(i)single storey industrial unit (gross area 2,772 sqm) and (ii) retention of gravel car parking area and (iii) revised site boundaries, landscaping, gates & boundary fencing works

Observations close 18 Sept 2026 6 days left
5 weeks from receipt (received 14 Aug 2026) · s.34 Planning and Development Act 2000 · art. 29 Regulations 2001 · fee 20 · council decision due 8 Oct 2026

The application

Reference
2660722 · full record
Authority
Wicklow County Council
Type
PERMISSION
Status
NEW APPLICATION
Applicant
not published by the national dataset — see the council register
Units
0
Floor area
Site area
Received
14 Aug 2026
We first saw it
11 Sept 2026, 18:51
Decision due
8 Oct 2026
Decision
N/a

The national dataset truncates descriptions (80 characters for DLR, 70 for Fingal) and omits the applicant. The full description and the drawings are on the council register linked in step 1.

How to submit an observation

  1. Read the file on the council register.Drawings, planning statement and site notices are at http://www.eplanning.ie/WicklowCC/AppFileRefDetails/2660722/0.
  2. Write your observation.Quote 2660722 at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on.
  3. Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. Wicklow County Council takes it online with the submission or at the counter.
  4. Submit before 18 Sept 2026.Online through the register above, or in writing to the Planning Department, Wicklow County Council. The test is the date the authority receives it, not the date you post it.
  5. Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.

Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.

After you submit: keep the acknowledgement. Under the 2024 Act it secures your right to appeal — only the applicant and a person who made a valid observation may bring the council's decision to An Coimisiún Pleanála, within four weeks of the decision. Making a valid observation is also what buys a right of appeal: under s.37(1) of the 2000 Act, only the applicant and a person who made a valid submission or observation to the planning authority may appeal the decision to An Coimisiún Pleanála (within four weeks of the decision). Missing the five-week window closes both doors.

What the site is zoned

No current zoning polygon covers this site in the store.

Designations on or near the site

Nothing designated within 100 m of the site.

Nearby precedents within 500 m, last 5 years

Decisions

ReferenceDecisionDecidedUnitsDistanceDescription
2560933Conditional12 Jan 20260116 msingle storey welfare block (Gross Area 200 Sqm) and installation of covered timber storage racks to rear of existing unit 3
2560516Refused27 Aug 20250118 m- 2 no. warehouse buildings with a gross floor area (GFA) of c. 3,364 sq.m each and a total height of c. 14.1m. Each warehouse includes a warehouse area of c. 2,419 sq.m, reception area, office, staff facilities, toilets, plant and storage areas at ground floor level, and office space, meeting rooms, staff facilities, toilets, plant and storage facilities at mezzanine level (c. 581 sq.m). - The provision of a service yard with a security hut (c. 34 sq.m) located at the main entrance, HGV unloading areas and 4 no. associated loading bay docks on the eastern elevation of each warehouse building. - The provision of 68 no. car parking spaces including 4 no. accessible spaces and 10 no. EV parking spaces serving staff and visitors. - The provision of 40 no. cycle parking spaces serving staff and visitors. - The provision of a sprinkler tank, sprinkler pump house (c. 13.3 sq.m), fire hydrant tank, hydrant pump house (c. 13.3 sq.m) and ESB substation (c. 25 sq.m) - Construction of a solar farm development consisting of photovoltaic (PV) panel arrays covering an area of approximately c. 15.7 ha on ground mounted steel frames, associated power trunk building (c. 539 sq.m) and 2 no. transformer compounds, underground cabling and ducting, new internal tracks for maintenance and all associated site services works. - Site access from the permitted development to south (WCC Reg. Ref.: 20/1088 as amended WCC Reg. Ref.: 23/62 and 24/88), which is subject to a current separate amendment application under WCC Reg. Ref.: 25/60350, and extension of the permitted inner relief road through the site. - The provision of a new statcom compound including a single storey control and valve building with a GFA of c. 253 sq.m and associated equipment adjacent to the permitted inner relief road to the south of the main site area. The proposed development also includes for the provision of associated landscaping and planting, berms, boundary treatments, internal road network, pedestrian and cyclist infrastructure, signage zones, site lighting, drainage works, sustainable drainage systems (SuDS) and all ancillary site development works
2560399Conditional16 Jul 20250476 m1) construction of a single storey extension to existing office building. 2) construction of a single storey extension to existing production building and 3) all associated and ancillary works, including reconfiguration of existing external steps and footpaths and connections to existing surface water collection network, all at existing facility
2560350Conditional27 Jun 20250305 mamendments to the Battery Energy Storage System (BESS) permitted on site, under WCC Reg. Ref.: 23/62 (an amendment to WCC Reg. Ref.: 20/1088, which was subsequently further amended under WCC Reg. Ref.: 24/ 88). The proposedamendments comprise the following: • The provision of a BESS compound with a total area of c. 1.2 ha which will accommodate self-contained batteries and integral fire suppression equipment, climate control equipment and associated electrical components (in place of the previously permitted three-storey BESS structure and adjacent ancillary structures). • A single storey BESS Switchroom located to the south of the BESS facility with a total gross floor area (GFA) of c. 191 sq.m and total height of c. 5.3m accommodating a control room, relay room, and cable basement. • Water Services Plant and Storage equipment located to the north-east of the BESS comprising a single-storey fire pump house with a total GFA of c. 39 sq.m and total height of c. 3.1m, and 2 no. fire hydrant and water storage tanks with a total height of c. 10.3m. • All associated amendments including amendments to internal access routes, landscaping and planting, boundary treatments, the provision of an acoustic barrier to the south of the BESS compound, lighting, and all associated ancillary works. The operation of the development on site will require an EPA Industrial Emissions Directive (IE) Licence
2460614Conditional26 Nov 20240103 msaw enclosure(Gross Area 145 Sqm) to end of Unit 2 and all associated site works
2488Conditional17 Jul 2024050 malterations to the development permitted under Reg. Ref. 20/1088, as amended by Reg. Ref. 23/62, and will supersede the permitted information and communications technology (ICT) facility buildings permitted on site. In summary, the development comprises the replacement of the 3 no. part one and part two storey ICT facility buildings permitted on site, with 5 no. part two and part three storey ICT facility buildings with a reduced building footprint, along with an energy centre compound. The Battery Energy Storage System permitted under Reg. Ref. 23/62 and the substation and transmission line connections permitted under ABP Ref. 315200-22 will be unaffected by the proposed alterations. An Environmental Impact Assessment Report (EIAR) has been prepared and will be submitted to the planning Authority with the planning application. An EPA-Industrial Emissions Directive (IE) licence will be applied for to facilitate the operation of the proposed development
2460253Conditional19 Jun 2024041 msingle storey industrial unit (Gross Area 945 Sqm) and all associated site works
2360464Conditional15 Mar 20240346 mconstruction of a new single storey industrial unit with ancillary 2 storey office accommodation (Total Floor Area 2310 sq.m) and all associated site development works

Appeals

No appeals within 500 m in the last 5 years.

What has happened on this file

  • 14 Aug 2026 New application · observations close 18 Sept 2026
  • 14 Aug 2026 Decision