Folkstown Park, Balbriggan
70 homesGlenveagh Homes LimitedFingal County Council
All 70 permitted homes are built (Q3 2025).
On the planning register as Ladywell (F21A/0055). 150 new homes have sold at Folkstown Park since 25 Nov 2024, at a median €378,855 on the Property Price Register (without VAT). Build progress, sales and land nearby on Buildable →
- 29 Oct 2021Approved
- 25 Nov 2021Appealed
- 13 Oct 2023Appeal: Approved with conditions
- 13 Oct 2023Final approval
- 7 Mar 2024Building started
- 22 Nov 2024Signed off
- Status
- Building started
- Decision
- Approved · 29 Oct 2021
- Size
- 70 homes
- Uses
- residential
- Applicant
- Glenveagh Homes Limited
- Site
- 8.35 ha
- Appeal
- ACP 312048 · Approved with conditions
Building progress councils’ figures, Q3 2025
- 2023Approved
- 2023Building started
- 2024First homes signed off14 sign-offs
All 70 permitted homes are built (Q3 2025).
completed · under construction · not started · 70 houses and 0 apartments permitted
Quarter by quarter
| Quarter | Permitted | Under construction | Completed | Completed share |
|---|---|---|---|---|
| Q2 2025 | 70 | 0 | 70 | |
| Q3 2025 | 70 | 0 | 70 |
The scheme
Glenveagh Homes Limited proposes the development of Phase 3A at the site known as Ladywell in the townlands of Clonard. The project includes the construction of 70 permitted residential units along with associated roads and services.
it involves the development of 70 residential units
What the register says
The development will consist of Phase 3A as well as roads, services an…
Cut short by the council feed. Full text ↗
Summary from the register record.
Planning timeline 8 steps
- 3 Feb 2021Application lodged — Standard
- 29 Oct 2021Council decision — Grant
- 25 Nov 2021Appealed to An Coimisiún Pleanála — ABP-312048-21
- 13 Oct 2023Commission decision — Granted
- 13 Oct 2023Final approval
- 7 Mar 2024Building started
- Q2 2025Site completed — Site completed
- 10 Mar 2027Approval runs out (estimate)
The site 5.96 ha
Boundary of Folkstown Park, Balbriggan as the Dublin councils map it in the housing pipeline.
Planning applications inside the site 9 applications in the last 10 years
- Commencedat this site to the south of Flemington Lane,, within the townlands of
- CommencedWithin the townlands of ‘Clonard or Folkstown Great’ and ‘Clogheder’,
- Appeal decidedLands off Flemington Lane, Balbriggan, Co. Dublin
- Granted(On lands of c. 6.29 ha.) relating to: 'Phase 3' to be known as 'Ladyw
- CommencedPhase 3 to be known as 'Ladywell' within the townlands of Clonard or F
- CommencedPhase 3 to be known as 'Ladywell' within the townlands of Clonard or F
- CommencedLands at Taylor Hill, off the Naul Road, Balbriggan, Co Dublin
- CommencedLands off the Naul Road, Balbriggan, Co Dublin, Located North-West of
Appeals inside the site 13 with An Coimisiún Pleanála
- Withdrawnat this site to the south of Flemington Lane,, within the townlands of ?Clonard or Folkstown Great?, and ?Flemingtown?,, Balbriggan, Co. Dublin
- Granted with conditionsWithin the townlands of Clonard or Folkstown Great and Clogheder, Balbriggan, Co. Dublin
- OtherFlemington Lane, Balbriggan, Co. Dublin
- OtherStephenstown, Balbriggan, Co. Dublin
- OtherStephenstown, Balbriggan, Co. Dublin.
- Granted with conditionsLands off Flemington Lane, Balbriggan, Co. Dublin (flemingtonlaneLRD.ie)
- OtherStephenstown, Balbriggan, Co. Dublin
- OtherLands at Darcytown, Balrothery, Co. Dublin
- OtherLands off Flemington Lane, Balbriggan, Co. Dublin
- OtherStephenstown, Balbriggan, Co. Dublin
- OtherStephenstown, Balbriggan, Co. Dublin.
- Granted with conditions'Ladywell' within the townlands of Clonard or Folkstown Great, Clogheder & Flemington, Balbriggan, Co. Dublin
- RefusedBalbriggan, Co. Dublin.
Building work started inside the site 6 commencement notices
- CommencedWithin the townlands of ‘Clonard or Folkstown Great’ and ‘Clogheder’,
- CommencedPhase 3 to be known as 'Ladywell' within the townlands of Clonard or F
- CommencedPhase 3 to be known as 'Ladywell' within the townlands of Clonard or F
- CommencedPhase 3 to be known as 'Ladywell' within the townlands of Clonard or F
- CommencedPhase 3 to be known as 'Ladywell' within the townlands of Clonard or F
- CommencedPhase 3 to be known as 'Ladywell' within the townlands of Clonard or F
Other big developments nearby within 2 km
- Clonard or Folkstown Great and Clogheder · 197 homes · 122 m away
- Flemington Lane Development · 815 homes · 197 m away
- Lands off Flemington Lane · 218 m away
- Clogheder and Tankardstown · 553 m away
- Flemington Lane · 897 m away
- Bremore and Flemington · 1.0 km away
- Drogheda Road Development · 74 homes · 1.5 km away
- Quay Street & High Street · 1.9 km away
Something wrong on this scheme page, or a record you want corrected or removed? Contact us and we will check it against the source.