PlanningRegister.ie
Dún Laoghaire-Rathdown County Council · DZ22A/0846 · Permission (SDZ)

Cherrywood

Building: first homes signed off Apr 2023; approved Dec 2022.

CWTC Multi Fanily ICAVLoughlinstown and Glebe, Dún Laoghaire-Rathdown County Council

Email me when the next phase is lodged

Status
Building started
Decision
Approved · 22 Dec 2022
Applicant
CWTC Multi Fanily ICAV
Site
24.57 ha

Is it built?

  1. 2022Approved
  2. 2022Building started
  3. 2023First homes signed off3 sign-offs

The scheme

What the register says

Planning permission for development. This application relates to development in…

Cut short by the council feed. Full text ↗

Summary from the register record.

Planning timeline
  1. 4 Nov 2022Received
  2. 12 Dec 2022Building started
  3. 22 Dec 2022Approved
  4. 3 Apr 2023Signed off

The site 24.57 ha

Boundary of Cherrywood from the planning application.

Planning applications inside the site 71 applications in the last 10 years

Show 42 more

Showing the newest 50 of 71. The full list is in the report.

Appeals inside the site 15 with An Coimisiún Pleanála
Commencement notices inside the site 6

Other big developments nearby within 2 km

Everything within 1 km on the map →