Circle K Donnybrook
84 apartments12 storeysDublin 4, Dublin City Council
Refused Oct 2025.
Also known as Donnybrook Road and Brookvale Road.
Building progress councils’ figures, Q2 2025
84 homes proposed; none permitted yet (Q2 2025).
completed · under construction · not started · 0 houses and 0 apartments permitted
- Status
- Refused · activity on site: no
- Decision
- Refused · 6 Oct 2025
- Size
- 84 apartments · up to 12 storeys
- Site
- 1,074 m²
- Commission case
- ABP-310204-21 · Refused
The scheme
The proposal involves the demolition of existing structures at the Circle K petrol station site in Donnybrook, Dublin 4. It includes the construction of a twelve storey mixed-use development containing 84 apartments.
it proposes a twelve storey development on the site
Summary from the councils' pipeline record.
The site 1,074 m²
Boundary of Circle K Donnybrook as the Dublin councils map it in the housing pipeline.
Planning applications inside the site 3 applications in the last 10 years
- Awaiting decisionc. 0. 131 ha site at the Circle K petrol station at the junction of Donnybrook Road and Brookvale Road Donnybrook, Dublin 4, D04 K3T8
- GrantedPlanning permission for development at this c.0.131 ha site at the Circle K petrol station at the junction of Donnybrook Road and Brookvale Road,, Donnybrook., Dublin 4, D04K3T8. The proposals comprise the demolition of existing buildings and structures
- WithdrawnLands at the Circle K petrol station at the junction of Donnybrook Road and Brookvale Road, Donnybrook, Dublin 4, D04 K3T8
Appeals inside the site 3 with An Coimisiún Pleanála
- RefusedLands at the Circle K Petrol Station at the junction of Donnybrook Road and Brookvale Road, Donnybrook, Dublin 4, D04 K3T8
- Granted with conditionsBray to Dublin City Centre.
- Granted with conditionslands (c 0.11 ha) at the junction of Donnybrook Road and Brookvale Road, Donnybrook, Dublin 4, D04 K3T8
Planning timeline 6 steps
- 18 Feb 2021Application lodged — Standard
- 14 Apr 2021Council decision — Refuse
- 5 Nov 2021Appealed to An Coimisiún Pleanála — ABP-310204-21
- 6 Oct 2025Commission decision — Refused
- 6 Oct 2025Final approval
- 6 Oct 2025Approval runs out (estimate)
Other big developments nearby within 2 km
- Montrose Block 5 · 117 homes · 13 storeys · 231 m away
- Former RTÉ Campus at Montrose · 511 homes · 231 m away
- Former Smurfit Paper Mills Site · 167 homes · 7 storeys · 548 m away
- Former Murphy and Gunn Site · 74 homes · 991 m away
- Mount Saint Mary's and Saint Joseph's · 1.5 km away
- Sandymount Place · 67 homes · 4 storeys · 1.6 km away
- Sandymount Avenue Residential Development · 69 homes · 3 storeys · 1.6 km away
- Part Ground Floor of Permitted Block A · 1.8 km away
Something wrong on this scheme page, or a record you want corrected or removed? Contact us and we will check it against the source.