PlanningRegister.ie
Observation pack · Wicklow County Council

Cronelea , Shillelagh , Co. Wicklow

RED III Level 1- extension of the operational life of the existing Cronelea Wind Farm and associated infrastructure (as permitted pursuant to Wicklow County Council Planning Register Reference 01/4805) for a further period of 20 years from the date of the expiry of its current operational duration. No changes are proposed to the number or dimensions of the existing permitted wind turbines. The existing wind farm comprises: (i) four (4) wind turbines; (ii) associated turbine foundations and crane hardstandings; (iii) 1.7 kilometres of on-site access tracks; and (iv) underground electrical and communications cabling. The development provides for the installation of an aviation warning light on turbines T2, T3 and T4. This planning application is accompanied by an Environmental Impact Assessment Report and an Appropriate Assessment Screening which include an assessment of the likely significant effects of the proposed development; both individually and in combination with the relevant off-site or secondary developments which will occur as a direct result of the development, including the development’s existing grid connection infrastructure which comprises an electrical substation and approximately 14km of 20kV underground electricity line located within the townlands of Cronelea, Ballymarroge, Laragh, Kilquiggin, Quigginroe, Killabeg, Coolkenna, Lumcloon, Killinure, Rath East, Rath, and Knockloe, County Wicklow; and Ballyvangour and Tullowphelim, County Carlow

Observations close 3 Nov 2026 17 days left
5 weeks from receipt (received 29 Sept 2026) · s.34 Planning and Development Act 2000 · art. 29 Regulations 2001 · fee €20

The application

Reference
2660871 · full record
Authority
Wicklow County Council
Type
PERMISSION
Status
INCOMPLETED APPLICATION
Applicant
not published by the national dataset — see the council register
Units
0
Floor area
—
Site area
14.78 ha
Received
29 Sept 2026
We first saw it
7 Oct 2026, 01:19
Decision due
—
Decision
N/a

The national dataset truncates descriptions (80 characters for DLR, 70 for Fingal) and omits the applicant. The full description and the drawings are on the council register linked in step 1.

How to submit an observation

  1. Read the file on the council register.Drawings, planning statement and site notices are at http://www.eplanning.ie/WicklowCC/AppFileRefDetails/2660871/0.
  2. Write your observation.Quote 2660871 at the top, give your name and the address the authority should reply to, and confine it to planning matters — zoning objective, height, overlooking, traffic, drainage, heritage. What you say here is what you can later appeal on.
  3. Pay the €20 fee.Every submission needs it; without it the observation is invalid and is returned. Wicklow County Council takes it online with the submission or at the counter.
  4. Submit before 3 Nov 2026.Online through the register above, or in writing to the Planning Department, Wicklow County Council. The test is the date the authority receives it, not the date you post it.
  5. Keep the acknowledgement.The council's receipt is your proof of a valid observation — see below.

Statutory basis. Section 34(1) of the Planning and Development Act 2000 (as amended) requires a planning authority to consider any submission or observation made to it in accordance with the Regulations. Article 29 of the Planning and Development Regulations 2001 (as amended) sets the window: a submission or observation must be received by the authority within five weeks beginning on the date of receipt of the application, and must be accompanied by the prescribed fee of €20. A submission received after the window, or without the fee, is invalid and the authority must return it.

After you submit: keep the acknowledgement. Under the 2024 Act it secures your right to appeal — only the applicant and a person who made a valid observation may bring the council's decision to An Coimisiún Pleanála, within four weeks of the decision. Making a valid observation is also what buys a right of appeal: under s.37(1) of the 2000 Act, only the applicant and a person who made a valid submission or observation to the planning authority may appeal the decision to An Coimisiún Pleanála (within four weeks of the decision). Missing the five-week window closes both doors.

What the site is zoned

No current zoning polygon covers this site in the store.

Designations on or near the site

  • Radon risk area × 1
    About 1 in 10 homes in this area is likely to have high radon levels

Nearby precedents within 500 m, last 5 years

Decisions

ReferenceDecisionDecidedUnitsDistanceDescription
2460106Conditional22 Oct 20240267 mthe continued operation of the existing Cronelea Upper Wind Farm; as permitted under Wicklow County Council Planning Register Reference 01/4273 (An Bord Pleanála Reference PL27.125044); for a further period of 15-years following the expiry of its current planning permission. The existing wind farm comprises (i) 3 no. wind turbines and associated turbine foundations and crane hardstandings; (ii) a site entrance and approximately 1 kilometre of site access track; (iii) an electrical control building with a gross floor area of 55 square metres; (iv) underground electrical and communications cabling; and (v) all associated ancillary site infrastructure. The proposed development does not comprise any modifications to the existing wind farm. This planning application is accompanied by an Appropriate Assessment Screening Report
211096Conditional27 Oct 20211320 m1. Conversion of a cottage/outbuilding to the side of the main house from ancillary to residential use including the provision of new window and door openings. 2. The upgrade of the sewage treatment system for the entire site

Appeals

No appeals within 500 m in the last 5 years.

What has happened on this file

  • 29 Sept 2026 New application · observations close 3 Nov 2026
  • 29 Sept 2026 Decision

Generated from the Planning Register store; nothing was fetched live for this page. Source: national planning dataset, fetched 7 Oct 2026, 01:19. Not legal advice — confirm the deadline with Wicklow County Council before relying on it.