South Dublin County Council · SDZ22A/0014 · SDZ Application

Aderrig Development Area

207 homes4 storeysQuintain Developments Ireland LimitedLucan, South Dublin County Council

157 built, 50 under construction of 207 permitted homes (Q2 2026).

Also known as Adamstown.

  1. 26 Oct 2022Received
  2. 19 Apr 2023Approved
  3. 26 Feb 2024Building started
  4. 23 Oct 2024Signed off
Status
Building started
Decision
Approved · 19 Apr 2023
Size
207 homes · up to 4 storeys
Uses
residential, houses, apartments
Applicant
Quintain Developments Ireland Limited
Site
6.03 ha

Building progress councils’ figures, Q2 2026

  1. 2023Approved
  2. 2024Building started
  3. 2024First homes signed off14 sign-offs

157 built, 50 under construction of 207 permitted homes (Q2 2026).

207
homes permitted
207
homes started on site
157
homes completed

completed · under construction · not started · 75 houses and 132 apartments permitted

Quarter by quarter
QuarterPermittedUnder constructionCompletedCompleted share
Q2 202520717235
Q3 202520712978
Q4 202520790117
Q1 202620766141
Q2 202620750157

The scheme

Quintain Developments Ireland Limited proposes the construction of 207 residential units in the Aderrig Development Area of Adamstown. The development consists of 75 houses and 132 duplexes ranging from 2 to 4 storeys in height. The project includes associated site works, infrastructure, and parking across two sites separated by the Celbridge Link Road.

it involves the construction of 207 residential units

What the register says

Development on 2 sites separated by the permitted Celbridge Link Road with a total area of 6.36 Ha; The south-western site (5.39 Ha) is generally bound to the east by Celbridge Link Road, to the south and west by undeveloped land and an electrical substation and to the north by the Tubber Lane Development Area. The north-eastern site (0.97 Ha) is generally bound to the east by the undeveloped Primary School site and Aderrig Park Avenue, to the south by Airlie Park Road West and the undeveloped Primary School site, to the west by Celbridge Link Road and the Tubber Lane Development Area and to the north by the Tubermaclugg Village Development Area. This application is being made in accordance with the Adamstown Planning Scheme 2014 (as amended) and relates to a proposed development within the Aderrig Development Area of the Adamstown Strategic Development Zone; The proposed development will principally consist of: the demolition and removal of derelict hardstanding and walls; and the construction of 207 residential units (64 two bed, 127 three bed and 16 four bed), ranging in height from 2 storeys to 4 storeys, comprising 75 houses (59 three bed and 16 four bed) and 132 duplexes (64 town bed and 68 three bed); The development will also include: vehicular junctions to access the development from Celbridge Link Road (2 No.) and Adamstown Way (3No.); internal road, cycle and footpath network; 314 car parking spaces; cycle parking; bin storage areas; public, communal and private open space areas, with balconies and terraces facing all aspects; hard and soft landscaped areas; boundary treatments; public lighting; 2 sub-stations; and all associated site and development works above and below ground

Summary from the register record.

Planning timeline 5 steps

  • 26 Oct 2022
    Application lodged — DZ
  • 19 Apr 2023
    Council decision — Grant
  • 19 Apr 2023
    Final approval
  • 26 Feb 2024
    Building started
  • 2 Jun 2028
    Approval runs out (estimate)

The site 6.03 ha

Boundary of Aderrig Development Area as the Dublin councils map it in the housing pipeline.

Planning applications inside the site 8 applications in the last 10 years

Appeals inside the site 1 with An Coimisiún Pleanála

Building work started inside the site 16 commencement notices