Dublin City Council · 2683/21 · Permission

Glenavon House

52 apartments6 storeysGlenavon Developments LimitedGlasnevin, Dublin City Council

44 under construction of 52 permitted homes (Q2 2026).

Also known as 46 Ballymun Road.

  1. 9 Mar 2022Approved
  2. 1 Apr 2022Appealed
  3. 17 Feb 2023Building started
  4. 21 Jul 2023Appeal: Approved with conditions
  5. 21 Jul 2023Final approval
  6. 19 Sept 2024Signed off
Status
Building started
Decision
Approved · 9 Mar 2022
Size
52 apartments · up to 6 storeys
Uses
residential, apartments
Applicant
Glenavon Developments Limited
Site
3,877 m²
Appeal
ACP 313193 · Approved with conditions

Building progress councils’ figures, Q2 2026

  1. 2023Approved
  2. 2023Building started
  3. 2024First homes signed off1 sign-off

44 under construction of 52 permitted homes (Q2 2026).

52
homes proposed
52
homes permitted
44
homes started on site
0
homes completed

completed · under construction · not started · 0 houses and 52 apartments permitted

Quarter by quarter
QuarterPermittedUnder constructionCompletedCompleted share
Q2 202552440
Q3 202552440
Q4 202552440
Q1 202652440
Q2 202652440

The scheme

Glenavon Developments Limited proposes the construction of a 5 to 6 storey apartment building at Glenavon House, 46 Ballymun Road, Glasnevin. The project involves the demolition of the existing house and outbuildings to accommodate 52 residential units. The development includes associated site works, basement parking, and landscaping.

it involves the construction of 52 residential units

What the register says

Permission for development at a site (c.039Ha) at Glenavon House, 46 Ballymun Road, Glasnevin, Dublin 9. The subject site is generally bounded to the west by Ballymun Road and Clonmore Court apartments, to the north by Glenavon Court and Hillcrest Court apartments, to the east by the rear gardens of houses on St. Mobhi Road, and to the south by Mobhi Court apartments and houses at The Haven. The development will consist of the construction of a 5 to 6 storey apartment building (total GFA c.5,330 sqm excluding car park), partially over basement, accommodating 52 no. residential units (13 no. 1-bed apartments, 9 no. 2-bed apartments, 17 no. 2-bed duplex apartments, 8 no. 3-bed apartments and 5 no. 3-bed duplex apartments), all with private balconies on the east or west elevation. And, all associated and ancillary site development, landscaping and boundary treatment works, including: Demolition of existing habitable house and ancillary outbuildings. Modification of existing vehicular and pedestrian site entrance to Ballymun Road. 1 no. car share space at surface level. 37 no. car parking spaces at basement. 80 no. bicycle parking spaces. ESB substation and switch room. Solar panels and green roof

Summary from the register record.

Planning timeline 7 steps

  • 28 Apr 2021
    Application lodged — Standard
  • 9 Mar 2022
    Council decision — Grant
  • 1 Apr 2022
    Appealed to An Coimisiún Pleanála — ABP-313193-22
  • 21 Jul 2023
    Commission decision — Granted
  • 21 Jul 2023
    Final approval
  • 18 Apr 2024
    Building started
  • 3 Sept 2028
    Approval runs out (estimate)

The site 3,877 m²

Boundary of Glenavon House as the Dublin councils map it in the housing pipeline.

Planning applications inside the site 1 application in the last 10 years

Appeals inside the site 2 with An Coimisiún Pleanála

Building work started inside the site 2 commencement notices