Building: all 29 apartments are under construction (Q2 2026).

6 storeysPelletstown, Dublin City Council

Email me when the next phase is lodged

Status
Building started
Decision
Approved · 2 Dec 2024
Height
up to 6 storeys
Uses
residential, apartments, retail
Site
2,097 m²

Building progress councils’ figures, Q2 2026

  1. 2025Approved
  2. 2024Building started
  3. Not yetFirst homes signed off
29
homes permitted
29
homes started on site
0
homes completed

completed · under construction · not started · 0 houses and 29 apartments permitted

Quarter by quarter
QuarterPermittedUnder constructionCompletedCompleted share
Q2 202529290
Q3 202529290
Q4 202529290
Q1 202629290
Q2 202629290
Source and licence

The scheme

The development involves a change of use from office to residential at Meridian Court in Royal Canal Park, Dublin 15. It provides 29 apartments across the first to sixth floors of an existing building. The project includes facade modifications, refurbishment of a central courtyard, and the provision of bicycle parking and waste storage.

What the register says

The development will consist of change of use from office to residential use to provide 29 no. apartments (7 no. 1-bed, 16 no. 2-bed and 6 no. 3-bed units), accommodated on the 1st to 6th floors of existing vacant space over an existing vacant ground floor retail unit in a mixed-use building known as Meridian Court. Associated bicycle parking, waste storage and plant rooms will be provided in an existing single storey shared basement. The development includes refurbishment to the exiting shared central courtyard space. All apartment units to have new private balconies or terraces, locate on south, east and west building elevations. The development will include modifications to exiting facades with existing openings resized, partial recladding, additional balconies added and an overall reduction of window area. The existing ground floor retail unit will remain unchanged

Summary from the register record.

Planning timeline 5 steps
  • 18 Jun 2024
    Application lodged — Standard
  • Q4 2024
    Building started
  • 2 Dec 2024
    Council decision — Grant
  • 31 Jan 2025
    Final approval
  • 16 Mar 2030
    Approval runs out (estimate)

The site 2,097 m²

Boundary of Meridian Court as the Dublin councils map it in the housing pipeline.

Planning applications inside the site 4 applications in the last 10 years

Appeals inside the site 5 with An Coimisiún Pleanála
Commencement notices inside the site 1

Other big developments nearby within 2 km

Everything within 1 km on the map →

Something wrong on this scheme page, or a record you want corrected or removed? Contact us and we will check it against the source.