Dún Laoghaire-Rathdown County Council · D20A/0670 · Permission
Glenville Garden, Mount Merrion
69 homesStrand Court LimitedBlackrock, Dún Laoghaire-Rathdown County Council
69 under construction of 69 permitted homes (Q2 2026).
On the planning register as 24-28 Fosters Avenue (D20A/0670). Build progress, sales and land nearby on Buildable →
- 21 Sept 2020Received
- 18 Mar 2021Approved
- 12 Apr 2021Appealed
- 28 Aug 2023Appeal: Approved with conditions
- 17 Apr 2024Building started
- 15 Oct 2026Signed off
- Status
- Building started
- Decision
- Approved · 18 Mar 2021
- Size
- 69 homes
- Uses
- residential
- Applicant
- Strand Court Limited
- Site
- 6,539 m²
- Appeal
- ACP 309931 · Approved with conditions
Building progress councils’ figures, Q2 2026
- 2023Approved
- 2024Building started
- 2026First homes signed off1 sign-off
69 under construction of 69 permitted homes (Q2 2026).
72
homes proposed
69
homes permitted
69
homes started on site
0
homes completed
completed · under construction · not started · 0 houses and 69 apartments permitted
Quarter by quarter
| Quarter | Permitted | Under construction | Completed | Completed share |
|---|---|---|---|---|
| Q2 2025 | 69 | 26 | 0 | |
| Q3 2025 | 69 | 26 | 0 | |
| Q4 2025 | 69 | 69 | 0 | |
| Q1 2026 | 69 | 69 | 0 | |
| Q2 2026 | 69 | 69 | 0 |
The scheme
it involves the construction of 69 residential units
What the register says
Permission for development. The proposed
Summary from the register record.
Planning timeline 7 steps
- 21 Sept 2020Application lodged — Standard
- 18 Mar 2021Council decision — Grant
- 12 Apr 2021Appealed to An Coimisiún Pleanála — ABP-309931-21
- 28 Aug 2023Commission decision — Granted
- 28 Aug 2023Final approval
- 17 Apr 2024Building started
- 10 Dec 2028Approval runs out (estimate)
The site 6,539 m²
Boundary of Glenville Garden, Mount Merrion as the Dublin councils map it in the housing pipeline.
Planning applications inside the site 6 applications in the last 10 years
- Granted24-28, Fosters Avenue, Mount Merrion, Blackrock, Co. Dublin
- Appeal decided24-28, Fosters Avenue, Mount Merrion, Blackrock, Co. Dublin
- Granted23, St. Thomas Road, Mount Merrion, Blackrock, Co. Dublin, A94H778
- Commenced24,26 28, Fosters Avenue, Mount Merrion, Blackrock, Co Dublin
- Appeal decidedSite at No's, 24, 26 and 28, Foster's Avenue, Mount Merrion, Blackrock, Co. Dublin
- RefusedOn a site of 0.6068 ha at 24, 26 & 28 Foster's Avenue, Mount Merrion, Co Dublin
Appeals inside the site 5 with An Coimisiún Pleanála
- Granted with conditions24-28, Fosters Avenue, Mount Merrion, Blackrock, Co. Dublin
- Invalid24,26 28, Fosters Avenue, Mount Merrion, Blackrock, Co Dublin
- Granted with conditions24,26 28, Fosters Avenue, Mount Merrion, Blackrock, Co Dublin
- Granted with conditionsSite at No's, 24, 26 and 28, Foster's Avenue, Mount Merrion, Blackrock, Co. Dublin
- Refused24, 26 and 28 Fosters Avenue, Mount Merrion, Blackrock, Co. Dublin.
Building work started inside the site 1 commencement notice
Other big developments nearby within 2 km
- 26 & 28 Foster's Avenue · 0 m away
- Part Ground Floor of Permitted Block A · 155 m away
- 3.4 ha at Chesterfield · 846 m away
- Merrion · 849 m away
- Merrion at · 849 m away
- Chesterfield · 849 m away
- Knockrabo · 369 homes · 936 m away
- 2.54 hectares · 1.1 km away
Something wrong on this scheme page, or a record you want corrected or removed? Contact us and we will check it against the source.