PlanningRegister.ie
Dún Laoghaire-Rathdown County Council · D18A/0418 · Standard

Lands at

36 homesDalkey, Dún Laoghaire-Rathdown County Council

All 36 permitted homes are built (Q4 2025).

Building progress councils’ figures, Q4 2025

All 36 permitted homes are built (Q4 2025).

36
homes proposed
36
homes permitted
36
homes started on site
36
homes completed

completed · under construction · not started · 13 houses and 23 apartments permitted

Quarter by quarter
QuarterPermittedUnder constructionCompletedCompleted share
Q2 202536360
Q3 2025362313
Q4 202536036
Status
Completed · activity on site: completed
Decision
Approved · 1 Jul 2019
Size
36 homes
Site
9,469 m²
Commission case
ABP-303725-19 · Approved

The site 9,469 m²

Boundary of Lands at as the Dublin councils map it in the housing pipeline.

Planning applications inside the site 8 applications in the last 10 years

Appeals inside the site 1 with An Coimisiún Pleanála

Building work started inside the site 4 commencement notices

Planning timeline 8 steps

  • 4 May 2018
    Application lodged — Standard
  • 11 Jan 2019
    Council decision — Grant
  • 3 Feb 2019
    Appealed to An Coimisiún Pleanála — ABP-303725-19
  • 1 Jul 2019
    Commission decision — Granted
  • 25 Jul 2019
    Final approval
  • Q4 2023
    Building started
  • Q4 2025
    Site completed — Site completed
  • 2 Nov 2026
    Approval runs out (estimate)

Other big developments nearby within 2 km

Free

Living near Lands at?

Its progress and every other plan around it.

Something wrong on this scheme page, or a record you want corrected or removed? Contact us and we will check it against the source.