10 Pembroke Place and 36-38 Herbert Park
105 apartmentsBallsbridge, Dublin City Council
Building progress councils’ figures, Q2 2026
103 under construction of 103 permitted homes (Q2 2026).
completed · under construction · not started · 0 houses and 103 apartments permitted
Quarter by quarter
| Quarter | Permitted | Under construction | Completed | Completed share |
|---|---|---|---|---|
| Q2 2025 | 103 | 103 | 0 | |
| Q3 2025 | 103 | 103 | 0 | |
| Q4 2025 | 103 | 103 | 0 | |
| Q1 2026 | 103 | 103 | 0 | |
| Q2 2026 | 103 | 103 | 0 |
- Status
- Permitted · activity on site: yes
- Decision
- Approved · 8 Sept 2020
- Size
- 105 apartments
- Site
- 3,477 m²
The scheme
The proposed development is located at 10 Pembroke Place and 36 and 38 Herbert Park in Ballsbridge, Dublin 4. It consists of 105 residential units. The application was submitted as a Strategic Housing Development.
it is a Strategic Housing Development of 105 units
Summary from the councils' pipeline record.
The site 3,477 m²
Boundary of 10 Pembroke Place and 36-38 Herbert Park as the Dublin councils map it in the housing pipeline.
Planning applications inside the site 4 applications in the last 10 years
Appeals inside the site 4 with An Coimisiún Pleanála
- Granted with conditions36, 38, 40 Herbert Park and 10 Pembroke Place, Ballsbridge, Dublin 4. (www.herbertparkshd.com)
- Granted with conditions10, Pembroke Place, and Nos. 36 and 38 Herbert Park Road, Ballsbridge, Dublin 4
- Refused10 Pembroke Place, Ballsbridge, Dublin 4.
- Withdrawn10 Pembroke Place, Ballsbridge, Dublin 4.
Building work started inside the site 6 commencement notices
- Commenced10, Pembroke Place, Ballsbridge, Dublin 4
- Commenced36 Herbert Park, Dublin, Dublin 4, D04 X7F4
- Commenced10 Pembroke Place, Ballsbridge, Dublin, D04 V1W6
- Commenced10 Pembroke Place, Dublin, D04 V1W6
- Commenced10 Pembroke Place, Dublin, D04 V1W6
- Commenced10 Pembroke Place, Ballsbridge, Dublin 4, D04 V1W6
Planning timeline 7 steps
- 20 May 2020Application lodged — SHD
- 8 Sept 2020Council decision — Grant
- 9 Sept 2020Final approval
- 20 Oct 2020Judicial review lodged — 2020 761 JR
- 19 Nov 2021Judicial review concluded — Grant
- Q3 2024Building started
- 12 Jan 2029Approval runs out (estimate)
Other big developments nearby within 2 km
- Ballsbridge Hotel Site · 339 homes · 13 storeys · 335 m away
- RTÉ Campus at Montrose · 511 homes · 738 m away
- Former RTÉ Campus at Montrose · 511 homes · 738 m away
- Montrose Block 5 · 117 homes · 13 storeys · 738 m away
- 98 Merrion Road · 111 homes · 5 storeys · 752 m away
- Jefferson House · 62 homes · 11 storeys · 997 m away
- Sandymount Avenue Residential Development · 69 homes · 3 storeys · 1.1 km away
- Sandymount Place · 67 homes · 4 storeys · 1.1 km away