52-58 Station Road
Built: all 105 apartments are finished (Q2 2025).
Raheny, Dublin City Council
Also known as Station Road, Raheny.
Building progress councils’ figures, Q2 2025
105
homes permitted
105
homes started on site
105
homes completed
completed · under construction · not started · 0 houses and 105 apartments permitted
Source and licence
- Status
- Built
- Decision
- Approved · 24 Feb 2021
- Site
- 3,434 m²
- Commission case
- ABP-308552-21 · Approved
The scheme
The proposal involves the demolition of four existing dwellings, a workshop, and ancillary structures at 52-58 Station Road, Raheny. It includes the construction of 105 apartments and associated site works.
Summary from the councils' pipeline record.
The site 3,434 m²
Boundary of 52-58 Station Road as the Dublin councils map it in the housing pipeline.
Appeals inside the site 1 with An Coimisiún Pleanála
Planning timeline 7 steps
- 24 Feb 2020Application lodged — SHD
- 24 Feb 2021Council decision — Grant
- 24 Feb 2021Commission decision — Granted
- 24 Feb 2021Final approval
- Q3 2022Building started
- Q2 2025Site completed — Site completed
- 4 Aug 2026Approval runs out (estimate)
Other big developments nearby within 2 km
- Salvation Army Family Hub · approved 2024 · 28 homes · 2 storeys · 1.9 km away
- 794-798 Howth Road · lodged 2026, not decided · 58 homes · 5 storeys · 1.9 km away
- 796-798 Howth Road · refused 2024 · 57 homes · 6 storeys · 1.9 km away
Something wrong on this scheme page, or a record you want corrected or removed? Contact us and we will check it against the source.