Dún Laoghaire-Rathdown County Council · D18A/0257 · Standard

Brookfield

130 homesDublin 18, Dún Laoghaire-Rathdown County Council

Approved Sep 2019; building not started (Q2 2025).

Building progress councils’ figures, Q2 2025

130 homes permitted; building has not started (Q2 2025).

130
homes permitted
0
homes started on site
0
homes completed

completed · under construction · not started · 0 houses and 130 apartments permitted

Status
Expired · activity on site: no
Decision
Approved · 1 Sept 2019
Size
130 homes
Site
10.29 ha
Commission case
ABP-304396-19 · Approved

The site 10.29 ha

Boundary of Brookfield as the Dublin councils map it in the housing pipeline.

Planning applications inside the site 5 applications in the last 10 years

Appeals inside the site 2 with An Coimisiún Pleanála

Building work started inside the site 1 commencement notice

  • CommencedStepaside ETSS, Ballyogan Road, Leopardstown, Dublin 18, South Dublinnotice 17 Jun 2022 · Dún Laoghaire-Rathdown County Council

Planning timeline 6 steps

  • 26 Mar 2018
    Application lodged — Standard
  • 11 Apr 2019
    Council decision — Grant
  • 7 May 2019
    Appealed to An Coimisiún Pleanála — ABP-304396-19
  • 1 Sept 2019
    Commission decision — Granted
  • 26 Sept 2019
    Final approval
  • 26 Sept 2024
    Approval runs out (estimate)

Other big developments nearby within 2 km

Free

Living near Brookfield?

Its progress and every other plan around it.

Something wrong on this scheme page, or a record you want corrected or removed? Contact us and we will check it against the source.