What closes soonest 1 open window
Observations close 16 Sept 20264 days left
SD26A/0142W — application received — The development will consist of amendments to the residential development permitted under Reg. Ref. SD25A/0225W comprisi
5 weeks from receipt (12 Aug 2026) · s.34 Planning and Development Act 2000 · art. 29 Regulations 2001 · €20 to the council · 374 m away
R2 — Existing residentialsouth dublin county development plan 2022 2028 · 8 Mar 2022 – 8 Mar 2028
RES: To protect and/or improve residential amenity
What that means: An established residential area. The objective is to protect existing residential amenity as well as to provide housing — which is the objective a neighbour's objection to an overbearing extension is usually argued under.
This site is on an RZLT map — the draft map 2027 and the final map 2026 (0.04 ha). The owner is liable for an annual 3% tax on market value while it stays there. Submissions on the draft map closed 1 Apr 2026.
The development will consist of amendments to the residential development permitted under Reg. Ref. SD25A/0225W comprising: design modifications to the dwelling, including elevational changes, an increase in floor area to 677 sq m, and an increase in height to 9.15 m (ridge level); omission of the detached store (12 sq m) to the rear; and all associated site and development works above and below ground.
(a) Construct of a new 20m2 Ground floor & 4m2 1st floor extension to rear of the property.
(b) Install external insulation to all external walls of the property. The front facade external insulation will retain brick style finish in keeping with existing local properties.
To remove the existing dilapidated structure (see below appendix A) and replace it with an existing building owned by the Department of Education and Youth (see below appendix A). The replacement building is slightly larger in footprint than the original at 138m2 coming in at approx. 58m2 larger and is currently in storage. The proposal will see the 2no. classrooms be used for 1 to 1 classes, it is not anticipated that staffing and student numbers will increase as a result of the increase in floor area. The building would be relocated to the site and adapted as necessary to suit the operational needs of the school in compliance with statutory requirements and DEY supplementary design guidance, FSC and DAC reports would also be submitted to local building control authority. Works to existing building envelope to form 2 no. access and egress points to better aid accessibility to the existing building. existing window opes will be adapted to form new door openings in the existing facade rowan house itself is not a protected structure.
Retention permission for modification to planning permission SD12/0141 for the following; (A) Ground floor apartment known as 12A and (B) First Floor apartment known as 12B as part of the original 2 storey domestic extension to side (west) of property. Permission to extend by 2.0m across the rear of property at ground floor and at first floor.
Permission to consist of conversion of existing attic space comprising of modification of existing roof structure, raising of existing gable to form new metal clad straight gable with new window, new access stairs and flat roof metal clad dormer to both front and rear. Retention permission is being sought for the existing single storey front entrance porch.
SD26B/0037received 30 Jun 2026decided 8 Jul 2026271 m away
Change of use of part of the Ground Floor Level (105 sq m) and the First Floor Level (133 sq m) from a residential unit to a therapy clinic. The development will also include: internal alterations; elevational changes including the provision of a level-access ramp on the front elevation; signage; and all associated site and development works above and below ground. The existing use of part of the Ground Floor Level as a crèche / pre-school (permitted under Reg. Ref. SD21A/0021 / An Bord Pleanála Case Reference PL06S.310603) shall remain unchanged.
SD26A/0147Wreceived 17 Jun 2026decided 10 Aug 2026227 m away
Alterations to the roof including removal of existing hip roof and construction of a gable to facilitate an attic conversion, removal of existing chimney, installation of Velux windows and all associated site development works.
SD26B/0279Wreceived 8 Jun 2026decided 22 Jul 2026430 m away
Single storey extension to front of existing garage (circa 0.75m.sq.) incorporating new bay window to match existing living room window and conversion of garage (total floor areas 5.2.m.sq.) for habitable purposes / home office.
SD26B/0226Wreceived 12 May 2026decided 1 Jul 2026457 m away
Conversion of existing attic space comprising of modification of existing roof structure, raising of existing gable c/w window, new access stairs, 2no. roof windows to the front and flat roof dormer to the rear.
SD26B/0171Wreceived 10 Apr 2026decided 4 Jun 2026227 m away
`description` is truncated at source (80 chars for DLR, 70 for Fingal) and `applicant` is null nationally — NPAD publishes neither in full.
PPR addresses are geocoded, not surveyed — a sale's position is as good as its address match (`rooftop_n` says how many are address-accurate). Beds, floor area, BER and asking price come from the matched daft.ie advertisement, not from the Register, and only where a match was found (`enriched_n`).
Third-party advertisement data captured by Cara from daft.ie. Not open data: internal analysis only, no redistribution of listing content. Business-contact details (licensed PSP name and branch) are retained per Cara DECISIONS 2026-08-19; agent phone numbers and all vendor/buyer identities are dropped.
No publishable utility-capacity record within the radius. 8 records from Esb substation withheld: source licence forbids redistribution; see the operator's own register.
Public land (LDA register of relevant lands)
South Dublin County Council — Dublin city and suburbs
all-rights-reserved (esbnetworks.ie disclaimer: personal/non-commercial, no modification or republication without written ESB permission) — permission NOT sought · not redistributable — shown as a flag only
Third-party advertisement data captured by Cara from daft.ie. Not open data: internal analysis only, no redistribution of listing content. Business-contact details (licensed PSP name and branch) are retained per Cara DECISIONS 2026-08-19; agent phone numbers and all vendor/buyer identities are dropped.
all-rights-reserved (esbnetworks.ie disclaimer: personal/non-commercial, no modification or republication without written ESB permission) — permission NOT sought · not redistributable, flag only
Generated 12 Sept 2026, 23:22 from the Planning Register store. Nothing on this page was fetched live: every figure was already in the store with the fetch time shown. Deadlines are derived from published receipt and decision dates under the Planning and Development Act 2000; confirm with the planning authority before relying on them.