Fingal County Council · F17A/0556 · Standard
Innishannon
30 homesPortmarnock, Fingal County Council
All 30 permitted homes are built (Q3 2025).
Building progress councils’ figures, Q3 2025
All 30 permitted homes are built (Q3 2025).
30
homes proposed
30
homes permitted
30
homes started on site
30
homes completed
completed · under construction · not started · 30 houses and 0 apartments permitted
Quarter by quarter
| Quarter | Permitted | Under construction | Completed | Completed share |
|---|---|---|---|---|
| Q2 2025 | 30 | 0 | 30 | |
| Q3 2025 | 30 | 0 | 30 |
- Status
- Completed · activity on site: completed
- Decision
- Approved · 22 Jan 2019
- Size
- 30 homes
- Site
- 1.49 ha
- Commission case
- ABP-301635-18 · Approved
The site 1.49 ha
Boundary of Innishannon as the Dublin councils map it in the housing pipeline.
Planning applications inside the site 10 applications in the last 10 years
- Appeal decidedBalford & Dubh Laoch, Drumnigh Road, Portmarnock, Co. Dublin, D13 EX17
- GrantedBalford & Dubhlaoch, Drumnigh Road, Portmarnock, Co. Dublin.
- WithdrawnBalford & Dubhlaoch, Drumingh Road, Portmarnock, Co. Dublin
- GrantedDunkeld, Drumnigh Road, Portmarnock, Co. Dublin, D13 CT95
- WithdrawnDunkeld, Drumnigh Road, Portmarnock, Co. Dublin, D13 CT95
- WithdrawnDunkeld, Drumnigh Road, Old Portmarnock, D13CT95
- CommencedBaldford D13X17 & Dubhlaoch D13YW9, Drumnigh Road, Portmarnock, Co.Dub
- RefusedDunkeld, Drumnigh Road, Portmarnock, Co. Dublin, D13 CT95
Appeals inside the site 4 with An Coimisiún Pleanála
- RefusedBalford & Dubh Laoch, Drumnigh Road, Portmarnock, Co. Dublin, D13 EX17
- Granted with conditionsBaldford, D13 EX17 & Dubhlaoch, D13 YW96, Drumnigh Road, Portmarnock, Co. Dublin.
- Under appealLocated off the coast of Counties Dublin, Meath and Louth
- Granted with conditions3 Drumnigh Wood, Drumnigh, Portmarnock, Co. Dublin.
Building work started inside the site 1 commencement notice
Planning timeline 8 steps
- 11 Sept 2017Application lodged — Standard
- 20 Apr 2018Council decision — Grant
- 14 May 2018Appealed to An Coimisiún Pleanála — ABP-301635-18
- 22 Jan 2019Commission decision — Granted
- 22 Jan 2019Final approval
- Q1 2024Building started
- 22 Jan 2024Approval runs out (estimate)
- Q2 2025Site completed — Site completed
Other big developments nearby within 2 km
- Station Road · 461 m away
- Townlands Drumnigh · 470 m away
- Maynetown & Drumnigh · 471 m away
- Maynetown Phase 1E · 195 homes · 767 m away
- at this site (c. 8.13 Ha) generally bounded by the existing · 769 m away
- Teagasc Research Centre · 1.1 km away
- Auburn House · 1.4 km away
- GA3 Lands at Baldoyle · 1.4 km away