Dublin City Council · 3978/24 · Permission

Lighting & Electrical Distribution Group Ltd Factory Complex

50 homesWalkinstown, Dublin City Council

Approved Oct 2024; building started Nov 2025.

  1. 8 Jul 2024Received
  2. 30 Aug 2024Approved
  3. 15 Oct 2024Final approval
  4. 3 Nov 2025Building started
Status
Building started
Decision
Approved · 30 Aug 2024
Size
50 homes
Site
3,784 m²

Building progress councils’ figures, Q4 2025

  1. 2024Approved
  2. 2025Building started
  3. Not yetFirst homes signed off

7 homes proposed; none permitted yet (Q4 2025).

7
homes proposed
0
homes permitted
0
homes started on site
0
homes completed

completed · under construction · not started · 0 houses and 0 apartments permitted

Quarter by quarter
QuarterPermittedUnder constructionCompletedCompleted share
Q2 2025700
Q3 2025700
Q4 2025000

The scheme

What the register says

The proposed development comprises the following: Alterations to previously approved development granted under Reg. Ref. 3302/21 comprising: (i) reinstatement and revised layout of first floor on the southern block and part of 1st floor on the western block (which were previously omitted by condition) to provide for an additional 7 no. units. This will result in an increase from 43 no. to 50 no. units; (ii) revisions to the approved floor plan, including balconies, of 2nd floor on the southern block; (iii) alterations to external material finish and fenestration to façades of the apartment building; (iv) all associated site works necessary to facilitate the development

Summary from the register record.

Planning timeline 5 steps

  • 8 Jul 2024
    Application lodged — Standard
  • 30 Aug 2024
    Council decision — Grant
  • 15 Oct 2024
    Final approval
  • 3 Nov 2025
    Building started
  • 28 Nov 2029
    Approval runs out (estimate)

The site 3,784 m²

Boundary of Lighting & Electrical Distribution Group Ltd Factory Complex as the Dublin councils map it in the housing pipeline.

Planning applications inside the site 3 applications in the last 10 years

Appeals inside the site 1 with An Coimisiún Pleanála

Building work started inside the site 1 commencement notice

Other big developments nearby within 2 km

Everything within 1 km on the map →

Something wrong on this scheme page, or a record you want corrected or removed? Contact us and we will check it against the source.