133 and 152 Ballyogan Road
Approved May 2025: 49 homes; building not started (Q2 2026).
Ultra Dawn LimitedDublin 18, Dún Laoghaire-Rathdown County Council
- Status
- Approved
- Council decision
- Approved · 2 May 2025
- Uses
- residential
- Applicant
- Ultra Dawn Limited
- Site
- 4,865 m²
- Appeal
- ACP 322569 · pending
Building progress councils’ figures, Q2 2026
Quarter by quarter
| Quarter | Permitted | Under construction | Completed | Completed share |
|---|---|---|---|---|
| Q2 2025 | — | 0 | 0 | |
| Q3 2025 | 49 | 0 | 0 | |
| Q4 2025 | 49 | 0 | 0 | |
| Q1 2026 | 49 | 0 | 0 | |
| Q2 2026 | 49 | 0 | 0 |
Source and licence
The scheme
Ultra Dawn Limited proposes a development on lands at 133 and 152 Ballyogan Road in Dublin 18. The project involves the construction of 49 residential units on a site area of 0.49 hectares.
What the register says
Ultra Dawn Limited intend to apply for permission for development on lands at No…
Cut short by the council feed. Full text ↗
Summary from the register record.
Planning timeline 6 steps
- 11 Dec 2024Application lodged — Standard
- 2 May 2025Council decision — Grant
- 20 May 2025Appealed to An Coimisiún Pleanála — ABP-322569-25
- 18 Sept 2025Commission decision — Granted
- 18 Sept 2025Final approval
- 2 Nov 2030Approval runs out (estimate)
The site 4,865 m²
Boundary of 133 and 152 Ballyogan Road as the Dublin councils map it in the housing pipeline.
Planning applications inside the site 6 applications in the last 10 years
- Commenced135 Ballyogan Road, Carrickmines, Dublin 18, D18DW32
- Withdrawn135, Ballyogan Road, Carrickmines, Dublin 18, D18 DW32.
- Commenced135 Ballyogan Road, Carrickmines, Dublin 18, D18DW32
- Appeal decidedNos 133 and 152, Ballyogan Road, Ballyogan, Dublin 18, D18F882
- Withdrawn133 & 152, Ballyogan Road, D18 F882
- Appeal decided0.48 ha (4,773 sqm) site at Nos. 133-152, Ballyogan Road, Carrickmines, Dublin 18 (d18 F882 and D18 FN24)
Appeals inside the site 2 with An Coimisiún Pleanála
Other big developments nearby within 2 km
- Clay Farm · first homes signed off 2023 · 476 m away
- Kilternan · approved 2026, no start notice · 932 m away
- Clay Farm House · refused 2024 · 958 m away
- Clay Farm Loop Road linking with Clay Farm Phase 2 developme · refused 2023 · 996 m away
- c.2.81 ha · refused 2023 · 1.0 km away
- Ashwood Farm · withdrawn or invalid · 1.0 km away
- Lands located off Enniskerry Road · approved 2024, no start notice · 1.2 km away
- Shaldon Grange · first homes signed off 2025 · 1.2 km away
Start notices are matched from the national building control register; a start on site can be missed.
Something wrong on this scheme page, or a record you want corrected or removed? Contact us and we will check it against the source.