Moss Street
What closes soonest 1 open window
- Judicial review window closes 8 Oct 202624 days leftGrant permission with conditions8 weeks from the Commission's decision (13 Aug 2026) · s.50 Planning and Development Act 2000 · 387 m away
Where this is
- Settlement
- Dublin city and suburbs
- Electoral division
- Mansion House A
- Local electoral area
- South East Inner City
- Local authority
- Dublin City Council
Census 2022, small area 268096013
15.9% owner-occupied, 80.5% privately rented, 54.9% social. Vacancy 6.4%.
Zoning evaluated against the point
Zone Z5 - DEV PLAN 2022-2028
Z5: City Centre: To consolidate and facilitate the development of the central area, and to identify, reinforce, strengthen and protect its civic design character and dignity.
What that means: The main town centre — retail, offices, civic uses, apartments.
Source: zoning · fetched 12 Sept 2026, 02:04
| Source | Licence | Fetched | Link |
|---|---|---|---|
| zoning | CC-BY-4.0 | 12 Sept 2026, 02:04 | open |
Designations and constraints within 500 m
| Designation | Count | Examples |
|---|---|---|
| NIAH-recorded building | 291 | George's Dock Bridge; 'Famine'; CHQ Building |
| Radon risk area | 1 | About 1 in 20 homes in this area is likely to have high radon levels |
| Recorded monument | 42 | Religious house - Augustinian canons; Hospital; Boundary stone |
Sources: constraints, constraints.flood_cfram, constraints.niah, constraints.radon, constraints.smr · fetched 11 Sept 2026, 19:11
| Source | Licence | Fetched | Link |
|---|---|---|---|
| constraints | mixed — CC-BY-4.0 except OPW flood (CC-BY-NC-ND-4.0, publishable=false) | 11 Sept 2026, 19:11 | open |
| constraints.flood_cfram | CC-BY-NC-ND-4.0 · not redistributable — shown as a flag only | 11 Sept 2026, 19:11 | open |
| constraints.niah | CC-BY-4.0 | 11 Sept 2026, 19:11 | open |
| constraints.radon | CC-BY-4.0 | 11 Sept 2026, 19:11 | open |
| constraints.smr | CC-BY-4.0 | 11 Sept 2026, 19:11 | open |
Residential Zoned Land Tax
Source: rzlt · fetched 12 Sept 2026, 00:23
| Source | Licence | Fetched | Link |
|---|---|---|---|
| rzlt | CC-BY-4.0 | 12 Sept 2026, 00:23 | open |
Planning applications 240 in 5 years within 500 m
Recent decisions and applications
- A c. 0.078 Ha site at Nos. 32-35 Pearse Street, Dublin 2 (all Protected Structures)., The site is generally bound to the south by Pearse Street, and to the north by Brunswick Villas, Dublin 2. Registered ApplicationPROTECTED STRUCTURE: Esprit Investments Limited intend to apply for permission for development at this c. 0.078 Ha site at Nos. 32-35 Pearse Street, Dublin 2 (all Protected Structures). The site is generally bound to the south by Pearse Street and to the north by Brunswick Villas, Dublin 2. The proposed development, which will provide a total of 21 No. residential units (4 No. 2-bed apartments within Nos. 32-35 Pearse Street and 17 No. apartments (4 No. studios; 11 No. 1-bed units; and 2 No. 2-bed units) within a new residential building), will principally consist of the demolition (628 sq m) of all existing structures to the rear of Nos. 32-35 Pearse Street and the construction of a new part-6 to part-7 storey residential building (1,204 sq m). The development will also include: restoration, repair and internal modification of Nos. 32, 33, 34 and 35 Pearse Street; the change of use of the ground floor level of No. 33 Pearse Street from office to retail (49 sq m) and the first and second floor levels from office to residential (106 sq m); the change of use of the first floor level of No. 34 Pearse Street from retail to residential (53 sq m) and the second floor level from office to residential (53 sq m); the change of use of the first and second floor levels of No. 35 Pearse Street from office to residential (100 sq m); and the provision a single-storey extension to the rear of No. 32 Pearse Street (78 sq m). The existing/permitted uses at ground floor levels of No. 32 Pearse Street (a café/restaurant), No. 34 Pearse Street (retail) and No. 35 Pearse Street (retail) will remain unchanged. The existing uses at first and second floor levels of No. 32 Pearse Street (a residential unit) will also remain unchanged. The development will also include: elevational works to Nos. 32-35 Pearse Street, comprising the repair, cleaning and repointing of the brickwork; the removal of non-original render to the rear elevations of Nos. 33 and 35; the reinstatement of multi-pane sash windows to the rear elevations of Nos. 32-35 Pearse Street; hard and soft landscaping; bicycle parking; blue/green roofs; bin storage; plant; gates; and all associated site development works above and below ground.
- 1, 3, 5, 7, 9 Tara Street Dublin 2 and 5, 6 & 7 George's Quay, Dublin 2 Registered ApplicationWe, Greybirch Limited, intend to apply for planning permission at this site, of c. 0.1346 ha, at Nos. 1, 3, 5, 7, 9 Tara Street, Dublin 2 and Nos. 5, 6, 7 George’s Quay, Dublin 2. The proposed development will amend DCC Reg Ref 5042/22 and will include • Demolition of Nos. 5, 6, 7 George’s Quay and replacement with a new two storey building, which includes a retractable roof. • The omission of the roof garden and minor alterations to the elevations on the retained and refurbished Tara Street buildings. • Reduction in the number of permitted concessions from 13 no. units to 9 no. units. • Omit permitted basement extension, resulting in no changes to the existing basement. The proposal also includes all associated works to enable the development of the proposal. The remainder of the development will remain as permitted by Reg. Ref. 5042/22.
- 21 Westland Row, The University College of Dublin, Dublin 2 Registered ApplicationPROTECTED STRUCTURE: The construction of a new external access ramp and associated works to improve access to the existing front door at No 21 Westland Row, the University of Dublin Trinity College, Dublin 2. The proposed development is within the curtilage of a Protected Structure.
- 19-20 Lombard Street East, and 112-113 & 114 Townsend Street, Dublin 2 Registered ApplicationWe, ORHRE Management Services Limited, intend to apply for permission for development at this site at 19-20 Lombard Street East and 112-113 & 114 Townsend Street, Dublin 2. The proposals comprise amendments to planning permission DCC Reg. Ref.: WEB2350/25. The development will consist of the demolition of existing vacant two storey building (c. 173 sqm) at the southern perimeter of the site and the construction of a 5 storey (16.2 metres above ground level) extension (c. 300 sqm) of the permitted hostel development providing an additional 8 no. bedrooms (105 no. in total) at upper floors, publicly accessible café (c. 67 sqm) fronting Lombard Street (with external seating area and 2 no. visitor bicycle parking spaces), ESB substation, meter room, bike store and fire escape (accessed from the western elevation) at ground floor level, reconfiguration of layouts at basement to sixth floor level (additional 56 sqm), associated elevational changes to the southern, eastern and western elevations to provide additional and reconfigured windows, and material finishes, relocation of permitted signage area 01 from southern elevation to eastern elevation above café at ground floor level, green roof and plant (first floor roof level), minor amendments to roof level at sixth floor arising from fire certification and all associated works to facilitate the development.
- Citigroup Building, 1 North Wall Quay, Dublin 1, D01 T8Y1. The site is bound by North Wall Quay to the south, Commons Street to the west, Clarion Quay/Alderman Way to the north and an access ramp to the existing basement to the east. D01 T8Y1 Registered ApplicationWe, NWQ Devco Limited, intend to apply for a 10 year planning permission for development at a site consisting of the CitiGroup Building, 1 North Wall Quay, Dublin 1, D01 T8Y1. The site is bound by North Wall Quay to the south, Commons Street to the west, Clarion Quay/Alderman Way to the north and an access ramp to the existing basement to the east. The site area is c. 0.88 ha. The proposed development will consist of: • Partial demolition, removal of existing facades and extension of existing 5-6 storeys office building; • The resulting proposed extended development (c. 60,119 sq.m) ranges in height from 6 no. to 12 no. storeys in height over existing basement comprising office accommodation, 2 no. hotels, a retail/café unit and a community space; • The proposed development comprises 4 no. blocks: o Block A (6-11 storeys) comprises office accommodation. o Block B (12 no. storeys) comprises office accommodation. o Block C (10 storeys) will comprise a hotel with 201 no. bedrooms; o Block D (6-7 storeys) will comprise a hotel with 135 no. bedrooms; o It is noted that there will be a change of use of part of the existing retained floor area from office to hotel (c. 12,847 sqm) to accommodate the proposed hotels. • 1 no. retail/cafe unit (91 sq.m) is provided within Block D at ground floor level; • 1 no. internal community space (654 sq.m) is provided at ground floor level; • A shared entrance for Blocks C and D; • Provision of a shared atrium between Block C and Block D; • Outdoor terraces at 5th, 6th, 7th, 9th, and 11th floor levels; • Green roofs and blue roofs are provided across the scheme; • 32 no. car parking spaces will be provided at basement level to serve the development. This represents a reduction of 132 no. car parking spaces in comparison to the existing office building on the site; • 456 no. bicycle spaces (inc. and 4 no. motorcycle spaces are proposed at basement level; • 18 no. short-stay bicycle space (9 no. Sheffield stands) are proposed at surface level; • The development includes the fill and cover of existing access ramp to existing basement to provide a landscaped community pocket park (244 sq.m) to the east of the building. The park will include a pedestrian link from North Wall Quay to Clarion Quay; • Provision of upgrades to existing public realm within application site including public footpaths along North Wall Quay, Commons Street and Clarion Quay; • All ancillary and associated works to facilitate the development including plant, pv panels, switch rooms, generators, water tanks, sprinkler plant, ESB substations, landscaping, telecommunications infrastructure and utilities connections and infrastructure. An Environmental Impact Assessment Report and Natura Impact Statement have been prepared in respect of the proposed development and have been submitted with the planning application.
- 1, 3, 5, 7, 9 Tara Street & 5, 6, 7 George's Quay, Dublin 2 Application declared invalidWe, Greybirch Limited, intend to apply for planning permission at this site, of c. 0.1346 ha, at Nos. 1, 3, 5, 7, 9 Tara Street, Dublin 2 (D02X995, D02EP64, D02YD53, D02YD52, D02Y662, D02F991) and Nos. 5, 6, 7 George’s Quay, Dublin 2, (D02FR63, D02KW29). The proposed development will amend DCC Reg Ref 5042/22 and will include • Demolition of Nos. 5, 6, 7 George’s Quay and replacement with a new two storey building, which includes a retractable roof. • The omission of the roof garden and minor alterations to the elevations on the retained and refurbished Tara Street buildings. • Reduction in the number of permitted concessions from 13 no. units to 9 no. units. • Omit permitted basement extension, resulting in no changes to the existing basement. The proposal also includes all associated works to enable the development of the proposal. The remainder of the development will remain as permitted by Reg. Ref. 5042/22.
- Citigroup Building, 1 North Wall Quay, Dublin 1, D01 T8Y1 The site is bound by North Wall Quay to the South, Commons Street to the West, Clarion Quay/Alderman Way to the North and an access ramp to the existing basement to the East., D01 T8Y1 Application declared invalidWe, NWQ Devco Limited, intend to apply for a 10 year planning permission for development at a site consisting of the CitiGroup Building, 1 North Wall Quay, Dublin 1, D01 T8Y1. The site is bound by North Wall Quay to the south, Commons Street to the west, Clarion Quay/Alderman Way to the north and an access ramp to the existing basement to the east. The site area is c. 0.88 ha. The proposed development will consist of: • Partial demolition, removal of existing facades and extension of existing 5-6 storeys office building; • The resulting proposed extended development (c. 60,119 sq.m) ranges in height from 6 no. to 12 no. storeys in height over existing basement comprising office accommodation, 2 no. hotels, a retail/café unit and a community space; • The proposed development comprises 4 no. blocks: o Block A (6-11 storeys) comprises office accommodation. o Block B (12 no. storeys) comprises office accommodation. o Block C (10 storeys) comprises a hotel with 201 no. bedrooms. o Block D (6-7 storeys) comprises a hotel with 135 no. bedrooms. • 1 no. retail/cafe unit (91 sq.m) is provided within Block D at ground floor level; • 1 no. internal community space (654 sq.m) is provided at ground floor level; • A shared entrance for Blocks C and D; • Provision of a shared atrium between Block C and Block D; • Outdoor terraces at 5th, 6th, 7th 9th, and 11th floor levels; • Green roofs and blue roofs are provided across the scheme; • 32 no. car parking spaces will be provided at basement level to serve the development. This represents a reduction of 132 no. car parking spaces in comparison to the existing office building on the site; • 456 no. bicycle spaces (inc. and 4 no. motorcycle spaces are proposed at basement level; • 18 no. short-stay bicycle space (9 no. Sheffield stands) are proposed at surface level; • The development includes the fill and cover of existing access ramp to existing basement to provide a landscaped community pocket park (244 sq.m) to the east of the building. The park will include a pedestrian link from North Wall Quay to Clarion Quay; • Provision of upgrades to existing public realm within application site including public footpaths along North Wall Quay, Commons Street and Clarion Quay; • All ancillary and associated works to facilitate the development including plant, pv panels, switch rooms, generators, water tanks, sprinkler plant, ESB substations, landscaping, telecommunications infrastructure and utilities connections and infrastructure. An Environmental Impact Assessment Report and Natura Impact Statement have been prepared in respect of the proposed development and have been submitted with the planning application.
- Unit 1, Talbot Mall, Talbot Street, Dublin 1 Registered ApplicationThe erection of a new operator signage on the fascia and three clipper frame signs on the interior of the windows. The development includes all works associated with the proposed development.
- 21 Westland Row, The University Of Dublin Trinity College, Westland Row, Dublin 2 Application declared invalidPROTECTED STRUCTURE: The construction of a new external access ramp and associated works to improve access to the existing front door at No 21 Westland Row, the University of Dublin Trinity College, Dublin 2. The proposed development is within the curtilage of a Protected Structure.
- Pret A Manger, Pearse Street Station, Westland Row, Dublin 2, Ireland, D02 RV00 Registered ApplicationPROTECTED STRUCTURE: RETENTION: Carebrook Partnership Ltd. is applying to Dublin City Council for retention permission for illuminated signage advertising Pret A Manger café outlet to the north-west (front façade) of the building including two internally illuminated roundal signs on two doors and two internally illuminated projecting signs on the brick facade all at Pret A Manger, Pearse Street Station, Westland Row, Dublin 2, Ireland, D02 RV00, which is part of a protected structure (RPS Reg ref. 8520).
`description` is truncated at source (80 chars for DLR, 70 for Fingal) and `applicant` is null nationally — NPAD publishes neither in full.
Source: npad · fetched 13 Sept 2026, 20:39
| Source | Licence | Fetched | Link |
|---|---|---|---|
| npad | CC-BY-4.0 | 13 Sept 2026, 20:39 | open |
Appeals 31 in 5 years within 500 m
- ACP 500887 on WEB5358/25 Granted with conditions
- ACP 501846 on WEB2237/26 Pending
- ACP 323120 on WEB2729/24 Refused
- ACP 324028 on 4674/22 Refused
- ACP 501651 on WEB6103/25 Open
- ACP 500853 on WEB5774/25 Granted with conditions
- ACP 501478 on WEB1608/26 Pending
- ACP 500457 on WEB2350/25 Withdrawn
- ACP 321501 on FRG2105024DC Refused
- ACP 323272 on RZLT000259 Other
Source: acp · fetched 12 Sept 2026, 00:05
| Source | Licence | Fetched | Link |
|---|---|---|---|
| acp | CC-BY-4.0 | 12 Sept 2026, 00:05 | open |
Commencement notices 70 in 3 years within 500 m
- 22/23 Talbot Street, Dublin 1, D01 DW02 — Commencement notice
- Trinity College, Dublin 2, D02 DP29 — Short commencement notice
- 111 Talbot Street, Dublin 1, D01 H0F4 — Commencement notice
- 2 Connolly Station, Dublin 1, D01 H592 — Seven day notice
- 24/26 City Quay, Dublin, Dublin 2, D02 NY19 — Short commencement notice
- Custom House Quay, Dublin, Dublin 1, D01 Y6H7 — Seven day notice
- 64 Sráid Ghairdinéir Íochtarach, Dublin 1, D01 V8P5 — Short commencement notice
- 27-32 Talbot Street, Dublin 1, D01 A6F4 — Commencement notice
- Tara Street, Dublin, Dublin 2, D02HX37 — Seven day notice
- Building East, WWRC Quayside Building, Custom House Quay, Dublin 1, Dublin, Dublin 1, D01 KF84 — Commencement notice
One notice can cover many buildings — count notices, never building rows, or a single multi-unit scheme reads as a trend (T11).
Source: bcms · fetched 13 Sept 2026, 23:40
| Source | Licence | Fetched | Link |
|---|---|---|---|
| bcms | CC-BY-4.0 | 13 Sept 2026, 23:40 | open |
Sales 51 in 36 months within 500 m
€248,000 – €1,200,000, 24 Jan 2024 to 22 Apr 2026.
| Address | Sold | Price | Asking | Type | Beds | m² | €/m² | BER | Dist. |
|---|---|---|---|---|---|---|---|---|---|
| 273 CUSTOM HOUSE HARBOUR, CUSTOM HOUSE QUAY, DUBLIN 1 | 22 Apr 2026 | €675,000 | €675,000 | Apartment | 3 | 125 | 5,400 | D1 | 483 m |
| 14 COLLEGE CLOSE, TARA ST, DUBLIN 2 | 7 Nov 2025 | €320,000 | €300,000 | Apartment | 1 | 38 | 8,421 | C2 | 281 m |
| 8 ARCHERS WOOD CLOSE, ARCHERS WOOD, DELGANY | 6 Nov 2025 | €1,028,000 | €1,050,000 | Detached | 4 | 183 | 5,617 | A2 | 417 m |
| APT 311 TALBOT HALL, TALBOT ST, DUBLIN 1 | 15 Oct 2025 | €273,000 | €285,000 | Apartment | 1 | 56 | 4,875 | D2 | 427 m |
| 29 APT 2, GEORGES QUAY, DUBLIN 2 | 1 Oct 2025 | €410,000 | €410,000 | Apartment | 2 | 53 | 7,736 | C2 | 273 m |
| 34 CORN EXCHANGE, POOLBEG ST, DUBLIN 2 | 25 Sept 2025 | €422,500 | €390,000 | Apartment | 2 | — | — | C1 | 333 m |
| 25 TRINITY PLAZA, TOWNSEND ST, DUBLIN 2 | 28 Aug 2025 | €518,000 | €425,000 | Apartment | 2 | 66 | 7,848 | B3 | 251 m |
| 102 WESTLAND SQUARE, LOWER SANDWITH STREET, DUBLIN 2 | 26 Jun 2025 | €375,000 | €375,000 | Apartment | 2 | 60 | 6,250 | D1 | 441 m |
| 29 CORN EXCHANGE, POOLBEG ST, DUBLIN 2 | 16 Jun 2025 | €290,000 | €295,000 | Apartment | 1 | 43 | 6,744 | C2 | 333 m |
| 88 WESTLAND SQ, SANDWITH ST, DUBLIN 2 | 30 May 2025 | €300,000 | €265,000 | Apartment | 1 | 37 | 8,108 | D1 | 363 m |
PPR addresses are geocoded, not surveyed — a sale's position is as good as its address match (`rooftop_n` says how many are address-accurate). Beds, floor area, BER and asking price come from the matched daft.ie advertisement, not from the Register, and only where a match was found (`enriched_n`).
Sources: cara_listings, daft_gateway, ppr · fetched 11 Sept 2026, 20:14
| Source | Licence | Fetched | Link |
|---|---|---|---|
| cara_listings | Third-party advertisement data captured by Cara from daft.ie. Not open data: internal analysis only, no redistribution of listing content. Business-contact details (licensed PSP name and branch) are retained per Cara DECISIONS 2026-08-19; agent phone numbers and all vendor/buyer identities are dropped. | 11 Sept 2026, 20:14 | open |
| daft_gateway | Third-party advertisement data read from daft.ie's own JSON gateway. Not open data: internal analysis only, no redistribution of listing content. Business-contact details (the licensed PSP's name and branch) are retained per Cara DECISIONS 2026-08-19; agent phone numbers, profile images and all media URLs are dropped at fetch time and never written down. Vendor and buyer identities are not in this data. | 13 Sept 2026, 22:10 | open |
| ppr | PSI — PSRA re-use terms (psr.ie/re-use-of-public-sector-information). Free re-use in any format provided the source and PSRA copyright are acknowledged, the data is reproduced accurately and not used misleadingly, and it is NOT used 'for the principal purpose of advertising or promoting a particular product or service'. Attribution: 'Contains PSRA Residential Property Price Register data, © Property Services Regulatory Authority.' | 13 Sept 2026, 20:32 | open |
Consultations 4 matched by place
- Public Participation in the Identification of New Bathing Waters 11 days left
- iMEND 1 - Portobello Community Engagement 18 days left
- Lansdowne Valley Park Active Travel Scheme 24 days left
- Dublin District Heating Project Part 8 37 days left
Source: consult · fetched 12 Sept 2026, 02:04
| Source | Licence | Fetched | Link |
|---|---|---|---|
| consult | public | 12 Sept 2026, 02:04 | open |
Council items 10 in 24 months
- Report No. 167/2026 of the Chief Executive (R. Shakespeare) - Proposed refurbishment and adaptive reuse of a 3-storey vacant office building at 14/15 Fitzwilliam Quay, Dublin 4.
- One vacancy on the Board of the Ringsend Toll Bridge Designated Activity Company following the resignation of Councillor Christy Burke (Central Area)
- IrDEA Annual Conference 2026, 30th September 2026 - Radison Blu Royal Hotel, Golden Lane, Dublin 8
- Presentation - 2nd Notification of Proposed Part 8 refurbishment and adaptive reuse of 3-storey vacant office building to provide 15 no. 1 bedroom apartments located at 14/15 Fitzwilliam Quay, Ringsend, Dublin 4
- COUNCILLOR MANNIX FLYNN To ask the Chief Executive to initiate a survey regarding the potential of opening up what remains of the Viking settlements that were covered over during the building of Civic Offices? This present site is a huge significance and heritage importance not just for Dublin and Ireland but for the European cultural history.
- COUNCILLOR MICHEÁL MACDONNCHA To ask the Chief Executive if he will publish the consultants' report on the alleged extent of upgrading required, and alleged cost of such upgrading, for the Civic Offices, Wood Quay.
- Report No. 104/2026 of the A/Executive Manager (B. Corry) - With reference to the proposed grant of a 5-year Short Term Business Letting of Rooms at the Pigeon House Hotel, Pigeon House Road, Dublin 4 to Celtic Anglian Water Limited.
- One vacancy on the Board of the Ringsend Toll Bridge Designated Activity Company following the resignation of Councillor Christy Burke (Central Area)
- COUNCILLOR KARL STANLEY To ask the Chief Executive to provide a report detailing DCC's due diligence done relating to archaeological risks of further development of the Wood Quay site. Specifically, report is to outline any engagement or correspondence with archaeological experts (either within DCC or external) to assess legal risks relating to
- COUNCILLOR GAYLE RALPH To ask the Chief Executive to provide a detailed report on the current and projected use of the Wood Quay Civic Offices, including: The actual daily staff occupancy levels for each day of the week. If this data is not currently available, why not, and what is the estimated occupancy? Whether the City Manager will commit to publishing a
Source: moderngov · fetched 13 Sept 2026, 21:50
| Source | Licence | Fetched | Link |
|---|---|---|---|
| moderngov | public | 13 Sept 2026, 21:50 | open |
Capacity and public land
No publishable utility-capacity record within the radius. 85 records from Esb substation withheld: source licence forbids redistribution; see the operator's own register.
Public land (LDA register of relevant lands)
- Dublin Docklands Development Authority — Dublin city and suburbs
- Dublin Docklands Development Authority — Dublin city and suburbs
- Dublin Docklands Development Authority — Dublin city and suburbs
- Dublin Docklands Development Authority — Dublin city and suburbs
- The Office of Public Works — Dublin city and suburbs
- Córas Iompair Éireann — Dublin city and suburbs
- Dublin Docklands Development Authority — Dublin city and suburbs
- Dublin Docklands Development Authority — Dublin city and suburbs
Sources: esbn, lda_lands · fetched 11 Sept 2026, 16:42
| Source | Licence | Fetched | Link |
|---|---|---|---|
| esbn | all-rights-reserved (esbnetworks.ie disclaimer: personal/non-commercial, no modification or republication without written ESB permission) — permission NOT sought · not redistributable — shown as a flag only | 11 Sept 2026, 16:42 | open |
| lda_lands | CC-BY-4.0 | 11 Sept 2026, 16:43 | open |
Schools and public transport within 1.0 km
Schools
- CITY QUAY NS
- C.B.S. Westland Row
- CENTRAL INFS SCHOOL
- CENTRAL SENIOR MXD N S
- SCOIL CHAOIMHIN
- Larkin Community College
- RUTLAND NATIONAL SCHOOL
- St Laurence O'Toole's National School
Stops 194 · routes 1, 100X, 101, 101X, 103, 103X, 105X, 109, 109A, 109B, 109X, 11, 111, 111X, 115, 115C, 115X, 116, 118, 11B, 120, 120A, 120B, 120E, 120F, 120X, 122, 125, 126, 126A, 126B, 126D, 126E, 126N, 126T, 126U, 126X, 13, 130, 130A, 132, 133, 14, 142, 15, 150, 151, 15A, 15B, 15D, 16, 16D, 179, 180, 181, 19, 191, 193, 194, 2, 22, 23, 24, 245X, 27, 27A, 27B, 27X, 29n, 30, 300, 31n, 32, 32X, 33, 33D, 33E, 33X, 33n, 37, 38, 38A, 38B, 38D, 39, 39A, 39X, 4, 40D, 41, 41B, 41C, 41D, 41X, 42, 42n, 43, 44, 44D, 46n, 47, 49n, 500, 500N, 500X, 501, 502, 503, 505, 505X, 506, 506X, 507, 51D, 52, 53, 56A, 6, 60, 600, 65, 65B, 660, 68, 68A, 69, 69X, 69n, 7, 70, 700, 700X, 702, 704x, 705x, 707, 70n, 717, 721, 73, 735, 736, 74, 740, 740A, 740X, 761, 763, 77A, 77X, 77n, 782, 783, 784, 785, 7A, 7B, 7D, 7E, 7n, 80, 82, 836, 845, 847, 84n, 853, 860, 870, 88n, 900, 901, 901M, 910, 912, 932, 932A, 933, 933A, 980, 980A, 980B, C1, C2, C3, C4, C5, C6, Commuter, DART, E1, E2, F1, F2, F3, G1, G2, GD01, GD02, Green, H1, H2, H3, NX, P29, Red, X1, X2, X25, X26, X27, X28, X30, X31, X32, rail
- Moss Street
- George's Quay
- George's Quay
- George's Quay
- Prince's St South
- Tara Street
- IFSC
- Tara Street
Sources used in this report
| Section | Source | Licence | Fetched |
|---|---|---|---|
| Location | places | CC-BY-4.0 | 11 Sept 2026, 21:28 |
| Parcel | parcels | CC-BY-4.0 | 11 Sept 2026, 19:06 |
| Zoning | zoning | CC-BY-4.0 | 12 Sept 2026, 02:04 |
| Constraints | constraints | mixed — CC-BY-4.0 except OPW flood (CC-BY-NC-ND-4.0, publishable=false) | 11 Sept 2026, 19:11 |
| Constraints | constraints.flood_cfram | CC-BY-NC-ND-4.0 · not redistributable, flag only | 11 Sept 2026, 19:11 |
| Constraints | constraints.niah | CC-BY-4.0 | 11 Sept 2026, 19:11 |
| Constraints | constraints.radon | CC-BY-4.0 | 11 Sept 2026, 19:11 |
| Constraints | constraints.smr | CC-BY-4.0 | 11 Sept 2026, 19:11 |
| Rzlt | rzlt | CC-BY-4.0 | 12 Sept 2026, 00:23 |
| Planning | npad | CC-BY-4.0 | 13 Sept 2026, 20:39 |
| Appeals | acp | CC-BY-4.0 | 12 Sept 2026, 00:05 |
| Commencements | bcms | CC-BY-4.0 | 13 Sept 2026, 23:40 |
| Sales | cara_listings | Third-party advertisement data captured by Cara from daft.ie. Not open data: internal analysis only, no redistribution of listing content. Business-contact details (licensed PSP name and branch) are retained per Cara DECISIONS 2026-08-19; agent phone numbers and all vendor/buyer identities are dropped. | 11 Sept 2026, 20:14 |
| Sales | daft_gateway | Third-party advertisement data read from daft.ie's own JSON gateway. Not open data: internal analysis only, no redistribution of listing content. Business-contact details (the licensed PSP's name and branch) are retained per Cara DECISIONS 2026-08-19; agent phone numbers, profile images and all media URLs are dropped at fetch time and never written down. Vendor and buyer identities are not in this data. | 13 Sept 2026, 22:10 |
| Sales | ppr | PSI — PSRA re-use terms (psr.ie/re-use-of-public-sector-information). Free re-use in any format provided the source and PSRA copyright are acknowledged, the data is reproduced accurately and not used misleadingly, and it is NOT used 'for the principal purpose of advertising or promoting a particular product or service'. Attribution: 'Contains PSRA Residential Property Price Register data, © Property Services Regulatory Authority.' | 13 Sept 2026, 20:32 |
| Consultations | consult | public | 12 Sept 2026, 02:04 |
| Council items | moderngov | public | 13 Sept 2026, 21:50 |
| Capacity | esbn | all-rights-reserved (esbnetworks.ie disclaimer: personal/non-commercial, no modification or republication without written ESB permission) — permission NOT sought · not redistributable, flag only | 11 Sept 2026, 16:42 |
| Public land | lda_lands | CC-BY-4.0 | 11 Sept 2026, 16:43 |
| Projects | social_housing | CC-BY-SA-4.0 | 11 Sept 2026, 20:13 |
| Amenities | gtfs | CC-BY-4.0 | 11 Sept 2026, 19:16 |
| Amenities | schools | CC-BY-4.0 | 11 Sept 2026, 16:41 |
| Deadlines | acp | CC-BY-4.0 | 12 Sept 2026, 00:05 |
| Deadlines | consult | public | 12 Sept 2026, 02:04 |
| Deadlines | moderngov | public | 13 Sept 2026, 21:50 |
| Deadlines | npad | CC-BY-4.0 | 13 Sept 2026, 20:39 |
| Deadlines | rzlt | CC-BY-4.0 | 12 Sept 2026, 00:23 |
Generated 14 Sept 2026, 19:12 from the Planning Register store. Nothing on this page was fetched live: every figure was already in the store with the fetch time shown. Deadlines are derived from published receipt and decision dates under the Planning and Development Act 2000; confirm with the planning authority before relying on them.