PlanningRegister.ie
South Dublin County Council · SDZ25A/0030W · SDZ Application

Doddsborough

30 homesEvara Developments LimitedLucan, South Dublin County Council

Approved Oct 2025; building started May 2026.

  1. 3 Jul 2025Received
  2. 24 Oct 2025Approved
  3. 15 May 2026Building started
Status
Building started
Decision
Approved · 24 Oct 2025
Size
30 homes
Applicant
Evara Developments Limited
Site
8,707 m²

Building progress councils’ figures, Q2 2026

  1. 2025Approved
  2. 2026Building started
  3. Not yetFirst homes signed off

30 homes permitted; building has not started (Q2 2026).

30
homes proposed
30
homes permitted
0
homes started on site
0
homes completed

completed · under construction · not started · 30 houses and 0 apartments permitted

Quarter by quarter
QuarterPermittedUnder constructionCompletedCompleted share
Q3 2025000
Q4 20253000
Q1 20263000
Q2 20263000

The scheme

What the register says

Evara Developments Limited intend to apply for permission for development at this c. 0.85 Ha site in the townland of Doddsborough, Adamstown, Lucan, Co. Dublin. The site is generally bound: to the north by Adamstown Drive; to the east by lands subject to a live Application for Tandy's Lane Village Phase 3 Development (Reg. Ref. SDZ24A/0034W) and part of an access road (to form part of Tandy's Avenue) which is currently under construction (permitted under Tandy's Lane Village Phase 1 Development (Reg. Ref. SDZ19A/0011, as amended under Reg. Refs. SDZ21A/0008 & SDZ21A/0011) and also included within the Tandy's Lane Village Phase 2 Development (Reg. Ref. SDZ22A/0006, as amended under Reg. Ref. SDZ23A/0006) and the live Application for Tandy's Lane Village Phase 3 Development); to the south by part of an access road (to form part of Tandy's Row) which is currently under construction (permitted under Tandy's Lane Village Phase 2 Development); and to the west by part of an access road (to form part of Tandy's Glen) which is currently under construction (permitted under Tandy's Lane Village Phase 2 Development). This application is being made in accordance with the Adamstown Planning Scheme 2014 (as amended) and relates to Phase 4 of development within the Tandy's Lane Village Development Area of the Adamstown Strategic Development Zone. The development also includes amendments to the permitted Phase 2 Development within the Tandy's Lane Village Development Area (Reg. Ref. SDZ22A/0006, as amended under Reg. Ref. SDZ23A/0006). The proposed development will principally consist of the construction of 30 No. dwellings including 7 No. 2-bed units, 7 No. 3-bed units and 16 No. 4-bed units. The development will range in height between part 1 No. to 3 No. storeys. The development will also include: foul and surface water drainage connections; amendments to the landscaping and footpaths permitted to the east, south and west of the site and to the car parking layout to the west of the site permitted in Tandy's Lane Village Phase 2 Development; 52 No. car parking spaces; ESB substation; hard and soft landscaping; boundary treatments; public lighting; and all associated site and development works above and below ground

Summary from the register record.

Planning timeline 5 steps

  • 29 Sept 2025
    Application lodged — DZ
  • 24 Oct 2025
    Council decision — Grant
  • 24 Oct 2025
    Final approval
  • 15 May 2026
    Building started
  • 7 Dec 2030
    Approval runs out (estimate)

The site 8,707 m²

Boundary of Doddsborough as the Dublin councils map it in the housing pipeline.

Planning applications inside the site 8 applications in the last 10 years

Appeals inside the site 1 with An Coimisiún Pleanála

Building work started inside the site 1 commencement notice

Other big developments nearby within 2 km

Everything within 1 km on the map →

Something wrong on this scheme page, or a record you want corrected or removed? Contact us and we will check it against the source.