South Dublin County Council · LRD23A/0011 · Permission

Taobh Chnoic Phase 2B

131 homes3 storeysCairn Homes Properties LimitedNewcastle, South Dublin County Council

80 built, 44 under construction of 124 permitted homes (Q2 2026).

Also known as Newcastle South.

  1. 20 Oct 2023Received
  2. 19 Mar 2024Approved
  3. 11 Apr 2024Appealed
  4. 31 Jul 2024Appeal: Approved with conditions
  5. 20 Dec 2024Building started
  6. 2 Dec 2025Signed off
Status
Building started
Decision
Approved · 19 Mar 2024
Size
131 homes · up to 3 storeys
Uses
residential, houses, apartments
Applicant
Cairn Homes Properties Limited
Site
11.16 ha
Appeal
ACP 319500 · Approved with conditions

Building progress councils’ figures, Q2 2026

  1. 2024Approved
  2. 2024Building started
  3. 2025First homes signed off1 sign-off

80 built, 44 under construction of 124 permitted homes (Q2 2026).

124
homes permitted
124
homes started on site
80
homes completed

completed · under construction · not started · 118 houses and 6 apartments permitted

Quarter by quarter
QuarterPermittedUnder constructionCompletedCompleted share
Q2 20251241100
Q3 20251241240
Q4 20251248539
Q1 20261244480
Q2 20261244480

The scheme

Cairn Homes Properties Limited proposes the construction of 131 dwellings in the townland of Newcastle South. The development includes 119 two-storey houses and 12 apartments or duplex apartments in a three-storey building. The project also features open space, infrastructure upgrades, and new vehicle access from the Athgoe Road.

it represents the second phase of a large residential development

What the register says

The proposal comprises the 2nd phase (phase 2B) of a 2 phase development (first phase [phase2A] under planning reg. ref SD23A/0136 will comprise 48 no. duplex dwellings and phase 2 of Taobh Chnoic public park of c.1.74 hectares of open space, along with car parking and ancillary infrastructure) to result in an overall Phase 2 development of 179 no. dwellings (consisting of 119 no. 2 storey houses and 60 no apartments / duplex apartments in 5 no. 3 storey duplex buildings, and ancillary infrastructure). The phase 2B development will consist of the construction of 131 no. dwellings and open space as follows: A) 119 no. 2 storey houses (10 no. 2 bedroom houses, 95 no. 3 bedroom houses, 13 no. 4 bedroom houses and 1 no. 5 bedroom house. B) 12 no. apartments / duplex apartments in 1 no. 3 storey building - (6 no. 2 bedroom apartments and 6 no. 3 bedroom duplex apartments) all with terrace. C) Open space (c. 1.34 ha. in a series of open space areas) hard and soft landscaping (including public lighting & boundary treatment), communal open space for duplex apartments and apartments; along with single storey bicycle/bin stores and ESB substations; D) Vehicle access from the Athgoe Road from a new signalised junction along with upgrades to footpath and pedestrian crossing (on the Athgoe Road) as well as provision of vehicular/pedestrian/cycle link to permitted 'Graydon' (TA06S.305343) 'Newcastle Boulevard' to the East as well as 237 no car parking spaces and 94 no. bicycle spaces (4 no. motorcycle space) and all internal roads, cycleways, green routes and paths. E) Provision of surface water attenuation SuDs measures connection to water supply and provision of foul drainage infrastructure as well as an underground local pumping station (in northern pa rt of site) to Irish Water specifications and all ancillary site development / construction / landscaping works. F) The proposal also includes upgrades (to provide surface water pipe upgrades) to the surface water network along Athgoe Road and Hazelhatch Road (for c. 1.2 km)

Summary from the register record.

Planning timeline 7 steps

  • 20 Oct 2023
    Application lodged — LRD
  • 19 Mar 2024
    Council decision — Grant
  • 11 Apr 2024
    Appealed to An Coimisiún Pleanála — ABP-319500-24
  • 31 Jul 2024
    Commission decision — Granted
  • 20 Dec 2024
    Building started
  • 20 Jan 2025
    Final approval
  • 5 Mar 2030
    Approval runs out (estimate)

The site 11.16 ha

Boundary of Taobh Chnoic Phase 2B as the Dublin councils map it in the housing pipeline.

Planning applications inside the site 20 applications in the last 10 years

Show 12 more

Appeals inside the site 10 with An Coimisiún Pleanála

Building work started inside the site 5 commencement notices