PlanningRegister.ie
Dún Laoghaire-Rathdown County Council · ABP31128721 · Permission (SHD)

c.0.9ha at No. 97A Highfield Park

Pembroke Partnership LimitedOld Frankfort, Dún Laoghaire-Rathdown County Council

Approved Dec 2021; no start notice yet.

  1. 3 Sept 2021Received
  2. 20 Dec 2021Approved
  3. 20 Dec 2026Approval runs out
Status
Approved No start yet
Decision
Approved · 20 Dec 2021
Applicant
Pembroke Partnership Limited
Site
8,996 m²

Building progress councils’ figures, Q2 2026

101 homes permitted; building has not started (Q2 2026).

115
homes proposed
101
homes permitted
0
homes started on site
0
homes completed

completed · under construction · not started · 0 houses and 101 apartments permitted

Quarter by quarter
QuarterPermittedUnder constructionCompletedCompleted share
Q2 202511500
Q3 202511500
Q4 202511500
Q1 202611500
Q2 202610100

The scheme

What the register says

Permission for a strategic housing development consisting of the: demolition of…

Cut short by the council feed. Full text ↗

Summary from the register record.

Planning timeline 7 steps

  • 3 Sept 2021
    Application lodged — SHD
  • 20 Dec 2021
    Council decision — Grant
  • 20 Dec 2021
    Final approval
  • 21 Feb 2022
    Judicial review lodged — 2022 129 JR
  • 3 Dec 2024
    Judicial review concluded — Grant
  • 6 May 2026
    Commission decision — Granted
  • 2 Mar 2027
    Approval runs out (estimate)

The site 8,996 m²

Boundary of c.0.9ha at No. 97A Highfield Park as the Dublin councils map it in the housing pipeline.

Planning applications inside the site 9 applications in the last 10 years

Show 1 more

Appeals inside the site 4 with An Coimisiún Pleanála

Other big developments nearby within 2 km