PlanningRegister.ie
Observation pack · Tipperary County Council

Castlequarter , Toomevara , Nenagh

Renovations & extensions to existing house with all associated site works

Observations close 10 Dec 2026 24 days left
5 weeks from receipt (received 5 Nov 2026) · s.34 Planning and Development Act 2000 · art. 29 Regulations 2001 · fee €20 · council decision due 8 Jan 2027

The application

Reference
2661084 · full record
Authority
Tipperary County Council
Type
PERMISSION
Status
NEW APPLICATION
Site area
323 m²
Received
5 Nov 2026
Decision due
8 Jan 2027

How to submit an observation

  1. Read the file on the council register.Drawings, planning statement and site notices are at http://www.eplanning.ie/TipperaryCC/AppFileRefDetails/2661084/0.
  2. Write your observation.Quote 2661084 at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on.
  3. Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. Tipperary County Council takes it online with the submission or at the counter.
  4. Submit before 10 Dec 2026.Online through the register above, or in writing to the Planning Department, Tipperary County Council. The test is the date the authority receives it, not the date you post it.
  5. Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.

Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.

After you submit: keep the acknowledgement. Under the 2024 Act it secures your right to appeal — only the applicant and a person who made a valid observation may bring the council's decision to An Coimisiún Pleanála, within four weeks of the decision. Making a valid observation is also what buys a right of appeal: under s.37(1) of the 2000 Act, only the applicant and a person who made a valid submission or observation to the planning authority may appeal the decision to An Coimisiún Pleanála (within four weeks of the decision). Missing the five-week window closes both doors.

Designations on or near the site within 100 m

  • NIAH-recorded building × 1
    Saint Joseph's Catholic Church
  • Recorded monument × 9
    R137548 · Settlement deserted - medieval · Church

Nearby precedents within 500 m, last 5 years

Decisions

ReferenceDecisionDecidedDistanceDescription
2660417Conditional22 Oct 2026300 ma single storey flat roof extension to the rear, alteration of roof profile of existing ground floor side and rear extension to a flat roof, replacement of existing pitched roof on front porch with a flat roof, widening of front vehicular access with partial removal of boundary wall
2560865Conditional21 Oct 2025165 mthe installation of 6 no. new 20m lighting columns complete with 5 no. LED pitch floodlights on each column to illuminate the training pitch and replace the current pitch lighting system on site. Permission is also sought for 13 no. streetlights on 6m lighting columns including associated civils to replace the existing perimeter walkway lighting system on site
2560422Conditional3 Jul 2025453 malterations & renovations to house with all associated site works
2460076Conditional14 Nov 2024457 mextension of the existing gate lodge for residential use and all associated ancillary development works (Protected Structure)
23236Conditional11 Apr 2024164 mreplacement of existing sub-standard pitch flood lights and poles (4 No.) with new light pillars and upgraded pitch lighting (4 No.) - LED type
2360877Conditional4 Jan 2024351 mthe storage sheds constructed to rear of property
2360321Conditional1 Nov 202319 m1. change of use of existing building storage depot to residential dwelling house & 2. modification to front elevation
22137Conditional3 Oct 202263 ma) renovation of existing roof including improved air-tightness and insulation, b) removal of existing suspended ceilings and replacement with new ceilings, c) replacement of existing lightening conductors and d) associated ancillary site works. (St Josephs church is recorded as protected structure reference S385)

What has happened on this file

  • 5 Nov 2026 New application · observations close 10 Dec 2026
  • 5 Nov 2026 Decision