Building: 256 finished of 263 homes (Q2 2026).

Donabate, Fingal County Council

How the homes are counted263 permitted · 258 applied for
  • 263 homes permitted (the Dublin councils' housing pipeline, Q2 2026).
  • 258 homes applied for (the Dublin councils' housing pipeline, Q2 2026).

Building progress councils’ figures, Q2 2026

263
homes permitted
256
homes started on site
256
homes completed

completed · under construction · not started · 186 houses and 77 apartments permitted

Quarter by quarter
QuarterPermittedUnder constructionCompletedCompleted share
Q2 20252630178
Q3 20252630179
Q4 20252630256
Q1 20262630256
Q2 20262630256
Source and licence
Status
Building started
Decision
Approved · 1 Dec 2022
Site
2.96 ha

The site 2.96 ha

Boundary of Hearse Road as the Dublin councils map it in the housing pipeline.

Planning applications inside the site 4 applications in the last 10 years

Appeals inside the site 2 with An Coimisiún Pleanála
Commencement notices inside the site 1
  • CommencedThe Avenue, Donabate, Fingal, K36 A0P6notice 5 Nov 2025 · Fingal County Council

Planning timeline 5 steps

  • 7 Oct 2022
    Application lodged — Standard
  • 1 Dec 2022
    Council decision — Grant
  • 1 Dec 2022
    Final approval
  • 25 Apr 2024
    Approval runs out (estimate)
  • Q2 2025
    Building started

Other big developments nearby within 2 km

  • Corballis East · first homes signed off 2026 · 119 m away
  • Main Street · building started 2026 · 263 m away
  • The Gallery · first homes signed off 2026 · 500 m away
  • existing · first homes signed off 2026 · 500 m away
  • Ballymastone · first homes signed off 2025 · 742 m away
  • New Road · withdrawn or invalid · 884 m away

Living near Hearse Road?

Its progress and every other plan around it.

Something wrong on this scheme page, or a record you want corrected or removed? Contact us and we will check it against the source.