PlanningRegister.ie
Dún Laoghaire-Rathdown County Council · DZ25A/0318/WEB · Permission (SDZ)

Brennanstown

Manciano LimitedDublin 18, Dún Laoghaire-Rathdown County Council

Approved Aug 2025; building started Oct 2025.

  1. 17 Apr 2025Received
  2. 20 Aug 2025Approved
  3. 20 Oct 2025Building started
Status
Building started
Decision
Approved · 20 Aug 2025
Applicant
Manciano Limited
Site
6,198 m²

Building progress councils’ figures, Q2 2026

  1. 2025Approved
  2. 2025Building started
  3. Not yetFirst homes signed off

24 homes proposed; none permitted yet (Q2 2026).

24
homes proposed
0
homes started on site
0
homes completed

completed · under construction · not started

Quarter by quarter
QuarterPermittedUnder constructionCompletedCompleted share
Q2 2025—00
Q3 2025—00
Q4 2025—00
Q1 2026—00
Q2 2026—00

The scheme

What the register says

We, Manciano Limited, intend to apply for planning permission for a proposed dev…

Cut short by the council feed. Full text ↗

Summary from the register record.

Planning timeline 3 steps

  • 17 Apr 2025
    Application lodged — Standard
  • 20 Aug 2025
    Council decision — Grant permission
  • 20 Oct 2025
    Building started

The site 6,198 m²

Boundary of Brennanstown as the Dublin councils map it in the housing pipeline.

Planning applications inside the site 6 applications in the last 10 years

Appeals inside the site 6 with An Coimisiún Pleanála

Building work started inside the site 1 commencement notice

Other big developments nearby within 2 km

Everything within 1 km on the map →

Something wrong on this scheme page, or a record you want corrected or removed? Contact us and we will check it against the source.