PlanningRegister.ie
Planning report · Dublin City Council · 500 m around the house · the last 12 months · 19 Oct 2026, 04:12

Belgrove Park, Chapelizod

53.35196, -6.34945

Homes here mostly date from the 1960s. 6 planning files on this house, the latest from 2025. Home extensions nearby almost always get approved (94%). 23 homes approved 337 m away haven't started.

See on the mapWatch this area

How planning works, with this area's numbers

steps can overlap · medians for home extensions within 1.5 km, 10 years
  1. 1ApplySite notice up, plans online
  2. 2Comments5 weeks, €20. Comment to keep your right to appeal
  3. 3Decision8 weeks by law. Here 55 days
  4. 4Appeal window4 weeks after the decision
  5. 5AppealHere about 4 months
  6. 6PermissionLasts 5 years
  7. 7StartStart notice to the council. Here about 5 months after
  8. 8Sign-offCompletion cert, or the owner opts out
Question 1

What's the planning story of this house?

Figure 1

When it was built, and the rules since

Most homes here were built 1961–70, around when planning permission began (1964). 6 planning files on this house, the latest from 2026.

Timeline from 1955: planning permission needed from October 1964, building regulations from June 1992, building records online from March 2014, sign-off opt-out from September 2015. Most homes here were built 1961–1970. 6 planning files on this house.1960197019801990200020102020Oct 1964permission neededJun 1992building regulationsMar 2014building records onlineSep 2015owners may opt out of sign-offThis houseAll of Belgrove ParkBuilt: most homes in this small area date from 1961–1970 (census estimate)most built2026: WEB6008/25 · attic or dormer, approved2024: 3960/24 · porch, approved2024: 3913/24 · porch, withdrawn or invalid2024: WEB1323/24 · porch, refused2022: WEB1477/21 · attic or dormer, approved2020: WEB1607/20 · attic or dormer, refused2020: 3 files on Belgrove Park2021: 3 files on Belgrove Park2022: 1 file on Belgrove Park2024: 3 files on Belgrove Park2025: 1 file on Belgrove Park11 files

Each line is a rule that applies to work done after it.

MeasuredEstimatecouncil register via NPAD · build years: CSO Census 2022, small area

  1. 2026
    WEB6008/25 · attic or dormer · approved 2026 · started, no sign-off needed
    approvedstartedsigned off?
  2. 2024
    3960/24 · porch · approved 2024 · not started, runs out 2029
    approvedstartedsigned off
  3. 2024
    3913/24 · porch · withdrawn
    approved?started?signed off?
  4. 2024
    WEB1323/24 · porch · refused 2024
    approvedstarted?signed off?
  5. 2022
    WEB1477/21 · attic or dormer · approved 2022 · started, no sign-off needed
    approvedstartedsigned off?
  6. 2020
    WEB1607/20 · attic or dormer · refused 2020
    approvedstarted?signed off?
On this site
R2
Zoning · Existing residential
No
Protected or listed · on the council's list
No
Vacant land tax · lived-in homes don't pay it
1 in 10
Radon (EPA) · homes with high radon
Zoning, protection, tax and flood: the detail
Zoning
What it says

Zone Z1 - DEV PLAN 2022-2028

ZoningR2 · Existing residential
What it says

Z1: Sustainable Residential Neighbourhoods: To protect, provide and improve residential amenities.

An established residential area. The objective is to protect existing residential amenity as well as to provide housing — which is the objective a neighbour's objection to an overbearing extension is usually argued under.

development plan 2022 2028 · 14 Dec 2022 – 31 Dec 2028

ZoningR2 · Existing residential
What it says

Z1: Sustainable Residential Neighbourhoods: To protect, provide and improve residential amenities.

An established residential area. The objective is to protect existing residential amenity as well as to provide housing — which is the objective a neighbour's objection to an overbearing extension is usually argued under.

development plan 2022 2028 variation no 11 · 14 Dec 2022 – 31 Dec 2028

Heritage inventory1 within 100 m Shirley
Radon1 in 10 homes have high radon (EPA)

Not on this site: protected building, monument zone, conservation area, EU nature site, EU bird site, natural heritage area, tree order, landslide risk, derelict list.

Vacant land taxNo lived-in homes don't pay it
Flood riskWithin 100 m OPW map area within 100 m · floodinfo.ie
Within 500 mCountFor example
Natural heritage areas1Liffey Valley
Heritage inventory buildings23Park Lane Turnstile; house
Radon grid squares2
Monuments14Church; Graveyard
How we work this out
'On this site' means the record's own map outline touches the registered parcel (or a 12 m circle round the point where there is no parcel). Only the council's own list confirms a protected building; ask the council if in doubt. The council's map for the vacant land tax shows this spot inside an area of existing homes. Homes people live in, and their gardens, don't pay the tax. The OPW flood map's licence lets us show a yes/no only.
Sources: Development plan zoning (councils), National Inventory of Architectural Heritage, EPA radon map, Residential Zoned Land Tax maps, Constraint layers (bundle), OPW flood maps (CFRAM), Natural Heritage Areas (NPWS), Sites and Monuments Record · fetched 19 Oct 2026, 00:29
SourceLicenceFetchedLink
Development plan zoning (councils)CC BY 4.018 Oct 2026, 23:24open
National Inventory of Architectural HeritageCC BY 4.027 Sept 2026, 19:35open
EPA radon mapCC BY 4.027 Sept 2026, 19:36open
Residential Zoned Land Tax mapsCC BY 4.019 Oct 2026, 00:29open
Constraint layers (bundle)CC BY 4.0, CC BY-NC-ND 4.027 Sept 2026, 19:37open
OPW flood maps (CFRAM)CC BY-NC-ND 4.0 · shown as a yes/no only11 Sept 2026, 19:11open
Natural Heritage Areas (NPWS)CC BY 4.027 Sept 2026, 19:27open
Sites and Monuments RecordCC BY 4.027 Sept 2026, 19:29open
How we work this out
Applications whose site outline (or map point) falls on this property. 'No sign building has started' means we found no notice to the council's building control office; small jobs don't always file one, so ask. A missing completion certificate is not proof of a problem: an owner can opt out of official sign-off for a house or extension built for themselves.
Sources: Building Control Management System (commencement notices), National Planning Application Database · fetched 19 Oct 2026, 02:08
SourceLicenceFetchedLink
Building Control Management System (commencement notices)CC BY 4.019 Oct 2026, 01:33open
National Planning Application DatabaseCC BY 4.019 Oct 2026, 02:08open
Question 2

Could you extend?

Nothing on this site restricts it: not protected, not in a conservation area.

Figure 2

What happened to applications like yours

Extensions here: 70–97% by type. A new house in a garden is harder: 74% approved, and 1 in 3 is asked for more information.

Single-storey rear36 decided · more info asked 11%
94% · council 97%
Two-storey rear26 decided · more info asked 23%
92% · council 96%
Two-storey side16 decided · more info asked 19%
94% · council 98%
Attic or dormer72 decided · more info asked 14%
97% · council 96%
First-floor10 decided · more info asked 20%
70% · council 93%
New house in a garden or site19 decided · more info asked 32%
74% · council 72%
Approved nearbyDublin overall

Decided applications within 1.5 km, received in the last 10 years. The kind of work is read from each description.

CalculatedOur classificationcouncil register via NPAD · 179 nearby, 7,261 council-wide

Figure 3

Belgrove Park, file by file since 2020

9 of 11 decided extensions on the road were approved.

11 planning files on Belgrove Park since 2020, by kind and decision.2020202120222023202420252026Extensions, atticsNo. 9 · 2020 · two-storey rear · approved · 2298/20No. 13 · 2020 · single-storey side · approved · WEB1387/20No. 20 · 2020 · attic conversion / dormer · refused · WEB1607/20No. 20 · 2021 · garage conversion · approved · WEB1477/21No. 17 · 2021 · single-storey rear · approved · WEB1616/21No. 14 · 2021 · attic conversion / dormer · approved · WEB5225/21No. 13 · 2022 · attic conversion / dormer · approved · WEB1575/22No. 22 · 2024 · two-storey rear · approved · 3960/24No. 6 · 2024 · two-storey side · approved · WEB1233/24No. 22 · 2024 · two-storey rear · refused · WEB1323/24No. 24 · 2025 · attic conversion / dormer · approved · WEB6008/25Porches, roofs, otherNew house in a side garden
ApprovedRefusedWithdrawn or invalid

11 files with "Belgrove Park" in the address within 600 m, other roads of the same name left out. Hover a dot for the house number and reference.

MeasuredOur classificationcouncil register via NPAD · 2020–2026

Extensions and refusals right beside you 1 within 250 m · 0 refused within 100 m

Extensions and refusals near you 1 extensions within 250 m · the last 12 months

1 approved
KindAppliedApprovedRefused
Dormer or attic11—

Refused within 100 m 0 in the last 12 months

Nothing refused this close in the last 12 months.

    How we work this out
    Home extensions are read from the application's description (extension, attic or dormer, porch, garage conversion, garden room), so a few may be missed or mislabelled. The kind is the first that fits: a dormer with a rear extension counts as a dormer. Refusal reasons come from An Coimisiún Pleanála's inspector reports, so they exist only where the refusal was appealed (Dún Laoghaire-Rathdown so far). The council's own reasons are on its planning file.
    Sources: National Planning Application Database, An Coimisiún Pleanála cases (ArcGIS feed) · fetched 19 Oct 2026, 02:08
    SourceLicenceFetchedLink
    National Planning Application DatabaseCC BY 4.019 Oct 2026, 02:08open
    An Coimisiún Pleanála cases (ArcGIS feed)CC BY 4.016 Oct 2026, 23:06open
    Sources: An Coimisiún Pleanála cases (ArcGIS feed), Building Control Management System (commencement notices), National Planning Application Database · fetched 19 Oct 2026, 02:08
    SourceLicenceFetchedLink
    An Coimisiún Pleanála cases (ArcGIS feed)CC BY 4.016 Oct 2026, 23:06open
    Building Control Management System (commencement notices)CC BY 4.019 Oct 2026, 01:33open
    National Planning Application DatabaseCC BY 4.019 Oct 2026, 02:08open
    Question 3

    How long, and what if someone objects?

    Figure 4

    A home extension's journey here

    A decision takes 55 days. 1 in 7 is asked for more information, which adds about 62 days. Building starts about 5 months after permission.

    Comments open: 5 weeks · €20; Council decision: 55 days; If more info asked (1 in 7): 122 days; Appeal window: 4 weeks; If appealed: +115 days; Building starts: 140 days after permission0 mo3 mo6 mo9 mo12 mo15 moComments openComments close 5 weeks after the application is lodged5 weeks · €20Council decisionDecision: median 55 days, middle half 53–55 (n=166)55 daysIf more info asked (1 in 7)With further information: median 122 days (n=30)122 daysAppeal windowAnyone who commented can appeal within 4 weeks of the decision4 weeksIf appealedAt An Coimisiún Pleanála: median 115 days (n=27, all appeals within 1.5 km)+115 daysBuilding startsStart notice: median 140 days after permission (n=71)140 days after permissionSigned off60% of owners opt out of sign-off

    Bars are medians; whiskers show the middle half. Medians of separate steps don't add up exactly.

    Calculated196 decided home extensions, 72 start notices, 27 decided appeals · within 1.5 km, 10 years · NPAD, BCMS, An Coimisiún Pleanála

    Figure 5

    What appeals changed

    3 of 15 appealed refusals became permissions. 1 of 13 appealed approvals were reversed.

    Refusals appealed15 decided
    3 became permissions
    Approvals appealed13 decided
    1 reversed
    Ended approvedEnded refusedWithdrawn, invalid or other

    Every appeal decided within 1.5 km in 10 years, any kind of development.

    CalculatedAn Coimisiún Pleanála cases linked to the council file

    Appeals nearby 1 in the last 12 months

    None of 1 changed the council's decision

    • 500837 Granted with conditions · 26 New Row, Chapelizod, Dublin 20, D20 C956. · 497 m report
    Sources: An Coimisiún Pleanála cases (ArcGIS feed), Courts Service legal diary (judicial reviews), National Planning Application Database · fetched 19 Oct 2026, 02:08
    SourceLicenceFetchedLink
    An Coimisiún Pleanála cases (ArcGIS feed)CC BY 4.016 Oct 2026, 23:06open
    Courts Service legal diary (judicial reviews)© the publisher19 Oct 2026, 01:37open
    National Planning Application DatabaseCC BY 4.019 Oct 2026, 02:08open
    Question 4

    What's changing around you?

    Street map around Belgrove Park, Chapelizod with 10 numbered planning items
    ⌖ the houseDerelict buildingApproved, not startedBuilding startedApprovedNo decision yet
    1. 11 Mulberry Cottages Martin's Row Chapelizod Dublin 20 D20KW29 DS898Derelict building · 319 m
    2. 2Leitrim Lodge 4260/22Approved, no sign building has started · 337 m
    3. 36 Mulberry Cottages Martin's Row Chapelizod Dublin 20 D20ED28 DS954Derelict building · 344 m
    4. 410 Mulberry Cottages Martin's Row Chapelizod Dublin 20 D20TX99 DS901Derelict building · 352 m
    5. 539A Main Street Dublin 20 D20H971 DS1380Derelict building · 486 m
    6. 624 Belgrove Park, Chapelizod WEB6008/25Building started · 25 m
    7. 724 Belgrove Park, Chapelizod WEB6008/25Approved · 11 m
    8. 818, Glenaulin Park WEB5787/25Approved · 283 m
    9. 938 Maiden Row, Chapelizod WEB2469/26No decision yet · 467 m
    10. 1026, New Row WEB5759/25Approved · 497 m
    Figure 6

    What happens to applications within 500 m

    Permission isn't building. Of 48 permissions since 2016, 26 show a start notice and 2 have a completion certificate. Most owners opt out of sign-off.

    58 applications lodged within 500 m. Council: 47 approved, 7 refused. After appeals: 48 approved. Of those: 2 signed off, 14 built with the owner's opt-out, 10 started, 22 with no start notice found, 0 ran out.LODGEDCOUNCIL DECISIONAFTER APPEALSWHAT HAPPENED NEXT47: lodged → approved7: lodged → refused2: lodged → withdrawn or invalid2: lodged → undecided47: approved → approved6: refused → refused2: withdrawn or invalid → withdrawn2: undecided → undecided1 refused by the council, approved after an appeal22: approved → no start notice found14: approved → built, owner opted out10: approved → started, not signed off2: approved → signed off58 lodged58 lodged47 approved47 approved7 refused7 refused2 withdrawn or invalid2 withdrawn or invalid2 undecided2 undecided48 approved48 approved6 refused6 refused2 withdrawn2 withdrawn2 undecided2 undecided22 no start notice found22 no start notice found14 built, owner opted out14 built, owner opted out10 started, not signed off10 started, not signed off2 signed off2 signed off

    Purple bands are refusals turned into permissions on appeal. "No start notice found" includes small jobs that never needed one and notices we couldn't match.

    Measured58 applications in 10 years · NPAD, An Coimisiún Pleanála, BCMS start notices and completion certificates

    Figure 7

    The next 30 days

    Nothing closes within 500 m in the next 30 days.

      Measuredcouncil registers and An Coimisiún Pleanála · deadlines worked out from the dates on file

      Figure 8

      Approved, stalled or planned, not built yet

      23 homes 337 m away were approved Apr 2024 with no start notice yet; the permission runs to Apr 2029.

      Leitrim Lodge · 23 homes: 23 homes approved Apr 2024, not started2024202520262027202820292030Leitrim Lodge · 23 homes337 m · 4260/2223 homes approved Apr 2024, not started23 homes approved Apr 2024, not startedtoday

      Each row is a dated fact from a public register: no score and no forecast.

      Measuredcouncil registers, BCMS, derelict sites registers, development plan layers (CC BY 4.0)

      Sites that could change 5 within 500 m

      Derelict building 4

      • 11 Mulberry Cottages Martin's Row Chapelizod Dublin 20 D20KW29 · derelict since Jun 2015 · 319 m
      • 36 Mulberry Cottages Martin's Row Chapelizod Dublin 20 D20ED28 · derelict since Apr 2019 · 344 m
      • 410 Mulberry Cottages Martin's Row Chapelizod Dublin 20 D20TX99 · derelict since Jun 2015 · 352 m
      • 539A Main Street Dublin 20 D20H971 · derelict since Jan 2023 · 486 m

      Approved, not started 1

      • Leitrim Lodge · 23 homes approved Apr 2024, not started · 337 m
      Sources: An Coimisiún Pleanála cases (ArcGIS feed), Building Control Management System (commencement notices), Derelict sites registers, Council meetings (ModernGov), National Planning Application Database, Residential Zoned Land Tax maps · fetched 19 Oct 2026, 02:28
      SourceLicenceFetchedLink
      An Coimisiún Pleanála cases (ArcGIS feed)CC BY 4.016 Oct 2026, 23:06open
      Building Control Management System (commencement notices)CC BY 4.019 Oct 2026, 01:33open
      Derelict sites registersCC BY 4.012 Oct 2026, 23:08open
      Council meetings (ModernGov)Public19 Oct 2026, 02:28open
      National Planning Application DatabaseCC BY 4.019 Oct 2026, 02:08open
      Residential Zoned Land Tax mapsCC BY 4.019 Oct 2026, 00:29open
      Figure 9

      Applications within 500 m, by year

      Between 4 and 12 a year; busiest 2022. 87% of decisions were approvals.

      2019: 8, 2020: 10, 2021: 8, 2022: 12, 2023: 4, 2024: 6, 2025: 9, 2026: 1051015202019: 6 approved2019: 2 refused8’19*2020: 9 approved2020: 1 refused10’202021: 8 approved8’212022: 9 approved2022: 3 refused12’222023: 4 approved4’232024: 5 approved2024: 1 refused6’242025: 6 approved2025: 2 withdrawn or invalid2025: 1 undecided9’252026: 1 undecided1’26*
      ApprovedRefusedWithdrawn or invalidUndecided

      2019 and 2026 are part years (*). Exemption requests and time extensions are left out.

      Measuredcouncil register via NPAD

      Every application within 500 m 5 in the last 12 months

      See every application on the map

      How we work this out
      Descriptions are shortened by the national planning database (to 80 characters in Dún Laoghaire-Rathdown, 70 in Fingal), and it does not publish applicants' names.
      Sources: National Planning Application Database, An Coimisiún Pleanála cases (ArcGIS feed), Building Control Management System (commencement notices) · fetched 19 Oct 2026, 02:08
      SourceLicenceFetchedLink
      National Planning Application DatabaseCC BY 4.019 Oct 2026, 02:08open
      An Coimisiún Pleanála cases (ArcGIS feed)CC BY 4.016 Oct 2026, 23:06open
      Building Control Management System (commencement notices)CC BY 4.019 Oct 2026, 01:33open
      Building work nearby 2 in the last 12 months
      2 no sign-off needed
      • 624 Belgrove Park, Chapelizod, Dublin 20, D20 A003 · 20 Jul 2026 · start notice, opted out no sign-off needed · WEB6008/25 · 25 m
      • 21 Glenaulin, Dublin 20, D20 T669 · 15 Dec 2025 · start notice, opted out no sign-off needed · WEB1109/25 · 466 m
      How we work this out
      Each row is a notice the builder sent to the council's building control office before work started. One notice can cover many homes. 'Signed off as finished' means a completion certificate is on file; work done under an opt-out or a short notice doesn't need one.
      Source: Building Control Management System (commencement notices) · fetched 19 Oct 2026, 01:33
      SourceLicenceFetchedLink
      Building Control Management System (commencement notices)CC BY 4.019 Oct 2026, 01:33open
      Homes coming 23 not started
      • 2Leitrim Lodge · 23 homes · not started · runs out 24 Apr 2029 · 337 m
      • Hillside Manor, Lucan Road, Chapelizod, Dublin 20 (Phase 1)* · Completed · 30 homes · 437 m
      • Springvale Chapelizod Dublin 8 · Completed · 71 homes · 437 m
      • Teach San Labhras (St. Laurence House), Ballyfermot Road, Chapelizod, Dublin 10 (Phase 1)* · Completed · 27 homes · 437 m
      How we work this out
      Schemes of 10 or more homes approved since 2019, from the council and An Coimisiún Pleanála registers. 'Building started' means the builder told the council's building control office that work was starting (a commencement notice).
      Sources: An Coimisiún Pleanála cases (ArcGIS feed), Building Control Management System (commencement notices), National Planning Application Database, Social housing construction status report · fetched 19 Oct 2026, 02:08
      SourceLicenceFetchedLink
      An Coimisiún Pleanála cases (ArcGIS feed)CC BY 4.016 Oct 2026, 23:06open
      Building Control Management System (commencement notices)CC BY 4.019 Oct 2026, 01:33open
      National Planning Application DatabaseCC BY 4.019 Oct 2026, 02:08open
      Social housing construction status reportCC BY-SA 4.09 Oct 2026, 23:01open
      Named places nearby: estate, schemes, crèches, schools

      Named places estate, developments, inspections

      Developments within 1.0 km

      SchemeHomesProgressDistance
      Leitrim Lodge2424 not started (2026-Q2)313 m
      Former Faulkners Industries Factory2424 not started (2026-Q2)618 m
      Quadrant House106106 not started (2026-Q2)670 m
      Former De La Salle National School897531 built · 139 being built · 227 not started (2026-Q2)896 m

      Crèches and schools inspected

      NameLatest inspectionDistance
      Chestnut Daycare Ltd · Crèche23 Apr 2025 · report · Tusla Early Years Inspectorate664 m
      Teanga Beo Baile Formaid Cuideachta Faoi Theorainn Ráthaíochta · Crèche30 Sept 2025 · report · Tusla Early Years Inspectorate826 m
      The Preschool Stewarts Care Ltd · Crèche27 Jan 2026 · report · Tusla Early Years Inspectorate970 m
      St. Michael's Preschool & Afterschool Service · Crèche19 Mar 2026 · report · Tusla Early Years Inspectorate971 m
      St. Raphael's Preschool & Afterschool Project · Crèche10 Feb 2025 · report · Tusla Early Years Inspectorate983 m
      How we work this out
      Organisations only: a person named on an application is never listed. Inspection dates and links are the publisher's; read their report for the findings.
      Sources: Dublin housing delivery pipeline, National Planning Application Database, Department of Education school list, Tusla early years register · fetched 19 Oct 2026, 02:08
      SourceLicenceFetchedLink
      Dublin housing delivery pipelineCC BY 4.012 Oct 2026, 23:02open
      National Planning Application DatabaseCC BY 4.019 Oct 2026, 02:08open
      Department of Education school listCC BY 4.027 Sept 2026, 23:32open
      Tusla early years registerPublic register14 Oct 2026, 23:20open
      How busy is this area Busier than most of Dublin City Council.
      Homes approved
      Here47
      Council middle64
      Homes started
      Here845
      Council middle92
      How we work this out
      Homes approved counts schemes of 10 or more homes (one-off houses are not included). Homes started counts every home in a notice that building work was starting. The council figure is the middle value across the council's built-up squares of the same area (3.1 km², about a 1 km circle), so half of them saw more and half fewer.
      Sources: An Coimisiún Pleanála cases (ArcGIS feed), Building Control Management System (commencement notices), National Planning Application Database · fetched 19 Oct 2026, 02:08
      SourceLicenceFetchedLink
      An Coimisiún Pleanála cases (ArcGIS feed)CC BY 4.016 Oct 2026, 23:06open
      Building Control Management System (commencement notices)CC BY 4.019 Oct 2026, 01:33open
      National Planning Application DatabaseCC BY 4.019 Oct 2026, 02:08open
      Question 5

      What's the area like?

      Figure 10

      This street block against the council

      79% of homes built before 1971 (council 52%). 88% owner-occupied (council 47%).

      Homes built before 1971
      79% · council 52%
      Homes built since 2001
      3% · council 19%
      Owner-occupied
      88% · council 47%
      Rented
      8% · council 45%
      Children under 15
      19% · council 15%
      Aged 65 and over
      25% · council 13%
      Households with 2+ cars
      34% · council 19%
      Work mainly from home
      16% · council 12%
      This small area (305 people)Dublin

      MeasuredCSO Census 2022, Small Area Population Statistics (CC BY 4.0) · small area 268037012

      Road noise
      60–64 dB
      day–night average (EPA 2022)
      Bus
      183 m
      Belgrove Park · 80, C5, C6 · busiest stop within 500 m: 6 an hour at peak
      Radon
      1 in 10
      homes here likely high (EPA). Test it
      Flood
      Yes
      OPW flood map area within 100 m
      Nearest school
      367 m
      Chapelizod NS, 30 pupils
      Homes sold nearby
      32
      in 3 years (Property Price Register)
      Schools, stops and the council

      Schools

      • Chapelizod NS · primary · 30 pupils · 367 m
      • St Patricks Ns · primary · 203 pupils · 553 m
      • St Michaels Spec School · primary · 163 pupils · 589 m
      • Kylemore College · postprimary · 479 pupils · 776 m
      • St Louise de Marillac Primary School · primary · 256 pupils · 793 m
      • St. Seton's Secondary School · postprimary · 741 pupils · 870 m
      • St Michaels Ns · primary · 314 pupils · 960 m
      • St Raphaels Ns · primary · 380 pupils · 983 m

      Stops 16

      • Belgrove Park · 80, C5, C6 · 5/hour at peak · 183 m
      • Belgrove Park · 80, C5, C6 · 5/hour at peak · 187 m
      • Chapelizod W · 80, C5, C6 · 5/hour at peak · 289 m
      • Kylemore Rd N · 80, C5, C6, L55 · 6/hour at peak · 299 m
      • Glenaulin · 80, C5, C6, L55 · 6/hour at peak · 416 m
      • Glenaulin · L55 · 430 m
      • Chapelizod W · 80, C5, C6 · 5/hour at peak · 459 m
      • Chapelizod Village · 80, C5, C6 · 5/hour at peak · 565 m

      Schools growing or shrinking planning in 3 years · pupils last year

      • Chapelizod NS · 367 m0% pupils (30)
      • St Patricks Ns · 553 m+0.5% pupils (203)
      • St Michaels Spec School · 589 m+1.2% pupils (163)
      • Kylemore College · 776 m+2.8% pupils (479)
      • St Louise de Marillac Primary School · 793 m+2.8% pupils (256) · temporary classrooms 2025, approved
      • St. Seton's Secondary School · 870 m-4.8% pupils (741)

      Open consultations

      Council meetings 30 items

      Public land

      • The Office of Public Works · 150.43 ha · 136 m
      • Dublin City Council · 0.14 ha · 179 m
      • Dublin City Council · 0.74 ha · 233 m
      • Dublin City Council · 4.15 ha · 239 m
      • Dublin City Council · 1.78 ha · 239 m
      • Dublin City Council · 0.97 ha · 351 m
      Sources: Public transport stops and routes (NTA GTFS), Department of Education school list, National Planning Application Database, Council consultation portals, Council meetings (ModernGov), Land Development Agency public land register, cso_saps_2022, National Transport Authority, Fingal County Council and Dún Laoghaire-Rathdown County Council development plan layers (CC BY 4.0), dartplus.ie project extents over NTA GTFS rail shapes (CC BY 4.0), EPA strategic noise maps, Fingal County Council · fetched 19 Oct 2026, 02:28
      SourceLicenceFetchedLink
      Public transport stops and routes (NTA GTFS)CC BY 4.018 Oct 2026, 23:44open
      Department of Education school listCC BY 4.027 Sept 2026, 23:32open
      National Planning Application DatabaseCC BY 4.019 Oct 2026, 02:08open
      Council consultation portalsPublic19 Oct 2026, 01:38open
      Council meetings (ModernGov)Public19 Oct 2026, 02:28open
      Land Development Agency public land registerCC BY 4.011 Sept 2026, 16:43open
      cso_saps_2022CC BY 4.0—open
      National Transport AuthorityCC BY 4.0——
      Fingal County Council and Dún Laoghaire-Rathdown County Council development plan layers (CC BY 4.0)CC BY 4.0——
      dartplus.ie project extents over NTA GTFS rail shapes (CC BY 4.0)CC BY 4.0——
      EPA strategic noise mapsCC BY 4.0——
      Fingal County CouncilCC BY 4.0——
      Question 6

      What to ask, and who

      1. Attic or dormer (WEB6008/25) built without official sign-off: built properly?
        Ask for: An engineer's opinion of compliance.
        Seller · solicitor
      2. Porch (3960/24) approved 2024, not started: still planned?
        Ask for: The grant, and whether it stays with the house.
        Seller · solicitor
      3. Attic or dormer (WEB1477/21) built without official sign-off: built properly?
        Ask for: An engineer's opinion of compliance.
        Seller · solicitor
      4. Flood risk area within 100 m: can you insure it?
        Ask for: A flood-cover quote before sale agreed.
        Insurer
      5. High radon area (1 in 10 homes): has it been tested?
        Ask for: Radon test results.
        Seller
      6. Any work done without planning permission?
        Ask for: An opinion of compliance for the whole house.
        Seller · solicitor
      Reference

      Where this is, the terms, the sources

      Electoral division
      Chapelizod
      Electoral area
      Ballyfermot-Drimnagh
      Council
      Dublin City Council
      Everything we found, as a list 8 lines
      • 6 applications on this site; latest WEB6008/25, approved 2026, started, no sign-off needed.
      • Zoned R2 (existing residential); not protected; no vacant land tax; flood risk area within 100 m; high radon area.
      • 5 sites nearby could change: 4 derelict, 1 approved scheme.
      • 23 homes approved nearby, not started; largest 23 at Leitrim Lodge.
      • Glenaulin (bus 80, C5) 416 m away: 6 an hour at morning peak; 33 from all stops within 500 m.
      • Noise from road traffic mapped at 60–64 dB (day-evening-night average, EPA 2022).
      • Here (2022 census): 88% owner-occupied (council 47%); 3% of homes empty (council 8%); most built 1961–1970; 48% drive to work (council 28%); population up 11% since 2016.
      • 1 home extension within 250 m since 2025.
      What the terms mean 7 terms
      • Vacant land tax (Residential Zoned Land Tax (RZLT)): A yearly tax of 3% of the land's value on land that is zoned for homes and serviced but left unbuilt.
      • Building started (Commencement notice (BCMS)): The builder must tell the council's building control office 14 to 28 days before work starts.
      • Signed off as finished (Certificate of Compliance on Completion): A certificate filed when a building is finished, confirming it meets the building regulations.
      • Approved (Grant of permission): The council said yes, usually with conditions.
      • Listed by the council as derelict (Derelict Sites Register): Councils keep a public list of land and buildings in a ruinous or dangerous state.
      • Appeal (Appeal to An Coimisiún Pleanála): The applicant, or anyone who commented in time, can appeal the council's decision within four weeks.
      • What the land is zoned for (Zoning objective): The council's development plan sets what each area is for: homes, shops, open space and so on.
      Sources and licences 31
      SourcePublisherLicenceFetched
      EPA strategic noise maps—CC BY 4.0—
      Fingal County Council—CC BY 4.0—
      Fingal County Council and Dún Laoghaire-Rathdown County Council development plan layers (CC BY 4.0)—CC BY 4.0—
      National Transport Authority—CC BY 4.0—
      services-eu1.arcgis.comAn Coimisiún PleanálaCC BY 4.016 Oct 2026
      data.nbco.gov.ieNational Building Control Office (BCMS)CC BY 4.019 Oct 2026
      data.gov.ieVarious (see each layer)CC BY 4.0, CC BY-NC-ND 4.027 Sept 2026
      s3.eu-west-1.amazonaws.comOffice of Public WorksCC BY-NC-ND 4.0 · flag only11 Sept 2026
      services-eu1.arcgis.comNational Parks and Wildlife ServiceCC BY 4.027 Sept 2026
      services-eu1.arcgis.comNational Inventory of Architectural HeritageCC BY 4.027 Sept 2026
      gis.epa.ieEnvironmental Protection AgencyCC BY 4.027 Sept 2026
      services-eu1.arcgis.comNational Monuments Service (SMR)CC BY 4.027 Sept 2026
      dlrcoco.citizenspace.comLocal authorities (consultation portals)Public19 Oct 2026
      www2.courts.ie—© the publisher19 Oct 2026
      cso.ie—CC BY 4.0—
      dartplus.ie project extents over NTA GTFS rail shapes (CC BY 4.0)—CC BY 4.0—
      services-eu1.arcgis.comLocal authorities (derelict sites registers)CC BY 4.012 Oct 2026
      services.arcgis.comDublin local authorities (housing delivery pipeline)CC BY 4.012 Oct 2026
      esbnetworks.ie—© the publisher · flag only11 Sept 2026
      transportforireland.ieNational Transport AuthorityCC BY 4.018 Oct 2026
      lda.ieLand Development AgencyCC BY 4.011 Sept 2026
      meetings.fingal.ieLocal authorities (council meetings)Public19 Oct 2026
      services.arcgis.comDepartment of Housing (National Planning Application Database)CC BY 4.019 Oct 2026
      services-eu1.arcgis.comTailte ÉireannCC BY 4.011 Sept 2026
      services-eu1.arcgis.comCSO, Tailte Éireann, OpenStreetMap contributorsCC BY 4.04 Oct 2026
      propertypriceregister.ieProperty Services Regulatory Authority (PPR)© PSRA, PSI licence19 Oct 2026
      services.arcgis.comLocal authorities (RZLT maps)CC BY 4.018 Oct 2026
      gov.ieDepartment of EducationCC BY 4.027 Sept 2026
      gov.ieDepartment of HousingCC BY-SA 4.09 Oct 2026
      tusla.ieTusla (Early Years Inspectorate)Public register14 Oct 2026
      services.arcgis.comLocal authorities via the Department of Housing (GZT / MyPlan)CC BY 4.018 Oct 2026
      Measured
      counted from a public register
      Calculated
      a rate or median we worked out from those counts
      Our classification
      we sorted it by reading each description
      Estimate
      inferred from another source (census, map data)
      Rule summary
      the law, simplified: check before relying on it
      How we work this out
      Generated 19 Oct 2026, 04:12 from the Planning Register store; nothing was fetched live. Not a legal search: the council's planning file is the record. Deadlines come from published dates under the Planning and Development Act 2000: confirm with the council before relying on them. Street map © OpenStreetMap contributors; building outlines © Overture Maps Foundation. The text version carries every figure with its source, for an AI assistant.