of front entrance wall; Adjusted location of vehicle entrance to house site;Construction of domestic garage and field shelter;and all associated site and ancillary works.
2260235Conditional11 Jul 20220363 mthe demolition of existing pillar and portion of bay window and permission to extend and renovate dwelling
211666Conditional19 Jan 20221215 ma dwelling, effluent treatment system and entrance along with all associated site works

Appeals

No appeals within 500 m in the last 5 years.

What has happened on this file

  • 28 Oct 2026 New application · observations close 2 Dec 2026
  • 28 Oct 2026 Decision

Generated from the Planning Register store; nothing was fetched live for this page. Source: national planning dataset, fetched 3 Nov 2026, 23:01. Not legal advice — confirm the deadline with Tipperary County Council before relying on it.