All 255 permitted homes are built (Q4 2025).

  1. 13 Apr 2022Received
  2. 28 Mar 2023Approved
  3. 5 Jun 2024Building started
  4. 25 Sept 2026Signed off
Status
Building started
Decision
Approved - decision by abp · 28 Mar 2023
Applicant
Cosgrave Developments Unlimited Company
Site
1.55 ha

Building progress councils’ figures, Q4 2025

  1. 2023Approved
  2. 2024Building started
  3. 2026First homes signed off1 sign-off

All 255 permitted homes are built (Q4 2025).

255
homes proposed
255
homes permitted
255
homes started on site
255
homes completed

completed · under construction · not started · 0 houses and 255 apartments permitted

Quarter by quarter
QuarterPermittedUnder constructionCompletedCompleted share
Q2 20252552550
Q3 20252552550
Q4 20252550255

The scheme

What the register says

The proposed development will consist of the construction of a residen…

Cut short by the council feed. Full text ↗

Summary from the register record.

Planning timeline 7 steps

  • 13 Apr 2022
    Application lodged — SHD
  • 28 Mar 2023
    Council decision — Grant
  • 28 Mar 2023
    Commission decision — Granted
  • 28 Mar 2023
    Final approval
  • Q4 2025
    Site completed — Site completed
  • 19 May 2026
    Building started
  • 27 Mar 2028
    Approval runs out (estimate)

The site 1.51 ha

Boundary of c.1.5 hectare site as the Dublin councils map it in the housing pipeline.

Planning applications inside the site 4 applications in the last 10 years

Appeals inside the site 2 with An Coimisiún Pleanála

Building work started inside the site 1 commencement notice

Other big developments nearby within 2 km

Everything within 1 km on the map →

Something wrong on this scheme page, or a record you want corrected or removed? Contact us and we will check it against the source.