Dún Laoghaire-Rathdown County Council · D18A/0551/E · Standard

Grounds and Dwellings Ards & Cartref

72 homesCabinteely, Dún Laoghaire-Rathdown County Council

All 72 permitted homes are built (Q2 2026).

Building progress councils’ figures, Q2 2026

All 72 permitted homes are built (Q2 2026).

72
homes proposed
72
homes permitted
72
homes started on site
72
homes completed

completed · under construction · not started · 26 houses and 46 apartments permitted

Quarter by quarter
QuarterPermittedUnder constructionCompletedCompleted share
Q2 202572610
Q3 202572610
Q4 202572720
Q1 2026725715
Q2 202672072
Status
Completed · activity on site: completed
Decision
Approved · 4 Jul 2019
Size
72 homes
Site
1.47 ha
Commission case
ABP-303675-19 · Approved

The site 1.47 ha

Boundary of Grounds and Dwellings Ards & Cartref as the Dublin councils map it in the housing pipeline.

Planning applications inside the site 2 applications in the last 10 years

Appeals inside the site 6 with An Coimisiún Pleanála

Building work started inside the site 1 commencement notice

  • CommencedBray Road, Cabinteely, Dún Laoghaire-Rathdownnotice 4 Mar 2024 · Dún Laoghaire-Rathdown County Council

Planning timeline 8 steps

  • 8 Jun 2018
    Application lodged — Standard
  • 11 Jan 2019
    Council decision — Grant
  • 12 Feb 2019
    Appealed to An Coimisiún Pleanála — ABP-303675-19
  • 4 Jul 2019
    Commission decision — Granted
  • 4 Jul 2019
    Final approval
  • Q1 2024
    Building started
  • Q2 2026
    Site completed — Site completed
  • 11 Oct 2029
    Approval runs out (estimate)

Other big developments nearby within 2 km

Free

Living near Grounds and Dwellings Ards & Cartref?

Its progress and every other plan around it.

Something wrong on this scheme page, or a record you want corrected or removed? Contact us and we will check it against the source.